| CONTRACT NO: | 11-2T1814 |
| ROUTE / PM | 11-SD-54,805-1.8,5.5/9.4 |
| LOCATION | In San Diego County In Chula Vista And National City On Route 54 At 805/54 Separation And On Route 805 From 0.4 Mile North Of Palomar Street Overcrossing To 0.6 Mile North Of Route 805/54 Separation. |
| DESCRIPTION | Construct North And South Bound Hov Lanes. |
| CONTRACT TYPE | A + B Bidding |
| ESTIMATE | $34,900,000 |
| WORKING
DAYS |
800 |
| ADVERTISE DATE | 02/06/2012 |
| BID OPENING | 04/05/2012 |
| FINAL
POSTING |
04/05/2012@
07:00
|
The Caltrans District 11
Office is located at 4050 Taylor Street, San Diego, CA 92110. The
District 11 Duty Senior telephone number is (619) 688-6635. Please
submit all inquiries in the proper format by fax to (619) 688-6988 or
e-mail to:
Duty_Senior_Const_District11@dot.ca.gov.
The responses to bidder' inquiries,
unless incorporated into a formal addenda to the contract, are not a
part of the contract and are provided for the bidder's convenience
only. In some instances, the question and answer may represent a
summary of the matters discussed rather than a word-for-word
recitation. The responses may be considered along with all other
information furnished to prospective bidders for the purpose of bidding
on the project. The availability or use of information provided in the
responses to bidder' inquiries is not to be construed in any way as a
waiver of the provisions of Section 2-1.03 of the Standard
Specifications or any other provision of the contract, the plans,
Standard Specifications or Special Provisions, nor to excuse the
contractor from full compliance with those contract requirements.
Bidders are cautioned that subsequent responses or contract addenda may
affect or vary a response previously given.
Caltrans
District 11 Construction Department has developed this method of
answering Bidder's Inquiries to better serve the needs of the
Contractors who bid on our Projects. Caltrans District 11 Construction
Department will post all of the questions submitted by any of the
contractors that are registered Planholders for that Contract, but
reserves the right to not answer any questions deemed unsatisfactory
for public viewing.
The BIDDER'S INQUIRIES & RESPONSES
will be updated continuously and all attempts will be made to do the
final posting by 15:00 on the day prior to the bid opening. However, to
allow the Department reasonable time to review and respond, bidders are
recommended to send in their inquiries at least four (4) working days
prior to the bid opening.
INFORMATION
AVAILABLE
|
|
|
|
|
|
|
|
ORDERING
PROJECT PLANS AND SPECIFICATIONS
ADDENDUM
|
|
BIDDER'S INQUIRY SUBMITTAL FORM
|
|
Inquiry |
|
1 Q:02/14/12 |
Plan Sheet / Specification Reference= Item 105, Column Casings, 585/635, 604/635, and 624/635 Question
= This is a request that you provide the as-built column heights for
all of the columns that receive column casings. In reviewing the
contract drawings these heights are not provided as they typically are
on column casing retrofits, nor are the bottom of footing elevations
for each column that has a casing.
|
|
2 Q:02/14/12 |
Plan Sheet / Specification Reference= 70,76, Page Q-3(sheet 357), L-1(sheet 7), PS-1(sheet 23) Question=Page Q-3
(sheet 357) gives a structural section summary of quantities, this list
calls out 545.46 CY of JPCP between station 316+00 and 323+83.37 on the
southbound side. On both the Layout Drawings (L-1, sheet 7) and the
profile drawings (PS-1, sheet 23) the work is called out to begin at
station 323+00 and the first section to end at station 323+72.47 in the
southbound direction. Please provide clarification as to what
stationing the work is to begin and the corresponding quantities for
the first section of work.
|
|
3
Q:02/21/12 |
Plan Sheet / Specification Reference= Temp Sidewalk and Ramps per Sheet 252, ramps have Detectable Warning Surfaces 3 x 4 , various locations Bonita Road, Sweetwater Rd, and Eucli70,76, Page Q-3(sheet 357), L-1(sheet 7), PS-1(sheet 23) Question= In which bid item is the cost to provide & install Detectable Warning surfaces on ramps constructed under PLACE HMA (Miscellaneous areas)to be paid for?
|
|
4
Q:02/21/12 |
Plan Sheet / Specification Reference= Item 137, Minor Concrete (Curb and Sidewalk) Plan Sheet 356 Summary of quantities. Question=
Quantities listed on Q sheet appear incorrect for both the curb and the
sidewalk. For Type A2-6 Curb, CALTRANS standard plan indicates
.05903 CY per LF, this does not correspond with quantities shown for
the Curb. Sidewalk quantities also do not calc correctly.
Example # 1 26 LF x 5' x 4" thick should be 1.59 CY, chart indicates
4.81. The last one on the chart plan indicates a length of 522
LF, which would equate to 31.9 CY, chart indicates 4.81 CY.
Please clarify.
|
| 5
Q:03/02/12 |
Plan Sheet / Specification Reference= Var Question= We have
the following questions in regards to the captioned project:
2. Bonita Rd UC – Sht
558 of 635 – Abutment Layout – Plan View – Please
provide the dimensions of the abutment footing.
|
|
6 Q:03/13/12 |
Plan Sheet / Specification Reference= Item # 105, Column casings Question= Please provide information on how to obtain As-Built Drawings for the bridge columns. Also there is no information on what columns will require casings. a Column table will be helpful. On sheet 604 (steel column casing), under note #5, it says 1/4" min for thick for casings with a 4'-4" dia or less. These column casings are not round
at the base measure 4'-4" X 10'-4".
|
|
7 Q:03/14/12 |
Plan Sheet / Specification Reference= E-39 Question= On plan sheet E-39 there is a symbol calling for a 200W HPS Soffit fixture however this is not a standard symbol so i was wondering if you could provide more detail about this fixture or perhaps a cut sheet. We are trying to find out what this fixture is and how it should be installed. The plans are also calling for a 400W fixture. On plan sheet E-38 there is a ES-90 detail which is not explained on the plans or in the specs. So again we were wondering if you could provide more information on this detail.
|
| 8
Q:03/26/12 |
Plan Sheet / Specification
Reference=HP 14 X 89 Driven Piling, Sheet Number 577 Question= Note 2 on pile data table indicates that a pile lug is required for the HP 10 x 57 piles. Piles on this structure only include HP 14 x 89 piles. Please indicate if pile lugs are required for the HP 14 x 89 piles.
|
|
9 Q:03/29/12 |
Plan Sheet / Specification Reference=
122-125, Pipe Culverts, 83-170: Piple layout drawings Question= In locations where new pipe culverts are installed in existing paved shoulders that are not reconstructed with new pavement sections; under which bid items does the pavement patching get measured and paid?
|
|
10 Q:04/02/12 |
Plan Sheet / Specification Reference= 2-Do you want 1/2" or 3/8" cover plates for Type 60 R-4 Barrier. 3- What
is the required Vertical Ht. for the 1/2" or 3/8" Cover plate on the
low paving side shown in Sect G-G on plan sheet 51 of 635.
|
| 11
Q:04/03/12 |
Plan Sheet / Specification
Reference=
Special Provision
Question= 1- Ref Special Provision Section 10-1.69- Please confirm the apparent requirements to paint new Light Weight and Truss Type sign structures.
2- 1- Ref Special Provision Section 10-1.65 specifically " Measurement and Payment- Wher and what items require Epoxy Coated or galvanized reinforcing steel for this contract.
|
|
12
Q:04/03/12 |
Plan Sheet / Specification
Reference=
Special ProvisionPlan Sheet / Specification Reference=134 Slope Paving
(masonry block) Bid Item Question= The bid item quantity for the slope paving (masonry block) appears to be less than the actual slope length quantity of 50,000 sf. Please verify.
|
|
13
Q:04/03/12 |
Plan Sheet /
Specification Reference= Question= 1- Ref Electrical Plan Sheets E-1 to E-42. Your requirements seem to call for electrical conduit and pull boxes in some of the Type 60 Series Concrete Barrier. There are no Standard Details in Type 60 Series Barrier that accomodate reinforcing steel elimination or barrier dimensional details. Request that these details be provided by addendum to all bidders, prior to bid date.
2-Ref plan Sheet 548- With revisions per Addendum # 1, please confirm that the details for Type 60 GA MOD shown on Sheet 548 no longer apply.
|
|
14 Q:04/04/12 R:04/04/12 |
Plan Sheet / Specification Reference=
|
|
15 Q:04/04/12 R:04/05/12 |
Plan Sheet / Specification Reference=
|
OTHER LINKS OF INTEREST
DISTRICT 11 CONSTRUCTION
BIDDER'S INQUIRIES & RESPONSES
DISTRICT 11 HOMEPAGE
CALTRANS OFFICE ENGINEER:
Contract Advertisement, Special Provisions, Plan Holders, Contract
Awards, etc.
DEPARTMENT OF TRANSPORTATION