The responses to bidder's inquiries, unless incorporated into a formal addendem to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.

Q1) Are the locations for Item 12 "Spot Blast Clean and Paint Undercoating" marked out on the existing bridge?

A1) No, the spot blasting is not marked out on Bridge. The SSPs on page 12 reflect the total anticipated quantity of spot blasting per bridge site.


Q2) Will Caltrans remove and replace the chain link fence, so that the Contractor has access to prepare and paint the steel?

A2) Please bid per contract document.


Q3) Does Caltrans expect that the Contrator will remove and replace the chain link fence, so that the Contractor has access to prepare and paint the steel?

A3) Please bid per contract document.