Place Triple Precast Reinforced Concrete Box Culvert And Replace Bridge Railing.
Advertise
Date 04/23/01
Bids
Open
06/07/01
Caltrans District 11 Construction Department
has developed this method of answering Bidder's Inquiries to better serve
the needs of the Contractors who bid on our Projects. Only when stated
in the Special Provisions will contracts have posted INQUIRIES AND RESPONSES.
The BIDDER'S INQUIRIES
& RESPONSES will be updated continuously and all attempts will be made
to do the final posting by 15:00 on Wednesday prior to the bid opening.
Caltrans District 11 Construction Department
will post all of the questions submitted by any of the contractors that
are registered Planholders for that Contract, but reserves the right to
not answer any questions deemed unsatisfactory for public viewing.
|
05/09/01 |
05/24/01 |
|
|
|
Inquiry |
|
|
Plan Sheet / Specification Reference=GENERAL
The 30 working days allowed for the job seems adequate for actual construction, however the design, shop drawing approval, and manufacturing period could easily consume the entire 30 working days and then some. Why not allow an advance period for the preliminaries (i.e.design,approval,manufacture) and THEN 30 working days for the on-site work?
|
|
|
Plan Sheet / Specification Reference=GENERAL
The traffic control plans seem to give no option other than full-time, 24 hours per day, 7 days per week, coverage with at least 2 on-site flaggers during construction when only one lane of traffic is possible. Was there any intent to allow a portable traffic light regulating time periods of each direction of traffic flow?
|
|
|
Plan Sheet / Specification Reference=
Where is the Bridge demolition paid?
|
|
|
Plan Sheet / Specification Reference=Special
Provisions Section 5-1.16
The copy of the US Fish and Wildlife
permit does not contain even numbered pages.
|
|
|
Plan Sheet / Specification Reference=Page
10 section 5-1.018 Excavation Safety Plans 5-1.02A, third bulleted paragraph
This requires 3 weeks allowance for the engineer to review the shoring drawings. This represents 15 working days of the 30 allowable. Can additional time be added to the project to compensate for this review time?
|
|
|
Plan Sheet / Specification Reference=Page
39 section 10-1.01 Order of Work
Each stage construction of prefabricated rcb is 10 wd. Each stage requires excavation, demolition, dewater of the excavation, construction of the cutoff wall, placement of the precast rcb, wingwall footing construction, wall construction, wait for concrete strength, backfill, type 25 rail construction and paving. No night work is allowed per fish & Game Permit. Thirty working days ia not an adequate amount of time to accomplish all of the above. Can additional time be added to the contract to accomplish the above work?
|
|
|
Plan Sheet / Specification Reference=
Suppliers of the precast box indicate a 12 week production time after approval of the shop drawings. Can the contract time be increased to accommodate this production schedule?
|
|
|
Plan Sheet / Specification Reference=Section
10-1.10 Construction Zone Enhanced Enforcement. The total number of chp
hours is 490.
Two 10 day work periods at 24 hours per day, 7 days a week = 576 hours. The contractor is required to schedule the chp 15 days in advance of work requiring the CHP. What is the criteria for CHP support?
|