California Department of Transportation District 11 ­ San Diego & Imperial Counties

District 11

Friday, April 23, 2010

Contact: Public Information Officer Hayden Manning

Phone: (619) 688-6670

Bridge Falsework Focus of SR-67 Construction

SAN DIEGO – Construction crews for the State Route 52 Sunny Side Gateway Project will start removing falsework on some of the bridge connections and building others.  Starting Sunday, April 25 through Thursday, April 29 southbound State Route 67 will close between Woodside and Prospect avenues from 9 p.m. to 5 a.m. An hour On earlier crews will close the southbound Magnolia Avenue on-ramp.

Beginning Tuesday at 11 p.m. Magnolia Avenue will close from Prospect Avenue to the Magnolia southbound on-ramp, according to the California Department of Transportation. This closure will also reopen at 5 a.m. for the remainder of the week.

Crews will place detour signs to assist motorists around the closures.

The SR-52 Sunny Side Gateway project is scheduled to be completed by spring 2011. 

For more information, please see the State Route 52 Sunny Side Gateway Project Brochure at www.dot.ca.gov/dist11/facts/SR-52brochure.pdf or contact the Caltrans Public Information Office at (619) 688-6670.

# # # #