Contract 10-0S5304

The responses to bidder's inquiries, unless incorporated into a formal addendem to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.


Q1) The quantities on striping installation seem to be significantly off. The total quantity shows 99,947 LF, but when you add up the various details, it adds up to 148,523 LF. The bid item calls for 100,000 LF. Please advise.

A1) No additional information will be provided. If changes are necessary, they will be handled by proposed Contract Change Order. 4May10.


Q2) The quantities for stripe removal appear to be incorrect. Per section 15-2.06 of the standard specs, when 8" stripe is to be removed, the quantity is doubled for measurement purposes. I believe the quantity should read 2960 LF. Please advise.

A2) No additional information will be provided. If changes are necessary, they will be handled by proposed Contract Change Order. 4May10.