Existing
Escape ramp To Be Rehabilitated, Gravel Pit To Be Enlarged.
Advertise
Date 02/26/01
Bids
Open
03/29/01
The responses to
bidder' inquiries, unless incorporated into a formal addenda to the contract,
are not a part of the contract and are provided for the bidder's convenience
only. In some instances, the question and answer may represent a summary
of the matters discussed rather than a word-for-word recitation. The responses
may be considered along with all other information furnished to prospective
bidders for the purpose of bidding on the project. The availability or
use of information provided in the responses to bidder' inquiries is not
to be construed in any way as a waiver of the provisions of Section 2-1.03
of the Standard Specifications or any other provision of the contract,
the plans, Standard Specifications or Special Provisions, nor to excuse
the contractor from full compliance with those contract requirements. Bidders
are cautioned that subsequent responses or contract addenda may affect
or vary a response previously given.
Caltrans District 11 Construction Department
has developed this method of answering Bidder's Inquiries to better serve
the needs of the Contractors who bid on our Projects. Only when stated
in the Special Provisions will contracts have posted INQUIRIES AND RESPONSES.
The BIDDER'S INQUIRIES
& RESPONSES will be updated continuously and all attempts will be made
to do the final posting by 15:00 on Wednesday prior to the bid opening.
Caltrans District 11 Construction Department
will post all of the questions submitted by any of the contractors that
are registered Planholders for that Contract, but reserves the right to
not answer any questions deemed unsatisfactory for public viewing.
|
|
|
|
|
|
Inquiry |
|
|
Plan Sheet / Specification Reference=Plan
Sheet 2 of 10; TYPICAL CROSS SECTIONS X-1.
I would appreciate any information you could provide as to the type and size of any material below the existing sub grade of the Escape ramp. We are required to lower the existing grade by 1' (305 mm).
|
|
|
Plan Sheet / Specification Reference=ITEM
# 15 PEA GRAVEL, SECTION 10-1.22 PEA GRAVEL
The size of the material spec'd for pea gravel is not available locally, is that the correct size?
|
|
|
Plan Sheet / Specification Reference=TYPICAL
SECTION X-1 (sheet 2 of 10)
The typical section shows the recycled material replaced in the same location, and the entire depth to be pea gravel. Where is the new and where is the placement of the recycled?
|
|
|
|
|
|
|