|
Inquiry No.
|
Inquiry |
1
Q:07/12/2010
R:07/29/2010
R:08/09/2010
|
Plan Sheet / Specification
Reference= Bid Item 39
Question= In
the Material Handout Caltrans
refers to their Borrow Source (SMARA Permit # 91-13-0052). Please
provide the following:
1. Location; Thomas Bros Coordinates,physical
directions or GPS Coordinates
- OCOTILLO, Latitude 32.56778 and Longitude -116.00861.
2. Permit Restrictions if any
- Please contact County of Imperial Planning Department.
3. Borrow Site Plan the contractor will be obligated
to follow if any
4. Reclamation Plan the contractor will be obligated
to follow if any
5. Any all fees the contractor will be obligated to pay
- Please refer to section 7-1.04 "Permits and Licenses" of the Standard Specifications.
Contact information is in the reference website.
|
2
Q:07/13/2010
R:08/09/2010
|
Plan Sheet / Specification
Reference= Bid Item # 88 Prefabricated
Vertical Drains
Question= The plans
call for the vertical drain material to be cut off at
OG. There is no gravel, piping or filter fabric indicated on the
drawings. Please confirm the bidders are not to include any gravel,
filter fabric or drainage piping for the water to drain through during
the subsidence phase or the ultimate location of the abutments.
- Please bid per the current contract documents. Based on the Kalin Rd UC Foundation Report (dated May 18, 2009), in the Information Handout, Bidders are not to include any cost for gravel or filter fabric for the water to drain through during the settlement/primary consolidation phase of the abutments. However, drainage piping for the water to drain through during the settlement/primary consolidation phase of the abutments are at contractor's option and if used will be at contractor's expense.
|
3
Q:07/13/2010
R:07/29/2010
|
Plan Sheet / Specification
Reference= Bid Item # 107 the React 9cbb
Question= Will
Caltrans accept post bid CRIPs for bid item 107 to substitute SCI-100
Smart Crash Cushion in lieu of the React 9cbb?
- No. Please refer to section 5-1.14 of the
Standard Specfication.
|
4
Q:07/13/2010
R:07/29/2010
|
Plan Sheet / Specification
Reference=Bid Item # 39 Imported Borrow
Question= The Q Sheet
Quantities appear to be short if you extend the
math. The amount short appears to be appproximately the subsidence
quantity. Please clarify
- Quantities are correct, please bid per current
Contract Documents.
|
|
5
Q:07/13/2010
R:07/21/2010 |
Plan Sheet / Specification
Reference=Cross Sections - PDCL1 and CWNCL1 Lines
Question= The PDCL1
Line of the cross sections appears to be missing cross sections from
183+30-187+20. Will those cross sections be made available?
The CWNCL1 Line says there is 70 sheets, however the cross sections
stop at sheet 52. Is 52 the correct number of sheets, or are we missing
some of those sheets?
- Additional cross-sections have been added to
the link X-SECTIONS 07/21/10 above.
|
|
6
Q:07/13/2010
R:07/29/2010
R:08/09/2010 |
Plan Sheet / Specification
Reference= IID Utility Irrigation Relocations
Question=There is no
schedule or availability related to IID facility relocations. Please
provide relocation availability times if they will not relocate per the
bid documents.
Please bid per current contract documents.
- Please refer to Section 5-1.17 "NONHIGHWAY FACILITIES (INCLUDING UTILITIES)" of the special provisions.
|
|
7
Q:07/13/2010
R:07/30/2010 |
Plan Sheet / Specification
Reference=Bid Item 39
Question=1. Are there
any designated borrow sites for this project?
- There are
optional borrow sites in this project. Refer to Information handout and
addendum #1
2. Is the Caltrans Ocotillo site a mandatory designated site?
- No mandatory
borrow sites for this contract.
3. If a farmer or any other entity is issued a grading permit from
Imperial County for whatever reason which results in export from that
site will that negate the SMARA requirement as far as Caltrans is
concerned?
- Contact the California Department of
Conservation regarding any of their requirements.
4. Caltrans had two designated sources for the previous project. Have
those sources been exhausted?
- Refer to information handout and addendum #1
for optional borrow sites.
5. The BLM routinely issues Borrow Site Permits in Imperial County. If
the BLM issues a royalty permit for borrow material will that negate
the SMARA requirement as far as Caltrans is concerned?
6. Will the contractors be allowed to haul through the current project
(11-167884) by February 2011, in order to avoid having to haul through
Brawley if the contractors borrow source is South and or East of
Brawley?
|
|
8
Q:07/13/2010
R:07/30/2010 |
Plan Sheet / Specification
Reference= bid item number 69(f)Structural
concrete bridge footing.
Question= Can you
please revise the bid item quantity? it is short by approx. 20%.
- Refer to Addendum No. 1 dated July 29, 2010.
|
|
9
Q:07/13/2010
R:07/30/2010 |
Plan Sheet / Specification
Reference= bid item 70(f) sheet 306
Question= Sheet 306
deck contour plans, the contour line elevations are in conflict with
the written BB elevations. which is correct?
- The written BB/EB elevations are CORRECT.
|
|
10
Q:07/19/2010
R:07/30/2010 |
Plan Sheet / Specification
Reference= BId # 59 Continuously Reinforced Concrete Pavement Wide
Flange Beam Terminal. sheet 69
Question= The plan
view detail on sheet 69 shows the wide flange beam detail running
continuously through the graded median or from one side of the freeway
to the other. Is this what Caltrans intends. Also under what item is
the lean concrete base material to be paid?
- Wide Flange should run from EP to EP on both
sides. See addendum #1 for payment clause of the lean concrete base.
|
|
11
Q:07/20/2010
R:07/30/2010 |
Plan Sheet / Specification
Reference= Item 39, Imported Borrow, special provisions section 10-1.31
"EARTHWORK", states "The portion of imported borrow placed with 1.5 m
of the finished grade shall have a Resistance (R-Value) of not less
than 10."
Question= What quality
requirements, if any, are imposed on imported borrow placed in the
planned embankment other than the portion of the subgrade under the
first layer of structural section material necessary to comply with the
1.5 meter specification in the referenced section. We do not see any
quality requirements for material placed elsewhere. Please clarify.
- Please refer to Addendum 1 dated July 29, 2010.
|
|
12
Q:07/20/2010
R:07/29/2010 |
Plan
Sheet / Specification Reference= Item 33, ROADWAY EXCAVATION.
Plan sheet X-1 (sheet 2 of 325) has a call out for "300 mm FOUNDATION
TREATMENT". Plan sheet Q-1 (sheet 233 of 325) under "EARTHWORK
QUANTITIES" has a row entitled "FOUNDATION TREATMENT" with a quantity
listed of 34,600 under the column entitled "ROADWAY EXCAVATION (m3)".
Question= We find
nothing in the specifications defining a procedure "FOUNDATION
TREATMENT" nor defining means of measurement and payment. Please
define the operational procedure called out as "300 mm FOUNDATION
TREATMENT" and verify that it is to be measured and paid as cubic
meters of ROADWAY EXCAVATION.
- FOUNDATION TREATMENT is the removal of 300 mm
of material below OG and replacing it with embankment material
|
|
13
Q:07/20/2010
R:07/29/2010
R:08/09/2010 |
Plan Sheet / Specification
Reference= page 147 last sentance for mesurement and payment of
continuously reinforced concrete pavement. States full compensation for
epoxy coating of reinforcing steel is to be paid per cubic meter for
continuously reinforced concrete pavement.
Question= There is
nothing showing epoxy coated rebar any where on the plans or in the
spec's other then this sentence. Is all of the reinforcing steel for
the continuously reinforced concrete pavement to be epoxy coated?
- Please refer to Section 10-1.47 "CONTINUOUSLY
REINFORCED CONCRETE PAVEMENT" and Section 11 "MODIFIED STANDARD SPECIFICATION SECTIONS" 40-2 "MATERIALS" of the Special Provisions.
|
|
14
Q:07/20/2010
R:07/29/2010 |
Plan Sheet / Specification
Reference= Item 33, ROADWAY EXCAVATION, plan sheets PS-1 thru PS-14 (30
thru 43 of 325)and plan sheets G-12,G-13,& G-14.
Question= The roadway
excavation quantities listed on the PS (1-14) sheets agree fairly well
with the quantities listed on the Q sheets but differ greatly from the
information presented on the G (12-14)sheets. The PS sheets list
approximately 275,000 cubic meters of excavation between stations
199+55 and 206+20. The G sheets depict original ground elevations and
finish grade contours that yield a volume of approximately 440,000
cubic meters for the same region when calculated. Which volume is
correct? Which plan differs from the actual site condition?
- Original Ground shown is prior to stage 2
construction, PS sheets are correct.
|
|
15
Q:07/20/2010
R:07/29/2010 |
Plan Sheet / Specification
Reference= Item 33, ROADWAY EXCAVATION, plan sheet X-1, have call outs
for "300 mm FOUNDATION TREATMENT" where the planned subgrade elevation
is higher than exiting original ground.
Question= What is the
plan for any "FOUNDATION TREATMENT" when all or part of the planned
subgrade elevation falls below original ground between 0 and 300mm, and
greater than 300mm?
- FOUNDATION TREATMENT applies to locations shown
on the plans regardless if original ground is below or above subgrade
|
|
16
Q:07/29/2010
R:08/02/2010
R:08/09/2010 |
Plan Sheet / Specification
Reference= Special Provisions Section 10-1.41, page 124
Question= Section
10-1.41, of the project special provisions, makes reference to
California Test 371, historically projects, bidding and build, in the
lower desrt area requiring aggregates incorporated in hot
mix asphalt have not specified the use of Test 371. Is California Test
371 applicable to this project?
Please
bid per current contract documents.
- Not required for aggregates with known history.
|
|
17
Q:07/29/2010
R:07/30/2010 |
Plan Sheet / Specification
Reference= Item 33, Roadway Excavation, plan sheets X-1,X-2.X-3.X-4,
These sheets depict a 2.0 meter wide trapezoidal shaped ditch along the
toes of embankment on the 'P' line of unknown depth, and a 'V' shaped
ditch along the toes of embankment on most other lines.
Question= What depth
are these ditches? How are they paid? There is no "Ditch Excavation"
item. Is the volume of these ditches included in the calculated volume
of roadway excavation per Section 19-4.03, third paragraph, of the
Standard Specifications?
- Depth of
ditches are shown on the X-sections provided, and it is paid as roadway
excavation because it is part of the roadway prism as shown in standard
plan A62A.
|
|
18
Q:07/29/2010
R:08/06/2010 |
Plan Sheet / Specification
Reference=Reference Plan Sheet No. 2 of 325.
Question= Reference
Plan Sheet No 2 of 325 - detail approximately mid page titled "HMA Dike
Placement on PCC". This detail calls for structural section No. 1 to be
widened 0.2m outside the ES where HMA dike is to be placed. Please
confirm that the intent is to widen the CRCP 0.2m in areas where HMA
dike is to be placed.
|
|
19
Q:07/29/2010
R:08/06/2010
R:08/09/2010 |
Plan Sheet / Specification
Reference= Reference Plan Sheet No. 9 of 325.
Question= At
approximately Sta 158+00.947 "P" and 397+78.919 "N" on plan sheet 9 of
325, there is a call out for Structural Section No. 1 at the
intersection of Route 78 and Route 86. Is the intent to place CRCP in
that intersection? If so, please provide a joint layout and limits of
the CRCP.
Please
bid per current contract documents.
- Yes. CRCP is required through the intersection as shown on the layout sheets. Joints will be required at limits shown on plans per construction detail sheets.
|
|
20
Q:07/30/2010
R:08/02/2010 |
Plan Sheet / Specification
Reference=Item #13 Temp Hydraulic Mulch, Section 10-1.04 Pg65, 66
Question= 1. Summary
and materials specify a tackifier; application specifies wood and
cellulous fiber. Are we to use just the wood fiber?
- The contractor is given the option to use wood
fiber, cellulose fiber, alternate fiber, or a combination of these
fibers that meet the criteria stated in Section 10-1.04 "Temporary
Hydraulic Mulch" of the special provisions.
A tackifier is also required by the same
section 10-1.04 of the special provisions.
|
|
21
Q:07/30/2010
R:08/02/2010 |
Plan Sheet / Specification
Reference= Item #40, Erosion Control BFM Section 10-1.34 pg 118-120
Question= 1. Regarding
a BFM in 2 application process; 2 application usually done to include a
seed but find no seed specified so are you not including seed? If no
seed why two applications?
- The two
applications without seeding are needed because the material will be
applied from 2 or more directions per Section 10-1.34 "EROSION CONTROL
(BONDED FIBER MATRIX)" of the special provisions to achieve a continuos
mat (page 119, under Application).
|
|
22
Q:07/30/2010
R:08/09/2010 |
Plan Sheet / Specification
Reference= ITEM 39, IMPORTED BORROW
Question= REFERENCE
BIDDERS INQUIRY NO. 1, (7/12/2010) RESPONSE (7/29/2010). The response
is non-responsive. What website? If the "reference website" is meant to
be the CONSERVATION website listed on page 6 of the original MATERIALS
INFORMATION BROCHURE, that website deals with hundreds, if not
thousands, of SMARRA sites, issues, rules, and regulations. The 3098
list available on the website only reveals the location of this site as
"OCOTILLO". We could not find information regarding location of SMARA
91-13-0052 on the website nor on the latest version of the ACTIVE
SURFACE MINING OPERATIONS MAP provided by the Planning &
Development Services Department of the County of Imperial. Further, the
"ADDITIONAL INFORMATION HANDOUT" included with Addendum #2 makes
reference to a site identified only as "DUTTON" MATERIAL SITE, with no
further coordinating identifying information. Is "DUTTON" the same as
SMARA 91-13-0052? Please provide some usefull information regarding the
State borrow sites (or site).
- Dutton Parcel is parcel 34423 as shown on the Keymap and its included as part of the project.
|
|
23
Q:07/30/2010
R:08/06/2010
|
Plan Sheet / Specification
Reference= ITEM 33, ROADWAY EXCAVATION, specifically FOUNDATION
TREATMENT
Question= INQUIRY #12
(7/20/2010 RESPONSE (7/29/2010) and INQUIRY 15 (7/20/2010) RESPONSE
(7/29/2010)address this issue but fail to resolve all concerns
regarding procedure and payment. We conclude from the information
provided in the bid documents and the answers provided to the above
stated inquiries, and our previous experience that FOUNDATION TREATMENT
is an operation wherein the native, in-situ earthen material is
excavated for a depth of 300 mm below existing original ground or
subgrade, whichever is lower, and re-used in ordinary embankment
somewhere on the project; and the volume thus excavated and re-used
will be measured and payment will be made therefor as contract item 33,
ROADWAY EXCAVATION. Please confirm.
|
|
24
Q:07/30/2010
R:08/09/2010
|
Plan Sheet / Specification
Reference= Addendum 1 and Information Handout, Materials Information
Question= Addendum 1
and accompanying Information Handout references optional sites for
Imported Borrow. How does ValRock, a subsidiary of Vulcan Materials
Co., also get referenced as an optional site as we have sites also
available and supplied Imported Borrow as well as other materials to
the previous phase (11-167884)
|
|
25
Q:07/30/2010
R:08/09/2010
R:08/09/2010
|
Plan Sheet / Specification
Reference= ITEM39, IMPORTED BORROW, Special Provisions section 10-1.31
EARTHWORK
Question= The
referenced section of the special provisions of the contract documents,
as modified by addendum #1, dated July 29, 2010, provides that the
"Embankment material within 0.8 meters of the finished grade shall have
a sand equivalent (SE) between 10 and 45." The only definition of
"finished grade" that we can find in the contract documents is provided
in the Standard Specifications, Section 19-1.01 DESCRIPTION, paragraph
2, "Whenever reference to finished grade is made, it shall be
considered to be the finished surface of the completed facility." We
conclude that the only quality requirement for imported borrow placed
in embankment volumes not reserved for material of the SE range
stipulated below is found in the Special Provisions, Section 10-1.31
EARTHWORK, ninth paragraph; and the Standard Specifications, Section
19-7.01 IMPORTED BORROW, second paragraph. Further, we conclude that
there the added contract requirement applicable to the material placed
in any embankment, anywhere on the project, including the top 35mm of
subgrade in paved areas designated as typical structural section #1,
(no portion of the subgrade of paved areas designated as typical
structural section #2), all medians, shoulders, and embankment slopes,
of all roadways constructed under this contract, including the mainline
of routes 78 & 86, frontage roads, connector roads, and surface
roads is the SE range of between 10 and 45. Further, we conclude that
any and all roadway excavation developed in the construction of the
project must be placed in embankment locations not reserved for
material of the SE range stipulated above. Please confirm.
Yes, confirmed.
- Roadway excavation material generated as part of the project meeting contractual requirements for SE may be utilized for embankment.
|
|
26
Q:07/30/2010
R:08/09/2010
R:08/09/2010 |
Plan Sheet / Specification
Reference= ITEM39, IMPORTED BORROW, Special Provisions section 10-1.31
EARTHWORK
Question= The
referenced section of the special provisions of the contract documents,
as modified by addendum #1, dated July 29, 2010, provides that the
"Embankment material within 0.8 meters of the finished grade shall have
a sand equivalent (SE) between 10 and 45." The only definition of
"finished grade" that we can find in the contract documents is provided
in the Standard Specifications, Section 19-1.01 DESCRIPTION, paragraph
2, "Whenever reference to finished grade is made, it shall be
considered to be the finished surface of the completed facility." We
conclude that the only quality requirement for imported borrow placed
in embankment volumes not reserved for material of the SE range
stipulated below is found in the Special Provisions, Section 10-1.31
EARTHWORK, ninth paragraph; and the Standard Specifications, Section
19-7.01 IMPORTED BORROW, second paragraph. Further, we conclude that
there the added contract requirement applicable to the material placed
in any embankment, anywhere on the project, including the top 35mm of
subgrade in paved areas designated as typical structural section #2,
(no portion of the subgrade of paved areas designated as typical
structural section #1), all medians, shoulders, and embankment slopes,
of all roadways constructed under this contract, including the mainline
of routes 78 & 86, frontage roads, connector roads, and surface
roads is the SE range of between 10 and 45. Further, we conclude that
any and all roadway excavation developed in the construction of the
project must be placed in embankment locations not reserved for
material of the SE range stipulated above. Please confirm.
Yes, confirmed.
- Please refer to Addendum No. 1, all of section 10-1.31 "EARTHWORK" of the special provisions and section 19 "EARTHWORK" of the standard specifications.
|
|
27
Q:08/02/2010
R:08/09/2010
R:08/09/2010 |
Plan Sheet / Specification
Reference= ITEM 108, CONCRETE BARRIER (TYPE 60)
Question= Plan sheet
C-13 (65/325) shows the concrete barrier on "FG". The standard plan
A76A shows CONCRETE BARRIER TYPE 60 on "Pvmt or well compacted base".
What is required on this contract, pavement of some kind or well
compacted base of some kind? If either pavement or base is required,
what is the typical section detail and what is the basis for
measurement and payment?
- Where barrier is on pavement, pavement is paid as structural section. Where barrier is on soil, soil is compacted
to 90% in accordance with section 19-5 "COMPACTION" of the standard specifications.
|
|
28
Q:08/02/2010
R:08/09/2010 |
Plan Sheet / Specification
Reference= 54, Continuously Reinforced Concrete Pavement,plan sheet 67
Question= Per
construction details on C-15 for the Continuously Reinforced Concrete
Pavement, the contractor is provided an alternate Longitudinal
Construction Joint detail that shows the installation of a full length
tiebar in lieu of the multi-piece tiebar option. In this
detail, the tiebar is shown to be installed at D/2 from the top of the
concrete pavement, which would be 130 mm (D = 260 mm). From Table
1, the X distance (distance from the top of concrete to top of
reinforcing mat) is shown to be 102 mm for this paving depth.
With the top mat of longitudinal reinforcement being 19 mm thick, the
centerline of the transverse reinforcement will be at the 130 mm
distance also (102 mm + 19 mm + 19 mm/2), which is an exact fit for
these tiebars. But when tolerances for the installation of the
reinforcing, bar sized fluctuations, and variability in the subgrade
below the concrete are experienced, the 130 mm dimension can not be
maintained. This will only be discovered after the concrete has been
placed. Will Caltrans allow the tiebars to be installed at
a depth from the top of concrete of at least 155mm to allow the
alternate to be utilized or will Caltrans require multi-piece tiebars
to be installed?
- Bid to comply with applicable tolerances specified by contract. Utilize methods that will meet the contractual requirements considering the appropriate tolerances.
|
29
Q:08/03/2010
R:08/06/2010
R:08/09/2010 |
Plan Sheet / Specification
Reference= Contract Plan Sheet 4 of 325.
Question= Reference the Southbound typical section for Route 86 shown on plan sheet 4 of 325.
1. Is the longitudinal joint between the existing PCC and the new CRCP to be an Isolation Joint as shown on RSP P18 Detail A? If so, where is the work for the isolation joint to be paid? Typically there is a bid item for Seal Longitudinal Isolation Joint.
Please
bid per current contract documents.
- Yes an isolation joint will be required. Please refer to section 11, subsection 40-4.02 "PAYMENT" of the special provisions.
2. Will a 1 meter wide grind along the edges of the existing PCC be required where the new CRCP ties into the existing PCC? If so, where is the PCC grind work to be paid? Typically there is a bid item for Grind Existing PCC.
Please
bid per current contract documents.
- Grinding may be required per section 11, subsection 40 of the special provisions and payment under subsection 40-4.02 "PAYMENT" of the special provisions.
|
30
Q:08/03/2010
R:08/09/2010 |
Plan Sheet / Specification
Reference= STAGING PLANS PAGES 168-178
Question= THE STAGING PLANS DO NOT ADDRESS THE HANDLING OF TRAFFIC ON KALIN ROAD FOR THE CONSTRUCTION OF THE BRIDGE COLUMN FOOTINGS. WILL A PLAN BE PROVIDED?
- Please
bid per current contract documents.
|
31
Q:08/04/2010
R:08/09/2010 |
Plan Sheet / Specification
Reference= Grading
Question= I was wondering if you can release the AutoCAD linework for the grading portion of the job, so an accurate digital take off can be performed.
- Please
bid per current contract documents.
|
32
Q:08/09/2010
R:08/09/2010 |
Plan Sheet / Specification
Reference= Plan sheets 168-178, specifically Sheet SC-2
Question= I can't find where the reconstruction work planned for Brandt Road anywhere in the staged construction drawings (SC-1 to SC-10). Is it to be included along with the stage 2 scope?
|
33
Q:08/09/2010
R:08/09/2010 |
Plan Sheet / Specification
Reference= SPECIAL PROVISION SECTION 5-1.17 UTILITIES: At the bottom of the page (#24) under an extensive list of utilities to be relocated there is a note that states: "Imperial Irrigation District (IID) work forces or subcontractors working under their supervision may only perform work at one location at a time unless otherwise approved by the Engineer."
Question= What purpose is served by empowering the Engineer to require that the IID work be prosectued at only one location at a time other than to delay the completion of the project?
|
34
Q:08/09/2010
R:08/10/2010 |
Plan Sheet / Specification
Reference= Bid Item #32, Develop Construction Water
Question= Upon our review of the information provided in the materials handout associated with this item (IID Letter dated July 8, 2009), our interprutation is that Caltrans is providing the water source at no cost to the contractor and the contractor is responsible for supplying Caltrans with pump and appurtenances information so the EP can be perfected. Is this correct?
- No, the letter intended only to say the water is available. Contractor will need to obtain a permit from IID and pay for the water in accordance with section 17 "WATERING" of the standard specifications.
|
35
Q:08/10/2010
R:08/11/2010 |
Plan Sheet / Specification
Reference= Concrete Pavement
Question= Section 11-1, subsection 40-2.01D "Mix Proportions" spcifies that lab studies for mix design development in regards to water cementitious ratio must be 3.9 Mpa at 28 days and 4.5 Mpa at 45 days.
Section 11-1, subsection 40-1.03L "Engineer's Acceptance" specifies the minimum modulus of rupture for each lot is 3.9 MPa at 28 days.
Section 11-1, subsection 40-2.01E "Field Qualification" specifies that in order for the mix to be field qualified, the average strength of five beams must be at least 4.5 MPa at the age chosen by the Contractor, but not later than 28 days.
The specifications have always required 3.9 MPa or 565 psi for field qualification and material acceptance. The current English Unit version of the Standard Specification template for Section 40, from which Section 11-1 of this contract is derived, also requires 565 psi for field qualification. See the current version at http://www.dot.ca.gov/hq/esc/oe/specifications/SSPs/2006-SSPs/Updates/2010-07_updates/S1-020H_E_A07-30-10.doc
If 4.5 Mpa (650 psi) is required to field qualify, contractors will be forced to increase cement contents by as much as 1 sack/cy. This will drive up the cost of concrete accordingly. This cost is unnecessary since the acceptance criteria is only 3.9 Mpa. If Caltrans is looking for more durable pavement, this should be accomplished by adding thickness, not strength.
The Question is, will the engineer accept the concrete as being field qualified if the average strength at the age selected for testing, not later than 28 days, is at least 3.9 Mpa?
- Please
bid per current contract documents.
|
36
Q:08/11/2010
R:08/11/2010 |
Plan Sheet / Specification
Reference= Concrete Pavement
Question= Is it necessary for us to obtain railroad insurance on this project?
- Railroad insurance is only necessary when work is preformed within 50 feet of the Railrod Right of Way.
|
37
Q:08/11/2010
R:08/11/2010 |
Plan Sheet / Specification
Reference= Concrete Pavement
Question= Do you have a good phone number and contact for IID? The numbers within the handout are disconnected. The handout also references an industrial water rate per their schedule #7. Can you provide us with this rate amount?
- IID contact information is as follows
- Randy Gray 760-339-9240
Tony Montesinos 760-482-9900
- David Escobar is Project Manager for the IID Water relocations
760-339-9747 Phone
- IID Water rate info can be found at:
http://www.iid.com/Water/WaterRateSchedules
|