Contract 05-0Q6604

The responses to bidder's inquiries, unless incorporated into a formal addendem to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.


Q1) We purchased the plans for project 05-0Q6904 and do not understand why this job has 120 days to perform the work based on comparing the bid items. On the major items of work Contract 05-0Q6904 has 14% of the Roadway Excavation called out in O5-0Q6604, no class II Base, 40% of the Asphalt Concrete, and only 35% more concrete barrier. Why does 05-0Q6604 only have half the days project 05-0Q6904 has?

A1)Total length of project, drainage requirements, and considerations for Northbound and Southbound alignments and traffic were all factors in the working day calculations for 05-0Q6604 and 05-0Q6904.