The responses to bidder's inquiries, unless incorporated into a formal addendem to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The availability or use of information provided in the responses to bidder's inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.

Q) Note 10 on plan E-2 indicates flashing beacons are to be mounted on 1A pole with W3-3 sign. Plan PDD-1 Roadside Sign schedule indicates W3-3 signs are to be mounted on wood posts. Which is correct?

A) Bid in accordance with the plans and specifications. If changes are necessary, they will be handled by proposed contract change order, in accordance with Section 4-1.03 of the Standard Specifications.