Caltrans District 4
March 8, 2001
FOR IMMEDIATE RELEASE CONTACT:
Lauren E. Wonder/ (408)232-0228
uu
TRAFFIC ADVISORYuu
Beginning at 5 AM tomorrow, March 9, crews will close the off-ramp to McCarthy
Boulevard from southbound Interstate 880 in order to pour the concrete deck for
a connector being constructed as part of the 237/880 interchange improvement
project. Motorists accessing McCarthy Boulevard may use the next exit to Ranch
Drive/McCarthy Boulevard from westbound Route 237.
The off-ramp is scheduled to open at 6 PM tomorrow. All work is subject to good weather conditions.
The connector being constructed will create a direct connection for motorists traveling on southbound 880 to westbound 237. It’s scheduled to open in early summer 2001.
The 237/880 interchange improvement project is scheduled to be completed around May 2002.