BIDDER'S
INQUIRIES & RESPONSES
DISTRICT
11 CONSTRUCTION
MANDATORY PREBID MEETING FOR CONTRACT 11-267304 IS ON TUESDAY, DECEMBER 18, 2007 AT THE FOLLOWING LOCATION: 4050 TAYLOR STREET, SAN DIEGO, CA 92110
MEETING WILL BE HELD AT BUILDING 1, FLOOR 1, ROOM 134 (GALLEGOS CONFERENCE ROOM), FROM 9:00 A.M. - 12:00 P.M.
PLEASE CALL (619) 688-6635 OR (858) 688-1522 WITH QUESTIONS.
| CONTRACT NO: | 11-267304 |
| ROUTE / KP | 11-SD-52-7.4/13.3 |
| LOCATION | In San Diego County In San Diego From 0.1 Mile East Of 52/15 Separation To Mast Boulevard Undercrossing. |
| DESCRIPTION | Widen Freeway |
| CONTRACT TYPE |
A + B Bidding |
| ESTIMATE | $ 26,000,000 |
| WORKING
DAYS |
570 (250 Working Days Min. Type 2 Plant Establishment) |
| ADVERTISE DATE | 10/29/2007 |
| BID OPENING | 01/03/2008 |
| FINAL POSTING | 01/02/08
@ 15:10 |
The Caltrans District
11 Office is located at 4050 Taylor Street, San Diego, CA 92110. The
District 11
Duty
Senior telephone number is (619) 688-6635. Please submit all inquiries
in the proper format by fax to (619) 688-6988 or e-mail to:
Duty_Senior_Const_District11@dot.ca.gov.
The responses to
bidder' inquiries, unless incorporated into a formal addenda to the
contract,
are not a part of the contract and are provided for the bidder's
convenience
only. In some instances, the question and answer may represent a
summary
of the matters discussed rather than a word-for-word recitation. The
responses
may be considered along with all other information furnished to
prospective
bidders for the purpose of bidding on the project. The availability or
use of information provided in the responses to bidder' inquiries is
not
to be construed in any way as a waiver of the provisions of Section
2-1.03
of the Standard Specifications or any other provision of the contract,
the plans, Standard Specifications or Special Provisions, nor to excuse
the contractor from full compliance with those contract requirements.
Bidders
are cautioned that subsequent responses or contract addenda may affect
or vary a response previously given.
Caltrans District 11 Construction
Department
has developed this method of answering Bidder's Inquiries to better
serve
the needs of the Contractors who bid on our Projects. Caltrans District
11 Construction Department will post all of the questions submitted by
any of the contractors that are registered Planholders for that
Contract,
but reserves the right to not answer any questions deemed
unsatisfactory
for public viewing.
The BIDDER'S
INQUIRIES
& RESPONSES will be updated continuously and all attempts will be
made
to do the final posting by 15:00 on Wednesday prior to the bid opening.
INFORMATION
AVAILABLE
| CROSS SECTIONS |
|
|
|
|
| PREBID SIGN-IN SHEET | INFORMATION HANDOUT |
BIDDER'S INQUIRY SUBMITTAL FORM
|
|
Inquiry |
|
1
Q:11/07/07 |
Plan Sheet / Specification
Reference= Special Provision Section 5-1.17 Project Information
Question= Special Provision
Section 5-1.17 Project Information page 96, states that cross sections
are available in electronic copy. When will the cross sections be
available and in what format?
MESA REPROGRAPHICS 5560 Ruffin Road Suite 5 San Diego, CA 92123 (858) 541-1500 FAX (858) 278-0558 e-mail to plot@mesareprographics.com San Diego, CA 92123 |
2
Q:12/04/07 R:12/10/07 |
Plan
Sheet / Specification
Reference= Special Provisions; Section 7: Legal Relations and
Responsibilites; page 15. Question= In ¶7-1.12B, “Insurance”, the Amendments to May 2006 Standard Specifications contains a sub-paragraph ¶7-1.12B(2) entitled “Casualty Insurance”. Is “Casualty Insurance” a separate insurance product required by CALTRANS or is this sub-paragraph simply a reference to what the general requirements are for “Workers’ Compensation and Employer’s Liability Insurance” (sub-paragraph 7-1.12B(3)) and for “Liability Insurance” (sub-paragraph 7-1.12B(4)?
|
3
Q:12/05/07 R:12/10/07 R:12/12/07 |
Plan
Sheet / Specification
Reference= Special Provisions Sections 10-1.18, 10-1.25, 10-1.68 Question= Does the existing Concrete Barrier (Type K) to be removed under Contract Item 40 meet the criteria for use as Temporary Railing (Type K) to be installed under contract Item 21? Will the same existing Concrete Barrier (Type K) meet the requirements for use as Concrete Barrier (Type K) to be installed under Contract Item 98?
|
4
Q:12/07/07 R:12/10/07 |
Plan
Sheet / Specification
Reference= Proposal and Contract Question= Will the State of California Department of Transportation accept an electronic bid proposal? Can a Contractor submit the bid proposal bid item pages in a duplicated format typed and/or handwritten? For the LUMP SUM bid items, which have the words LUMP SUM prefilled in the "Unit Price" column, is it a requirement to also provide the lump sum price in dollars/cents under the words LUMP SUM?
|
| 5 Q:12/07/07 R:12/10/07 |
Plan
Sheet / Specification
Reference= Bid Opening: 01/03/2008 Question= Would the State consider extending the bid opening one week?
|
| 6 Q:12/11/07 R:12/11/07 |
Plan
Sheet / Specification
Reference=
|
| 7 Q:12/18/07 R:12/20/07 |
Plan
Sheet / Specification
Reference= Question= No section showing location of the temp. k-rail & Bridge rail at Spring & Oak. Is there enough room for both temp rail & pay rail?
|
| 8 Q:12/18/07 R:12/24/07 |
Plan
Sheet / Specification
Reference= Question= Are there requirements for collecting traffic data during construction i.e. collecting data on volume/speed/occupancy.
|
| 9 Q:12/18/07 R:12/20/07 |
Plan
Sheet / Specification
Reference= Question= Do subs that are not here meet requirements of project
|
| 10 Q:12/18/07 R:01/02/08 |
Plan
Sheet / Specification
Reference= Item 67, Concrete Pavement, L-16 & 17, L-19&20 Question= The PCC pavement end anchor stations are the same as the "begin bridge" and "end bridge" stations, leaving no room for an approach slab at either end of Oak Canyon bridge. At the west end of Spring Canyon bridge the plans allow 14' for an approach slab, at the East end the plans allow 4.5'. Please verify the PCC start and end stations at the bridges.
|
| 11 Q:12/21/07 R:12/24/07 |
Plan
Sheet / Specification
Reference= Plan Sheet X-1 thry X-4 Question= The existing bike lane is not delineated on the project plans. Please indicate where the current bike lanes are on the projectincluding exact locations and minimum widths.
|
| 12 Q:12/21/07 R:01/02/08 |
Plan
Sheet / Specification
Reference= Special Provisions section 10-1.20 - Maintaining Traffic Question= Traffic Chart No. 3 allows a shoulder closure throughout the duration of the project. If the current bike lane is in the shoulder does this include the closure of the bike lane for the duration of the contract? If not please add provisions to correct this chart. Traffic Chart No. 4 allows the closure of NB/SB Santo Road but the limits are from JCT RTE 78 to Shank Rd. Please review the limits indicated as they do not appear to be applicable to this project.
|
| 13 Q:12/21/07 R:12/21/07 |
Plan
Sheet / Specification
Reference= Specification Section 10-1.42 Asphalt, subsection
"Longitudinal Joints" page 183 and 184 Question= If Contractor does NOT construct longitudinal joints with a tapered notch wedge, will Engineer still be testing for joint compaction, will Contractor still be required to obtain cores for testing, and will material in joint be subject to reduced compensation? Or do these requirements only apply if a tapered notch wedge method is used?
|
| 14 Q:12/21/07 R:01/02/08 |
Plan
Sheet / Specification
Reference= Bid Items 99,100,101,102,103 Various special provisions and
plans including Construction detail sheets C9, C10, C12, C13 and C14;
and Quantity Summary plan sheets Q6, Q8, Q9 and Q10. Question= Request that an addendum be issued with clarification, additional details, revised special provisions and ammended bid quantities that will clarify the current ambiguity of the contract documents for Metal Beam Guard Rail, Thrie Beam Barrier and associated work.
|
| 15 Q:12/21/07 R:12/28/07 |
Plan
Sheet / Specification
Reference= Special Provision Section 10-1.33 - Controlled Low Strength
Material Contract Plan Sheet #137 - Drainage Details &
Contract Plan Sheet #234 - Summary of Quantities Question= The pipe excavation in shoulder detail located on sheet 137 indicates that the contractor shall excavate 2' clear on boths sides of the storm drain and slope as needed to reach the finished grade. If Section 10-1.33 - Controlled Low Strength Material allows the contractor to excavate 6 inches clear on boths sides of the storm drain and slope as needed to reach the finished grade. This creates a 3' trench patch in the existing 8' wide shoulder. Plan Sheet 234 - Summary of Quantities seems to indicate that Caltrans wants the enitre shoulder repaved in the area that drainage is installed. Will the contractor be allowed to just trench patch the 3' wide trench or will the entire 8' shoulder need to be repaved? If Caltrans requires the entire 8' shoulder to be repaved, how is the additional AC & Base excavation paid for?
|
| 16 Q:12/26/07 R:12/26/07 |
Plan
Sheet / Specification
Reference= Various Question= Please provide a listing of the prospective bidders who attended the mandatory pre-bid meeting, who are now the only prospective bidders whose bids will be accepted.
|
| 17 Q:12/26/07 R:01/02/08 |
Plan
Sheet / Specification
Reference= Item 68, page 194, paragraph 1-6 Question= The description under the heading " liquid joint sealant installation" refers to silicon sealant for sealing pavement joints. However, about 2/3 page down it describes the use of compression seal. Which type is approved, silicon or compression seal? Please clarify.
|
| 18 Q:12/26/07 R:12/27/07 |
Plan
Sheet / Specification
Reference= Construction Detail Sheet C-11 Question= Sheet C-11 shows "MBGR posts in PCC or AC" but then identifies the surrounding pavement as PCC. Is this detail intended to apply to the 1,100 or so posts to be set in existing AC shoulder?
|
| 19 Q:12/27/07 R:01/02/08 |
Plan
Sheet / Specification
Reference= Item 83 & 84 drainage profiles Question= During installation of the alternative pipe culvert the existing slotted pipe needs to be removed to install the new drainage profiles. If we have to replace the slotted pipe where the new grated line drain is not showing what gage is the pipe and can we use the existing pipe? If removed in good condition, do we add the cost to replace the pipe on the new drainage item?
|
| 20 Q:12/26/07 R:01/02/08 |
Plan
Sheet / Specification
Reference= ITEM 44, CLEAR & GRUBB, (SECTION 10-1.30), and MIGRATORY
BIRDS (SECTION 5-1.21). There is language
in the two referenced sections regarding activities before and after
February 15. Question= With a bid date of January 3, given the typical award, approval, and SWPPP submittal process, the probability of the contractor meeting the requirements of the above referenced sections is extremely remote. At the MANDATORY PRE-BID MEETING, a statement was made that the Caltrans maintenance department would perform the clearing and grubbing of the project in order to meet the February 15 deadline. We have seen no minutes of the meeting to provide assurance to the contractors that this commitment has been made. This issue is too important to rely on a brief verbal statement that could be subject to mis-understanding, mis-interpretation, or even mis-statement. PLEASE AFFIRM THIS IN WRITING AS AN ANSWER TO THIS QUESTION.
|
| 21 Q:12/28/07 R:12/31/07 |
Plan
Sheet / Specification
Reference= Various Thrie Beam Barrier and appurtenanaces. Question= Ref Special Provision Section 5-1.16- Confirm that the various Thrie Beam Barrier and appurtenances will be included in payment as materials furnished but not incorporated in the work.
|
| 22 Q:12/31/07 R:01/02/08 |
Plan
Sheet / Specification
Reference= Bid item #70, sec. 10-1.44 Grind Existing Concrete Pavement. Question= Per the description in the Specials, the grinding is to be performed full lane width. The quantities per the bid item and plans show grinding 3' wide. Is it the State's intent to only grind 3' wide? Also, the grinding areas match the isolation joint except for one location that is missing from sta 476+40.95 - 551+83.61. Should this location be added to the grinding quantity on bid item #70?
|
| 23 Q:12/31/07 R:01/02/08 |
Plan
Sheet / Specification
Reference= On the cover of the Special Provisions is stamped
"INFORMATION HANDOUT" and mentioned in section 5-1.17, "PROJECT
INFORMATION" is A. Water Source Information and B. Corrosion
Recommendations. Question= We don't seem to have received an "INFORMATION HANDOUT" or else the dog ate it. Please post it on-line.
|
| 24 Q:01/02/08 R:01/02/08 |
Plan
Sheet / Specification
Reference= Question= The contract documents do not provide information for existing site conditions below the existing finish grade. Please confirm that all areas of the contract work will NOT require rock or non-rippable excavations which would require any type of drilling, splitting, blasting, hoe-ramming and ripping.
|