SR 99 Los Molinos Phase II
![]() |
This page will offer periodic updates on construction progress and alert the community to upcoming stages, which may impact the traveling public. For additional information, or If you would like to be alerted via e-mail when information is updated, please contact: |
Project Description
Phase 1 of the Los Molinos 99 Bond project introduced traffic calming elements along State Route (SR) 99 from Orange Street to Grant Street and established a storm drainage system. Construction of this project was completed in 2010.
Phase 2 of this project has started and will complete the storm drainage system constructed in Phase 1 by extending the outlet from the west end of Grant Street to Mill Slough.
Other work in phase 2 includes:
- Between Aramayo Way and Tehama-Vina, on the west side of SR 99:
- Widen highway shoulders to accommodate a bike lane and on-street parking.
- Add sidewalks, drainage, street lighting, landscaping and irrigation.
- Between Aramayo Way and Tehama-Vina, on the east side of SR 99:
- Widen highway shoulders to accommodate a standard shoulder with a bike lane.
- Between Grant Street and Aramayo Way, on the east side of SR 99:
- Widen highway shoulders to accommodate a bike lane and on-street parking.
- Add sidewalks, drainage, street lighting, landscaping and irrigation.
- Between Grant Street and Tehama-Vina Road:
- Place a 3’ wide colored-textured pavement section between the vehicle and bike lanes.
- Overlay the existing highway pavement and place several colored-textured pavement sections within the existing two-way left turn lane.
These enhancements have already been constructed between Orange Street and Grant Street as part of the Phase 1 project.
- Install lighting at the intersection of SR 99 and Tehama-Vina Road.
- Upgrade the existing 35-mph zone radar feedback signs to a bigger and brighter display.