| CONTRACT NO: | 11-234714 |
| ROUTE / KP | 11-SD-15-54./5.6 |
| LOCATION | In San Diego County In San Diego From 0.2 Km North Of Monroe Avenue To Adams Avenue Overcrossing. |
| DESCRIPTION | Highway Planting And Irrigation. |
| ESTIMATE | $ 2,004,000.00 |
| ADVERTISE DATE | 07/30/01 |
| BID OPENING | 08/30/01 |
| FINAL POSTING | 08/29/01 @ 15:30 |
|
|
TERRA-CAL CONSTRUCTION, INC. | $ 1,732,522.75 |
|
|
BELAIRE-WEST LANDSCAPE, INC. | $ 1,942,822.50 |
| 3 | VALLEY CREST | $ 1,958,737.00 |
The Caltrans District 11
Office is located at 2829 Juan Street, San Diego, CA 92110. The mailing
address is P.O. Box 85406, San Diego, CA 92186-5406. The District 11 Duty
Senior telephone number is (619) 688-6635. Please submit all inquiries
in the proper format by fax to (619) 688-6988 or e-mail to:
Duty_Senior_Const_District11@dot.ca.gov.
The responses to
bidder' inquiries, unless incorporated into a formal addenda to the contract,
are not a part of the contract and are provided for the bidder's convenience
only. In some instances, the question and answer may represent a summary
of the matters discussed rather than a word-for-word recitation. The responses
may be considered along with all other information furnished to prospective
bidders for the purpose of bidding on the project. The availability or
use of information provided in the responses to bidder' inquiries is not
to be construed in any way as a waiver of the provisions of Section 2-1.03
of the Standard Specifications or any other provision of the contract,
the plans, Standard Specifications or Special Provisions, nor to excuse
the contractor from full compliance with those contract requirements. Bidders
are cautioned that subsequent responses or contract addenda may affect
or vary a response previously given.
Caltrans District 11 Construction Department
has developed this method of answering Bidder's Inquiries to better serve
the needs of the Contractors who bid on our Projects. Caltrans District
11 Construction Department will post all of the questions submitted by
any of the contractors that are registered Planholders for that Contract,
but reserves the right to not answer any questions deemed unsatisfactory
for public viewing.
The BIDDER'S INQUIRIES
& RESPONSES will be updated continuously and all attempts will be made
to do the final posting by 15:00 on Wednesday prior to the bid opening.
INFORMATION
AVAILABLE
|
08/16/01 |
|
BIDDER'S
INQUIRY SUBMITTAL FORM
|
|
Inquiry |
|
Q:08/08/01 R:08/16/01 |
Plan Sheet /
Specification Reference=Special provisions Page 13, Section 4 -Beginning
of Work, Time of Completion and Liquidated Damages. "160 Working Days."
Is the true intent to include plant establishment within the 160 working days?
|
|
Q:08/10/01 R:08/12/01 |
Plan Sheet /
Specification Reference=
Where can we get full size plans?
or through: MESA
BLUEPRINT
|
|
Q:08/10/01 R:08/16/01 |
Plan Sheet /
Specification Reference=Item 24: FERTILIZER PAK (PACKET)
Unit of measure shown is KG should be EA?
|
|
Q:08/22/01 R:08/27/01 |
Plan Sheet / Specification Reference=39,
Turf (sod)
Blend specified does not seem to exist; have called numerous local sod suppliers and all don't have product specified. How should we bid this item? Can we substitute?
|
|
Q:08/28/01 R:08/28/01 |
Plan Sheet / Specification Reference=Addendum
# 1
Where can we obtain cross sections?
|
|
|
|
|
|
|