Caltrans > Dist4 Internet > Dist4 Construction > Contract Inquiries > EA 04-3S6004 Inquiries |
CONTRACTOR'S INQUIRY RESPONSES
September 9, 2008
CONTRACT NO. 04-3S6004
REMOVE SLIDE AND REGRADE SLOPES
County Route: NAP-29-38.8/38.8NAP-29-42.6/42.6
The responses to contractors' inquiries, unless incorporated into a formal addenda to the contract, are not a part of the contract and are provided for the contractor's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The responses may be considered along with all other information furnished to prospective bidders for the purpose of bidding on the project. The availability or use of information provided in the responses to contractors' inquiries is not to be construed in any way as a waiver of the provisions of section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given, and any such subsequent response or addenda should be taken into consideration when submitting a bid for the project. Inquiries submitted within seventy-two (72 ) hours of the bid opening date might not be addressed.
The Caltrans District 4 Office is located at 111 Grand Avenue, Oakland, CA 94612. Send Contractor Inquiries via email to the Duty Senior at Duty_Senior_District04@dot.ca.gov. The mailing address is P.O. Box 23660, Oakland, CA 94623-0660. The Duty Senior's telephone number is (510) 286-5209 and the fax number is (510) 622-1805. All inquiries must include the contract number.
| Inquiry No. | Inquiry | Response |
|
1.0 |
In review of the above contract number, the question I have has to do with construction access to the top of the cut slope. Can we/are we able to clear an access within the PSE to cut the key trench and install the upper rock bolts, or is all access from street level only? | Submitted for consideration. |