The Caldecott Tunnel Schedule News

Targeted Schedule

2004/2005 Perform Environmental and Engineering Studies
May 12 – July 31, 2006 Public Circulation of the Draft Environmental Document
June 7 & 15, 2006 Hold Public Hearing on Draft Environmental Document
Summer 2007 Release Final Environmental Document and Receive Project Approval
Winter 2008-2009 Perform Final Design | Acquire Right-of-Way
Summer 2009 Begin Construction
2013-2014 Complete Construction – Tunnel Open for Service


Funding

Funding identified for the Caldecott Improvement Project includes $20 million allocated from the state Transportation Congestion Relief Program (TCRP), $18 million from the State Transportation Improvement Program-Interregional Improvement Program (STIP-IIP), and $31 million from the State Transportation Improvement Program-Regional Improvement Program (STIP-RIP). In addition, $50 million will be generated from Regional Measure 2* and $125 million will be generated from Contra Costa County Measure J**. $1.6 million will come from other federal funds and $175 million will come from the Cash Management Improvement Act (CMIA). Current funds total approximately $420 million and the project is fully funded.

*In March 2004, Bay Area voters approved Regional Measure 2, raising the toll on the nine State-owned toll bridges in the San Francisco Bay Area by $1.00, thereby generating funds for regional transportation projects including $50 million for construction of the fourth Caldecott Tunnel bore.

**In November 2004, voters in Contra Costa County passed Measure J, a half-cent sales tax to pay for specific transportation projects. Measure J will generate $125 million for construction of the Caldecott Tunnel fourth bore.

Caltrans logo & Caldecott Improvement Project logo