The responses to bidder' inquiries, unless incorporated into a formal addenda to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The responses may be considered along with all other information furnished to prospective bidders for the purpose of bidding on the project. The availability or use of information provided in the responses to bidder' inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.
Caltrans District 11 Construction Department
has developed this method of answering Bidders Inquiries to better serve
the needs of the Contractors who bid on our Projects.
BIDDER'S INQUIRIES
& RESPONSES will be updated continuously with the final posting no
later than 15:00 on the Wednesday prior to the bid opening.
Caltrans District 11 Construction Department
will post all of the questions submitted by any of the registered Planholders
for that Contract, but reserves the right not to answer any questions deemed
unsatisfactory for public viewing.
|
10/06/00 |
10/19/00 |
|
|
Inquiry |
|
|
How do we obtain full size plan sheets?
They can be printed directly from the above
listed site or downloaded for printing at any available reprographics company.
|
|
|
Plan Sheet / Specification Reference=
When will the cross sections be available?
5560 Ruffin Road Suite 5 San Diego, CA 92123 (858) 541-1500 FAX (858) 278-0558 e-mail to MESA@flashnet.com |
|
|
Plan Sheet / Specification Reference=ITEM
#7- FLASHING BEACON, ITEM #9- PORTABLE CMS SIGN, ITEM #10 FLASHING ARROW
SIGN
THE SPECIAL PROVISIONS FOR THESE THREE
ITEMS OF WORK MAKE NO REFERENCE AS TO WHETHER THESE ITEMS BECOME THE PROPERTY
OF THE STATE, OR ARE RETAINED BY THE CONTRACTOR AT THE CONCLUSION OF THE
WORK.
|
|
|
Plan Sheet / Specification Reference=SUBMISSION
OF BID
Is it necessary to acknowledge Addendum 2 if we already submit our bid today?
|
|
|
|
|
|
|
|
|
|