| CONTRACT NO: | 11-288404 |
| ROUTE / KP | 11-SD-52,805-2.6/5.9, 22.5/24.5 |
| LOCATION | In San Diego County In San Diego On Route 52 From 0.3 Mile East Of Genesee Avenue Undercrossing To 0.4 Mile East Of Convoy Street Overcrossing And On Route 805 From 0.1 Mile South Of Clairemont Mesa Overcrossing To 0.1 Mile North Of Governor Drive Undercrossing. |
| DESCRIPTION | Irrigation System Conversion To Recycled Water. |
| ESTIMATE | $ 490,000 |
| WORKING DAYS | 370 |
| ADVERTISE DATE | 04/14/2008 |
| BID OPENING | 05/15/2008 |
| FINAL POSTING | 05/14/08
@ 1505 |
The Caltrans District
11
Office is located at 4050 Taylor Street, San Diego, CA 92110. The
District 11
Duty
Senior telephone number is (619) 688-6635. Please submit all inquiries
in the proper format by fax to (619) 688-6988 or e-mail to:
Duty_Senior_Const_District11@dot.ca.gov.
The responses to
bidder' inquiries, unless incorporated into a formal addenda to the
contract,
are not a part of the contract and are provided for the bidder's
convenience
only. In some instances, the question and answer may represent a
summary
of the matters discussed rather than a word-for-word recitation. The
responses
may be considered along with all other information furnished to
prospective
bidders for the purpose of bidding on the project. The availability or
use of information provided in the responses to bidder' inquiries is
not
to be construed in any way as a waiver of the provisions of Section
2-1.03
of the Standard Specifications or any other provision of the contract,
the plans, Standard Specifications or Special Provisions, nor to excuse
the contractor from full compliance with those contract requirements.
Bidders
are cautioned that subsequent responses or contract addenda may affect
or vary a response previously given.
Caltrans District 11 Construction
Department
has developed this method of answering Bidder's Inquiries to better
serve
the needs of the Contractors who bid on our Projects. Caltrans District
11 Construction Department will post all of the questions submitted by
any of the contractors that are registered Planholders for that
Contract,
but reserves the right to not answer any questions deemed
unsatisfactory
for public viewing.
The BIDDER'S
INQUIRIES
& RESPONSES will be updated continuously and all attempts will be
made
to do the final posting by 15:00 on Wednesday prior to the bid opening.
INFORMATION
AVAILABLE
|
|
|
|
|
|
BIDDER'S INQUIRY SUBMITTAL FORM
|
|
Inquiry |
|
1
Q:05/07/08 |
Plan Sheet / Specification
Reference= DVBE requirements for performing a Commercially Useful
Function
Question=Regarding the
"Commercially Useful Function (CUF)" requirement, do temporary workers
supplied by a DVBE, and who work directly on the jobsite, qualify as a
CUF?
|
|
2
Q:05/12/08 |
Plan Sheet / Specification
Reference= Compliance with DVBE Commercially Useful Function
requirements
Question= Would like you to
clarify for prime bidders that hiring a DVBE subcontractor to supply
temporary workers for this job satisfies the Commercially Useful
Function criteria, in that the workers will be "...responsible for
performing a distinct element of the work and carry out its
responsibility by actually performing...the work."
|
|
3
Q:05/14/08 |
Plan Sheet / Specification
Reference= Item 32 (Water Meter); Special Provision Section: 10-2.05
Irrigation System pg 177
Question= According to pg 177
of the specs the contractor is required to pay the installation costs
of the water meter. Since the contractor is installing the meter is the
contractor also required to pay the costs of water during the plant
establishment period?
|