| CONTRACT NO: | 11-272504 |
| ROUTE / KP | 11-SD-94-3.3 |
| LOCATION | In San Diego County In San Diego At Chollas Creek Bridge |
| DESCRIPTION | Rebuild Concrete Channel. |
| ESTIMATE | $ 350,000 |
| WORKING
DAYS |
30 |
| ADVERTISE DATE | 07/28/2008 |
| BID OPENING | 08/28/2008 09/11/2008 |
| FINAL POSTING |
09/10/08 @
1605 |
The Caltrans District
11
Office is located at 4050 Taylor Street, San Diego, CA 92110. The
District 11
Duty
Senior telephone number is (619) 688-6635. Please submit all inquiries
in the proper format by fax to (619) 688-6988 or e-mail to:
Duty_Senior_Const_District11@dot.ca.gov.
The responses to
bidder' inquiries, unless incorporated into a formal addenda to the
contract,
are not a part of the contract and are provided for the bidder's
convenience
only. In some instances, the question and answer may represent a
summary
of the matters discussed rather than a word-for-word recitation. The
responses
may be considered along with all other information furnished to
prospective
bidders for the purpose of bidding on the project. The availability or
use of information provided in the responses to bidder' inquiries is
not
to be construed in any way as a waiver of the provisions of Section
2-1.03
of the Standard Specifications or any other provision of the contract,
the plans, Standard Specifications or Special Provisions, nor to excuse
the contractor from full compliance with those contract requirements.
Bidders
are cautioned that subsequent responses or contract addenda may affect
or vary a response previously given.
Caltrans District 11 Construction
Department
has developed this method of answering Bidder's Inquiries to better
serve
the needs of the Contractors who bid on our Projects. Caltrans District
11 Construction Department will post all of the questions submitted by
any of the contractors that are registered Planholders for that
Contract,
but reserves the right to not answer any questions deemed
unsatisfactory
for public viewing.
The BIDDER'S
INQUIRIES
& RESPONSES will be updated continuously and all attempts will be
made
to do the final posting by 15:00 on Wednesday prior to the bid opening.
INFORMATION
AVAILABLE
|
|
|
|
|
|
ORDERING PROJECT PLANS AND SPECIFICATIONS
ADDENDUM
|
|
BIDDER'S INQUIRY SUBMITTAL FORM
|
|
Inquiry |
|
1
Q:08/07/08 |
Plan Sheet / Specification
Reference= SPECIAL PROVISION SECTION 10-1.07 PAGE 34 Question= THE SECOND PARAGRAPH
STATES "THE SOIL LABORATORY DATA FROM CHOLLAS
|
|
2
Q:08/07/08 |
Plan Sheet / Specification
Reference= 17 Concrete (Channel Lining) Question= Are you allowing shotcrete for this work?
|
|
3
Q:08/07/08 |
Plan Sheet / Specification
Reference= section 5-1.03 Information at the district office Question= Who do I contact to see the information listed on page 5? Is the SDRWQCB permit in place to do this work?
|
|
4
Q:08/07/08 |
Plan Sheet / Specification
Reference= Plan Sheet No. 8 of 10 CS-1 Question= See detail titled "TYPICAL - PLACEMENT OF TRAFFIC PLASTIC DRUM" Where on the job does this detail apply?
|
|
5
Q:08/07/08 |
Plan Sheet / Specification
Reference= Sheet 2 of 10 C-2 Question= This plan sheet
shows Exist 36" RCP and Exist AC DITCH. How do these facilities
interface with the existing channel and how do they tie in to the new
channel? Are details and bid items required?
|
|
6
Q:08/11/08 |
Plan Sheet / Specification
Reference= Item No. 16 & 17 Question= Item #16 - Page 54 of Special Provisions list Magnesium Phosphate based concrete and modified high alumina based concrete to be placed before overlay. Does this placement take place before or after the methacrylate resin prime coat
Item #17 - Is concrete for channel lining Minor Concrete? If not then what class concrete?
|
|
7
Q:08/15/08 |
Plan Sheet / Specification
Reference= Question= ON A PREVIOUS
QUESTION ASKING ABOUT THE USE OF SHOTCRETE THE ANSWER
|
|
8
Q:08/22/08 |
Plan Sheet / Specification Reference= Item #16 Place Polyester Concrete Overlay. Question=Will there be a need for spall repair prior to placing
the poly concrete and if so, how will that be paid?
|
|
9
Q:08/26/08 |
Plan Sheet / Specification
Reference= Question= 1. Is this to be a monolithic pour?