Description
Replace northbound structure of the Butte Creek Bridge.
Project Benefits
This project upgrades the northbound crossing over Butte Creek and ensures future mobility for motorists on Highway 99 in Butte County.
Funding Breakdown
Local - N/A
State - $10 million
Federal -N/A
Estimated Total Project Cost - $10 million
Project Schedule
Environmental Document Completed -- October 2010
Right of Way Acquisition Completed --June 2012
Design Completed -- June 2012
Advertise -- September 2012
Begin Construction -- April 2013
Expected Construction -- October 2015
Partnership
Caltrans, Butte County Association of Governments (BCAG), City of Chico
Project Contact
John Holder, Project Manager (530) 741-5448 email: john_holder@dot.ca.gov
Gilbert Mohtes-Chan, Public Information Officer (530) 741-4571 email: gilbert_mohtes-chan@dot.ca.gov
Workshop 1 Tuesday, May 3, 2011 5:00 p.m. to 7:00 p.m. Belle Cooledge Library, Community Room 5600 South Land Park Drive, Sacramento |
Workshop 2 Wednesday, May 4, 2011 5:00 p.m. to 7:00 p.m. Joseph Sims Elementary School, Multipurpose Room 3033 Buckmaster Drive, Elk Grove |
Public Notice (
258Kb)
Yolo, and Sacramento Counties - (530) 741-5474
Nevada, Placer, and Sierra Counties - (530) 634-7640
El Dorado County or the Tahoe Basin - (530) 741-4566