State Route 76 West Construction Schedule


Stages


Stage One - (Completed)

Description: Construct a four-lane expressway grading for six-lanes on new alignment from I-5, at the Hill Street interchange, to Foussat Road in the City of Oceanside. Signalized intersections are planned at Loretta Street, Benet Road, Airport Road and Foussat Road.
Est. Begin/End Spring 1994/November 1995 (COMPLETED)
Est. Cost
: $10 million (C)* $27.6 million (R/W)


Stage Two - (Under Construction)

Description:
Construct a four-lane expressway grading for six-lanes primarily on new alignment from Foussat Road to North Santa Fe Avenue then conventional highway from North Santa Fe
Avenue to Jeffries Ranch Road in the City of Oceanside. Signalized intersections are planned at Douglass Drive, Rancho Del Oro Drive, Old Grove Road, Frazee Road, Towne Center North Drive, College Boulevard, North Santa Fe Avenue, Guajome Lake Road, and Melrose Drive.
Est. Begin/End:
Summer 1996/ December 1999 (COMPLETED
Est. Cost:
$45 million (C)* $35.4 million (R/W)



Estimated construction cost (C), including right of way (R/W): $118 million
*The 1993 construction cost estimate does not include environmental mitigation or engineering costs.