California Department of Transportation
 

Contract 06-0L2305(06A1579)

The responses to bidder's inquiries, unless incorporated into a formal addendem to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.


Q1) Ref Bid Item 6 and Special Provision Section 10-1.02- The work of this contract, installing approximately 630 feet of guard rail and end treatments will take a qualified contractor 1 or 2 days to perform. Why is the State wasting money and time to require a biologist?? Suggest this item be deleted by addendum.

A1) Please bid per the Contract Documents.


Q2) Ref the signature page of the Special Provisions- Is this an awardable Contract without having the signature of at least one registered engineer?

A2) Submitted for Consideration.