BIDDER'S INQUIRIES & RESPONSES
DISTRICT 11 CONSTRUCTION
CONTRACT NO:  11-091804
ROUTE / KP 11-SD-905-Various
LOCATION In San Diego County In San Diego On Route 905 From 0.2 Km West Of Route 805/905 Separation And From Airway Road To Otay Mesa Border Crossing And On Route 805 At Palm Avenue Overcrossing.
DESCRIPTION Construction Of Interchange. -DESIGN SEQUENCING PILOT PROJECT-
ESTIMATE $ 14,792,000.00
ADVERTISE DATE 08/12/02
BID OPENING 09/19/02
FINAL POSTING 09/19/02    @   12:00  FINAL POSTING TO BE DONE TOMORROW AT 12 NOON 

BID RESULTS
  1 
FCI CONSTRUCTORS, INC $ 13,520,701.00
2
COFFMAN $ 13,665,000.00
3
ERRECA'S/ HANSON SJH $ 14,199,179.00
4
EL YEAGER CONSTRUCTION CO $ 14,950,463.00
5
HAZARD CONSTRUCTION CO $ 15,964,317.00

The Caltrans District 11 Office is located at 2829 Juan Street, San Diego, CA 92110. The mailing address is P.O. Box 85406, San Diego, CA 92186-5406. The District 11 Duty Senior telephone number is (619) 688-6635. Please submit all inquiries in the proper format by fax to (619) 688-6988 or e-mail to:
Duty_Senior_Const_District11@dot.ca.gov.
The responses to bidder' inquiries, unless incorporated into a formal addenda to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The responses may be considered along with all other information furnished to prospective bidders for the purpose of bidding on the project. The availability or use of information provided in the responses to bidder' inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.
Caltrans District 11 Construction Department has developed this method of answering Bidder's Inquiries to better serve the needs of the Contractors who bid on our Projects. Caltrans District 11 Construction Department will post all of the questions submitted by any of the contractors that are registered Planholders for that Contract, but reserves the right to not answer any questions deemed unsatisfactory for public viewing.
The BIDDER'S INQUIRIES & RESPONSES will be updated continuously and all attempts will be made to do the final posting by 12:00 on the Wednesday prior to the bid opening day.

INFORMATION AVAILABLE
 FACT SHEET
BID ITEMS
SPECIALS
 PLANS
 PLANHOLDERS
MIBs
CROSS SECTIONS
     

ADDENDUM

 ADDENDUM NO. 1
09/06/02
 ADDENDUM NO. 2
09/13/02
 
   

BIDDER'S INQUIRY SUBMITTAL FORM

Inquiry No.
Inquiry
1
Q:08/12/02
R:08/19/02
Plan Sheet / Specification Reference=NOTICE TO CONTRACTORS

When will the cross sections be available and where?

  • Cross sections will be available as of 08/19/02 and can be downloaded for printing at any local printing firm:  
       MESA BLUEPRINT
       5560 Ruffin Road Suite 5
        San Diego, CA 92123
       (858) 541-1500    FAX (858) 278-0558
       e-mail to  plot@mesablueprint.com San Diego, CA 92123
 2
Q:08/12/02
R:08/12/02
Plan Sheet / Specification Reference=

Is there a local printing firm to order full size plans from?

  • The plans can be downloaded through the link above and can be printed at any local printing firm. 
       MESA BLUEPRINT
       5560 Ruffin Road Suite 5
       San Diego, CA 92123
       (858) 541-1500    FAX (858) 278-0558
       e-mail to  plot@mesablueprint.com
3
Q:08/19/02
R:08/22/02
Plan Sheet / Specification Reference= Item 26 Remove Traffic Stripe and Pavement Marking

Item 26 Remove Traffic Stripe and Pavement Marking, unit of measure is by the Meter. 
Should this be changed to M2?

  • Per Section 15-2.06 of the Standard Specifications either method is allowable, therefor it shall be measured by the M.
 4
Q:08/20/02
R:08/22/02
Plan Sheet / Specification Reference=Special Provisions Section 1 

In what method will the additional phases be provided? Will they be considered as an "ordered change" per Section 4-1.03 of the Standard Specifications?

  • SEE ADDENDUM NO. 1
 5
Q:08/21/02
R:09/10/02
Plan Sheet / Specification Reference= NOTICE TO CONTRACTORS

Can a pre-bid meeting be held to discuss Design Sequencing? 

 6
Q:08/21/02
R:08/22/02
Plan Sheet / Specification Reference= MATERIALS INFORMATION

Is there any geotechnical information available?

  • Yes, it has been uploaded today - see link above.
 7
Q:08/22/02
R:08/23/02
Plan Sheet / Specification Reference=Items 22 & 23. Abandon RCB and Culverts.

Please provide details to sizes, locations. There is no way to project a cost with the data supplied by Caltrans at this time.

  • Due to the Design Sequencing bid process there will be no further information provided before bid opening. 
8
Q:08/26/02
R:09/10/02
Plan Sheet / Specification Reference=SPECIALS SECTION 10-1.33 EARTHWORK

PARAGRAPH 2 STATES: The Contractor shall remove the top 0.6 meter of existing soil within the roadbed prism.  The next 0.3 meter shall be scarified, moisturized, and compacted to 90 percent. After the 0.3 meter has been compacted to 90 percent the Contractor shall replace the 0.6 meter and compact in accordance with Section 19-5...

Is any of this removal, scarification, etc. to be measured and paid as roadway excavation?

  • The 0.6 M of removal is included in the roadway excavation item quantity, the compaction as required per Section 10-1.33 of the Special Provisions is included as defined in Section 19-5.06 PAYMENT of the Standard Specifications. 
 9
Q:08/26/02
R:08/27/02
Plan Sheet / Specification Reference=SPECIALS SECTION 10-1.33 EARTHWORK

PARAGRAPH 6 STATES: At the location and to the limits shown on the plans, expansive soil materials shall not be placed as part of the embankment for the full width of the embankment. 
Expansive soil = EI greater than 50 or a sand equivalent less than 20.

Where are these locations and limits shown on the plans?

  • Due to the Design Sequencing bid process there will be no further information provided before bid opening. 
10
Q:08/27/02
R:09/10/02
Plan Sheet / Specification Reference=PLAN SHEET X-2, TYPICAL CROSS SECTIONS;
AND PLAN SHEET Q-1, SUMMARY OF QUANTITIES.

There are typical sections for the "WESTBOUND NORTH CONNECTOR" and the "EASTBOUND NORTH CONNECTOR".  What about the SOUTH CONNECTORS?

There is no accounting for the quantities involved in the Structural Section for the any of the temporary connectors on the "Q" sheets.  Are the quantities involved in the structural section of the temporary connectors to be measured and paid?

  • Yes, the temporary connector quantities as shown on sheet 71 of 180 DETOUR DE-2 are included in the "SVR", "SV3" and "SV4".
11
Q:08/29/02
R:09/05/02
Plan Sheet / Specification Reference=Bid Opening

We request that the Bid Opening be revised to a later date, preferably a minimum of one week, September 26, 2002 to provide time between bids in Districts 4, 8 & 11.
Because the 905 project is a "Design Sequencing Contract", additional effort and time is required for developing an Estimate. The design portion in conjunction with the normal quantifying and estimating function's increases the work effort by approximately 30%. 
Please assist us by revising and sequencing these Bid openings so that we may assist you with complete and accurate estimates for your projects. 

  • No. 
12
Q:09/05/02
R:09/05/02
Plan Sheet / Specification Reference=Retaining Wall "W1" sheets 87 & 88.

Length of wall using stationing is 165.416 Meters, adding length along LOL is 158.4 Meters.
Which is correct and if the stationing is correct please provide design height for the missing wall section.

  • The dimensions shown on sheet 87 of 180 'R-1' are incorrect, the total length of 165.60 is accurate. 

  • REVISED SHEET 87 R-1
13
Q:09/06/02
R:09/06/02
Plan Sheet / Specification Reference=Addendum No. 1 / Closure Chart No.8

How do you expect the contractor to erect falsework using a chart that can only be used for falsework removal. Also considering that the Border is closed every night from 10 pm until 6am, and why do you limit the charts use to four times only? 

  • Chart No. 8 shall be revised by CCO to allow use for erection of the falsework and the maximum times shall be deleted. 
14
Q:09/06/02
R:09/10/02
R:09/11/02
R:09/12/02
Plan Sheet / Specification Reference=page 133-134, special provisions. Contract plans SC-5 sheet 66/180

The Traffic openings of 19.5 M SB & 16.8 M NB do not match the traffic configuration shown on the stage drawing. The stage drawing show two lanes of traffic for the Northbound and Southbound direction this would be 3.6 + 3.6 + 2.5 for a shoulder = 9.7 M . Why do the special provision require a different dimension ? 
Do we build in accordance with the staging drawings or the special provisions.

  • The Special Provisions prevail in accordance with Section 5-1.04 COORDINATION AND INTERPRETATION OF PLANS, STANDARD SPECIFICATIONS, AND SPECIAL PROVISIONS of the Standard Specifications. A CRIP may be proposed to allow for a narrower width in accordance with Section 5-1.019 COST REDUCTION INCENTIVE of the Special Provisions. 
  • SEE ADDENDUM NO. 2
15
Q:09/10/02
R:09/11/02
Plan Sheet / Specification Reference=ITEM 55, TRANSPLANT PALM TREES, PLAN SHEET 94-103, SECTION 10-1.39

The relocated palm trees will require watering for the maintenance period.  Will it possible for the contractor to utilize existing state owned irrigation facilities as a source of water at the destination sites?

  • Yes, the State shall be responsible for the source of water at the destination. 
16
Q:09/10/02
R:09/12/02
Plan Sheet / Specification Reference=PLAN SHEET Q-3, (84 of 180): 
In the earthwork quantities, there is a line entitled "*CLEARING AND GRUBBING REMOVAL" with a quantity of 15,393 M3, with the note by the asterisk below as "*0.15 m depth". The special provision sections on Clearing and Grubbing and Earthwork are silent on this issue.

Do the contract documents REQUIRE the stripping and disposal of 0.15M of material from the entire surface of the project, or is this an estimate and an attempt to provide for the possibility of such loss of earth materials with sufficient borrow quantity allowed?

  • SEE ADDENDUM NO. 2
17
Q:09/11/02
R:09/12/02
R:09/18/02
Plan Sheet / Specification Reference= Minor Structures, drainage sheets D-1 thru 26. 

Which pages govern the construction of the minor boxes.  Sheets D-7 thru D-16 have different boxes than the summary sheets D-23 thru D-26. Section shown on sheet D-20 reference DU 5k.  Sheet D-13 calls DU 5k to be a G-2.

  • In accordance with Section 5-1.04 COORDINATION AND INTERPRETATION OF PLANS, STANDARD SPECIFICATIONS, AND SPECIAL PROVISIONS of the Standard Specifications the information shown on the DRAINAGE PROFILE sheets prevail over the information shown on the DRAINAGE SUMMARY sheets. 
  • See also Section 9-1.015 FINAL PAY ITEMS of the Standard Specifications.
18
Q:09/13/02
R:09/16/02
Plan Sheet / Specification Reference=Special provisions 10-1.44 Para "Dowel Placement"

States dowels shall be placed as shown on the plans.
Are transverse dowels required in the shoulders?

  • Yes transverse dowels are required in the shoulders as shown on contract plan sheet 131 of 180 - Revised Standard Plan RSP A35B.

  • Sheet 13 - RSP A35B
19
Q:09/13/02
R:09/16/02
Plan Sheet / Specification Reference= Plan Sheet 84 of 180, "Earthwork Quantities", Ref Question 16

Adding up these quantities with the quantity for clear and grub is 104,156 M3. There seems to be a bust in the excavation item which has a quantity of 88,800 M3.
Which is correct?

  • See Addenda No. 2, the payment for the quantity 15,393 M3 is included in Item 34: CLEARING AND GRUBBING. 
20
Q:09/13/02
R:09/16/02
Plan Sheet / Specification Reference=Special Provision Section 10-1.13 - Computer Equipment and Software

In sub-paragraph A of the above referenced section there is a requirement for server systems with dual Pentium IV processors.  Pentium IV processors will not function in a dual processor system.  If you put two P4 processors in a system, the second chip will be ignored.  The fastest processor available that will function in a dual processor system is the Pentium III 1.4 GHz chip.  Will this be acceptable?

  • The specification for sub-paragraph A states:"....., or equal." therefore an alternative equal processor system is acceptable. 
21
Q:09/16/02
R:09/18/02
Plan Sheet / Specification Reference=Highway Planting Cost Breakdown (Special Provisions page 202)Plant (Group Z(A),(B),& (C)). 
Plan sheet #94 plant list and planting specifications Plant Group Z (A,B & C)and detail for Palm Tree Sizing.

Why three different groupings for the palm trees? 

Are they different species?

If they are which species goes with what plant group? 

How many at what size in each plant group?

How do we come up with a legitimate price for these items?

  • Due to the Design Sequencing bid process there will be no further information provided before bid opening. 
22
Q:08/27/02
Q:09/17/02
R:09/18/02
Plan Sheet / Specification Reference=Page 202 of Special Provisions / Sheet #94

Page 202 of the Special Provisions lists several thousand plants in (9) nine different plant groups. Sheet # 94 (HP-1 PLANT LIST) also refers to the same plant items but lack the botanical name or common name for the plant type. Please advise if this will be addressed by addendum. 

  • No, due to the Design Sequencing bid process there will be no further information provided before bid opening. 
23
Q:09/18/02
R:09/18/02
Plan Sheet / Specification Reference=Bid Item #. 82 BAR REINFORCING STEEL (RET. WALL) 

The takeoff qty for the wall is approximately twice the "final pay" quantity on a normal job we would bid take takeoff with little concern. With the current bid format however, is this item really final pay in that the design is not final nor the plans signed? Please advise.

  • Agreed the actual quantity is approximately twice the pay quantity but it is FINAL PAY. So, regardless of the method of bid process or unsigned plans the Standard Specifications still prevails in regard to final pay items, therefore the determination of actual quantity can be obtained based on the plan sheets and the quantity listed shall be used for payment in accordance with Section 9-1.015 FINAL PAY ITEMS. 

OTHER LINKS OF INTEREST