California Department of Transportation
 

Contract 05-0S1404

The responses to bidder's inquiries, unless incorporated into a formal addendem to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.


Q1) Currently, Bid Item #12 specifies HMA Type A 3/8" for the Overlay portion. Given the distance from the project to the nearest HMA plants, would Caltrans consider to change the specifications to Warm Mix Asphalt? As currently specified, the delivered temperatures of the HMA Type A 3/8" could be a problem.

A1) Bid in accordance with the current contract plans and documents. 10Mar10


Q2) Xxxxx?

A2) Xxxxx.


Q3) Xxxxx?

A3) Xxxxx.