Date 09/25/00
Bids
Open 10/26/00
The responses to bidder' inquiries, unless incorporated into a formal addenda to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The responses may be considered along with all other information furnished to prospective bidders for the purpose of bidding on the project. The availability or use of information provided in the responses to bidder' inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.
Caltrans District 11 Construction Department
has developed this method of answering Bidders Inquiries to better serve
the needs of the Contractors who bid on our Projects.
The BIDDER'S INQUIRIES
& RESPONSES will be updated continuously with the last posting no later
than 15:00 on Wednesday prior to the bid opening.
Caltrans District 11 Construction Department
will post all of the questions submitted by any of the registered Planholders
for that Contract, but reserves the right not to answer any questions deemed
unsatisfactory for public viewing.
|
|
|
|
|
Inquiry |
|
|
Plan Sheet / Specification Reference=GENERATOR
ROOF PLAN
Is there complete section / elevation or detail plan of the roof penthouse, located above the generator room . Is this a prefabricated structure? If so who is the manufacturer?
|
|
|
Plan Sheet / Specification Reference=DETAIL
3 ST3-3
It appears that the existing concrete slab is cantilevered over the footing. Please clarify.
|
|
|
Plan Sheet / Specification Reference=
The truck ramp extension does not indicate the demolition of the existing wide flange, flush with the concrete. Please clarify.
|
|
|
Plan Sheet / Specification Reference=
The sump pump replacements are they to be equal like and kind as to the replacements in the existing bays. Please clarify.
|
|
|
Plan Sheet / Specification Reference=
The glass doors and store front system a manufacture is not specified? Are they to match the existing doors and store front system at the facility?
|