California Department of Transportation
 

Contract 10-1G340(10A1940)

The responses to bidder's inquiries, unless incorporated into a formal addendem to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.

Inquiry 1.) : When are Award and NTP Anticipated?

Response 1.) The Award usually happens within 1-2 weeks after bid opens but can be dependent on bid review by DPAC.

Inquiry 2.) Is the project to be built in 2017 or 2018?

Response 2.) Caltrans would like the project to be built in 2017 but this is dependent on execution of contract from DPAC, then the prep time to order materials, and weather conditions at the time materials are ready.