| CONTRACT NO: | 11-294504 |
| ROUTE / PM | 11-SD-78-3.5/5.8 |
| LOCATION | In San Diego County In Oceanside And Vista From 0.2 Mile East Of College Boulevard Undercrossing To 0.1 Mile West Of Melrose Drive Undercrossing. |
| DESCRIPTION | Install Outer Separation Concrete Barrier. |
| ESTIMATE | $3,720,000 |
| WORKING
DAYS |
160 |
| ADVERTISE DATE | 07/18/2011 |
| BID OPENING | 08/11/2011 |
| FINAL
POSTING |
08/10/2011@ 14:30
|
The Caltrans District
11 Office is located at 4050 Taylor Street, San Diego, CA 92110. The
District 11 Duty Senior telephone number is (619) 688-6635. Please
submit all inquiries in the proper format by fax to (619) 688-6988 or
e-mail to:
Duty_Senior_Const_District11@dot.ca.gov.
The responses to
bidder' inquiries, unless incorporated into a formal addenda to the
contract, are not a part of the contract and are provided for the
bidder's convenience only. In some instances, the question and answer
may represent a summary of the matters discussed rather than a
word-for-word recitation. The responses may be considered along with
all other information furnished to prospective bidders for the purpose
of bidding on the project. The availability or use of information
provided in the responses to bidder' inquiries is not to be construed
in any way as a waiver of the provisions of Section 2-1.03 of the
Standard Specifications or any other provision of the contract, the
plans, Standard Specifications or Special Provisions, nor to excuse the
contractor from full compliance with those contract requirements.
Bidders are cautioned that subsequent responses or contract addenda may
affect or vary a response previously given.
Caltrans District 11 Construction
Department has developed this method of answering Bidder's Inquiries to
better serve the needs of the Contractors who bid on our Projects.
Caltrans District 11 Construction Department will post all of the
questions submitted by any of the contractors that are registered
Planholders for that Contract, but reserves the right to not answer any
questions deemed unsatisfactory for public viewing.
The BIDDER'S
INQUIRIES & RESPONSES will be updated continuously and all attempts
will be made to do the final posting by 15:00 on the day prior to the
bid opening.
INFORMATION
AVAILABLE
|
|
|
|
|
|
|
|
|
ORDERING
PROJECT PLANS AND SPECIFICATIONS
ADDENDUM
|
|
BIDDER'S INQUIRY SUBMITTAL FORM
|
|
Inquiry |
|
1 Q:07/29/11 |
Plan Sheet / Specification Reference= Var Question= Please provide Cross sections that define the vertical pavment offset dimensions for Type 60C Concrete Barrier.
|
|
2 Q:08/03/11 |
Plan Sheet / Specification Reference= Items 50 and 51 Type 60 Barriers Mod 1 and Mod 2 Sheet 87 (C-1) Question= The details for these barriers show a 12" barrier top and 6" batters whereas the standard Type 60 barrier has a 12.5" top and 5.75" batters. Both have a 24" bottom width at a 36" height. Is it permissable to use the standard Type 60 barrier dimensions for the upper 36" of the Type 60 Mod 1 and Type 60 Mod 2 barriers?
|
|
3 Q:08/03/11 |
Plan Sheet / Specification Reference= Section 10-1.15, MAINTAINING TRAFFIC, the project entails work on both the westbound and eastbound roadways. There are no lane closure charts for the westbound roadway and the lane closure charts for the eastbound roadway require that 2 lanes be kept open of the 3 lanes that exist in that reach. Question= The traffic handling plans provide for concrete K-rail to be placed in both eastbound and westbound roadways. It is not safe to deliver and place K-rail inside a closure of a single lane with high speed traffic in the adjscent 2 lanes. While most of the operation is performed by a crane interacting with a transport truck, workmen will be required to be on the ground during this unloading and loading operation. In the interests of the safety of the workmen and the travelling public, please provide land closure charts for two lanes to be closed at the work locations in both the eastbound and westbound roadways for sufficient shifts (max 10 inbound and 10 outbound) to deliver & place and then, upon completion of the work, reload & offhaul concrete K-rail.
|
|
4 Q:08/03/11 |
Plan Sheet / Specification Reference= Various Question= Traffic Charts #1 thru # 7 do not provide any information for work hours and shoulder/lane closure time along Plaza Drive. The work, as shown on plan sheet X-2 will likely require some shoulder/lane closure. Please provide your direction by a traffic chart for Plaza Drive.
|
|
5 Q:08/04/11 |
Plan Sheet / Specification Reference= Item 51 - Type 60 Mod 2 Barrier - Page 17 (C-1) of the plans. Question= 1.Is it permissable
to have a construction joint at approximately ground level on the Type
60 Mod 2 Barrier assuming we add #5 dowels similar to the detail for
the Type 60 Mod 1 Barrier.
|
|
6 Q:08/04/11 |
Plan Sheet / Specification Reference= N/A- Special Provision 10-1.25- Cleaning Inspecting and Preparation Host Pipe Question= Ref Special
Provision Section 10-1.25-Cleaning Inspecting and Preparation Host
Pipe- As currently provided for this work is complex, appears to
require some pre-qualified experienced specialty contractor, is far
removed from work covered in any Standard Specification in the 2006
Amennded Standards, involves many work tasks and is only to be measured
and paid for as .."included in the contract unit price per cyd for
concrete invert paving''... This is ambiguous, undefined, unclear and
is inappropriate. Request that you reconsider and provide for all this
work as Extra Work after award of contract. If this is not your pre bid
intent, than issue an addendum that provides all required design
information of existing pipe, including flow rates for materials that
run through the pipe, access to the source of water flow, and your
rquiremnent for diversion; the anticipated quantities of pressure
grouted repair; the anticipated quantity for CCTV inspections; quantity
for replacement of backfill and bedding below the pipe invert; quantity
for high velocity cleaning equipment and air moving; tunnel safety
requiremnets ?? and quantity for pay pipe repair.
|
|
7 Q:08/05/11 |
Plan Sheet / Specification
Reference= VARIOUS
Question= 1- Your response to previous Pre Bid Question # 6 is non-responsive to the question. Request that the current (deficient) contract documents be amennded to either define your estimated quantities for the many work tasks involved, and provide bid item(s) for those work tasks, or delete this vauge and undefined/non-quantified work from the contract.
2- Please provide a traffic chart to define hours of work and LANE closure at W/B Rte 78, Sta 246+29 to 250+ 90+/- and 275+00 to 331+75+/- so that work of installing Type E Asphalt Dike can be performed.
|
|
8 Q:08/07/11 |
Plan Sheet /
Specification Reference= 1-Item 25 Roadway Excavation Question= 1- The quantity Table of Earthwork Quantities, Plan Sheet 64 appears to have incorrectly included standard Roadway Excavation quantities that are necessary for Class 2 Agg Base, in a "Non Pay" footing excavation quantification. Please review and adjust the quantity of Item 25 before the bid date.
3- Have the engineers who approved the Special Provisions
reviewed the Plans? Have the engineers who approved the Plans, reviewed
the Special Provisions?
|
|
9 Q:08/08/11 |
Plan Sheet / Specification Reference= Question= 1- Why are you posting " Contractor's Interpretations" to Pre-Bid Questions??
|
|
10
Q:08/09/11
R:08/10/11
|
Plan Sheet / Specification
Reference= Item #34, 22" CIDH pile. Relative to the GEOTECHNICAL DESIGN
REPORT. Question= The Geo Report borings indicate SOLID IGNEOUS ROCK at depths of 5.0', 2.5', and 2.5' where the plans call for 22" CIDH pile extending to a depth of 8 feet below grade under the type 60 Mod 2 concrete barrier rail. Is it the intent of Caltrans to require the 22" CIDH pile to be installed by drilling through SOLID IGNEOUS ROCK?
|
OTHER LINKS OF INTEREST
DISTRICT 11 CONSTRUCTION
BIDDER'S INQUIRIES & RESPONSES
DISTRICT 11 HOMEPAGE
CALTRANS OFFICE ENGINEER:
Contract Advertisement, Special Provisions, Plan Holders, Contract
Awards, etc.
DEPARTMENT OF TRANSPORTATION