The responses to bidder's inquiries, unless incorporated into a formal addendem to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.


Q1) Will this project be postponed until May like the projects in the are have been?

A1) Please refer to Addendum No. 1 dated April 1, 2010. Bids for this work will be opened on Tuesday, May 11, 2010, instead of the original date of Wednesday, April 7, 2010. 2Apr10


Q2) Addendum 2 stated that there would be an optional prebid site meeting at 10:00 AM on May 4, 2010, for this project. There were several contractors there, and why weren't any representatives from CAL-TRANS there to answer questions?

A2) Per the addendum, the purpose of the meeting was to provide access to the job site. An escort was not needed as the job site was open to public.