California Department of Transportation - District 2
 

Various

   

VAR-VAR WORKER SAFETY (02-4E811)
Description: To widen, pave, and improve lighting at chain control areas
Project Manager: Steve Rogers
Construction is expected to begin in September 2014

   
   

VAR-VAR BRIDGE IMPROVEMENT (02-4F690)
Description: To replace PCC bridge rail end block and MBGR connections. Install new joint seals. Treat deck with methacrylate. Replace approach slabs, place polyester concrete overlay.
Project Manager: Lance Brown
Construction is expected to begin in June 2014

   
   

VAR-VAR FLUME CREEK MILL AND PLACE (02-4G160)
Description: To cold plane and replace asphalt and digouts
Project Manager: Lance Brown
Construction is estimated to begin in April 2014

   
    VAR-VAR 13/14 PAVEMENT MARKER JOB (02-4G200)
Description: To replace damaged pavement markers
Project Manager: Lance Brown
Construction is estimated to begin in June 2014