| CONTRACT NO: | 11-2358U4 |
| ROUTE / KP | 11-SD-5-R57.4/R61.98-R16.0/N17.6 |
| LOCATION | In
San Diego County In San Diego, Solana Beach And Encinitas From San
Dieguito River Bridge To San Elijo Lagoon Bridge. |
| DESCRIPTION | Construct
Nb/sb Hov Lane In Median & Revise Interchange sphalt Rubber Open Graded Overlay. |
| A + B Bidding | |
| ESTIMATE | $ 40,000,000 |
| WORKING
DAYS |
890 (Minimum 250 days of
Plant Establishment) |
| ADVERTISE DATE | 05/07/2007 |
| BID OPENING | 06/28/2007 |
| FINAL POSTING | 06/27/07
@ 16:55 |
The Caltrans District
11
Office is located at 4050 Taylor Street, San Diego, CA 92110. The
District 11
Duty
Senior telephone number is (619) 688-6635. Please submit all inquiries
in the proper format by fax to (619) 688-6988 or e-mail to:
Duty_Senior_Const_District11@dot.ca.gov.
The responses to
bidder' inquiries, unless incorporated into a formal addenda to the
contract,
are not a part of the contract and are provided for the bidder's
convenience
only. In some instances, the question and answer may represent a
summary
of the matters discussed rather than a word-for-word recitation. The
responses
may be considered along with all other information furnished to
prospective
bidders for the purpose of bidding on the project. The availability or
use of information provided in the responses to bidder' inquiries is
not
to be construed in any way as a waiver of the provisions of Section
2-1.03
of the Standard Specifications or any other provision of the contract,
the plans, Standard Specifications or Special Provisions, nor to excuse
the contractor from full compliance with those contract requirements.
Bidders
are cautioned that subsequent responses or contract addenda may affect
or vary a response previously given.
Caltrans District 11 Construction
Department
has developed this method of answering Bidder's Inquiries to better
serve
the needs of the Contractors who bid on our Projects. Caltrans District
11 Construction Department will post all of the questions submitted by
any of the contractors that are registered Planholders for that
Contract,
but reserves the right to not answer any questions deemed
unsatisfactory
for public viewing.
The BIDDER'S
INQUIRIES
& RESPONSES will be updated continuously and all attempts will be
made
to do the final posting by 15:00 on Wednesday prior to the bid opening.
INFORMATION
AVAILABLE
| CROSS SECTIONS |
|
|
|
|
| SITE
INVESTIGATION REPORT |
ENVIRONMENTAL SITE ASSESSMENT |
BIDDER'S INQUIRY SUBMITTAL FORM
|
|
Inquiry |
|
1
Q:05/10/07 |
Plan Sheet / Specification
Reference=
Question= WHEN WILL THE CROSS SECTIONS BE AVAILABLE?
MESA BLUEPRINT 5560 Ruffin Road Suite 5 San Diego, CA 92123 (858) 541-1500 FAX (858) 278-0558 e-mail to plot@mesablueprint.com San Diego, CA 92123 |
|
2 Q:05/14/07 R:05/21/07 |
Plan
Sheet / Specification
Reference=Item 48 Roadway Excavation (Aerially Deposited Lead) Question= Page 143 of Specials..."ADL is deposited within unpaved areas or formally unpaved areas"... It doesn't appear to be shown on the plans. On the qty sheets it is just listed by station along the "SD5" line. The entire excavation staging is dependent on this information. When will cross-sections be available for download? Will you make the lead investigation report downloadable also?
|
| 3 Q:05/29/07 R:06/21/07 |
Plan
Sheet / Specification
Reference=section 10-1.67 of specials Question=PLEASE PROVIDE A DESCRIPTION OF THE FINSIH FOR "MURAL BASE"
|
4 Q:05/29/07 R:06/21/07 |
Plan
Sheet / Specification
Reference=SECTION 10-1.62 Question=LANE CLOSURE CHART 1 ALLOWS 8 HRS TO WORK ON I-5. THE TYPE R APPROACH SLAB REQUIRES 6 HRS CURE. THIS ALLOWS 2 HRS TO PERFORM ALL WORK NECESSARY TO INSTALL 1 LANE OF THE APPROACH SLAB. PLEASE REVISE SOMETHING BETWEEN THESE TO SECTIONS THAT WILL ALLOW THE INSTALLATION OF THE APPROACH SLAB.
|
5 Q:05/29/07 R:05/30/07 R:06/21/07 |
Plan
Sheet / Specification
Reference=Page 223 of Special Provisions Plan Sheets SC-7 and SC-11 Question=Traffic chart No. 6, Located on page 233 of the special provisions, states, "This chart shall be used one time only, for a maximum of 21 consecutive days." Does said chart pertain to stages 2A, 2C and 3A? Is the one time only language per stage?
|
6
Q:06/04/07 R:06/21/07 |
Plan
Sheet / Specification
Reference= Reference sheets 570 & 571 of 671 – Typical Section Question= The location of “LSF-2” line is shown incorrectly (see Sheets 551 & 552). Please revise accordingly.
|
7
Q:06/04/07
R:06/21/07 |
Plan
Sheet / Specification
Reference= TRAFFIC CHART 6 & 8 Question= TRAFFIC CHART 6 & 8 ALLOW FOR 1 LANE OF TRAFIC FOR A PERIOD OF 21 DAYS. THE PLANS DO NOT INDICATE WHAT WORK IS TO BE DONE DURING THIS CLOSURE. WE ARE RESPONSIBLE FOR DETERMINING THE NUMBER OF DAYS THIS CONTRACT RUNS. THE TYPE AND QUANTITY OF WORK TO BE PERFORMED DURING THESE TWO 21 DAY CLOSURES IS IMPORTANT IN DETERMINING THE NUMBER OF DAYS IN THE CONTRACT. CAN YOU TELL US, AT A MINIMUM, WHAT WORK IS SCHEDULED TO BE PERFORMED DURING THESE CLOSURES?
|
|
8 Q:06/05/07
R:06/21/07 |
Plan
Sheet / Specification
Reference= PLAN SHEET 554 Question= ON PLAN SHEET 554 THE CONSTRUCTION SEQUENCE, ITEMS 2 & 8 REQUIRE FALSEWORK TO REMAIN IN PLACE UNTIL THE GIDERS IN THE ADJECENT SPANS ARE SET AND THE DECK CONCRETE PLACED. I COULD NOT FIND A TRAFFIC CONTROL STAGE THAT WILL ALLOW THIS WORK TO TAKE PLACE. PLEASE ENLIGHTEN THIS CONTRACTOR ON HOW THE TRAFFIC IS TO BE HANDLED DURING THIS CONSTRUCTION SEQUENCE?
|
|
9 Q:06/11/07
R:06/21/07 |
Plan
Sheet / Specification
Reference= Special Provisions,Section 10-1.23 Maintaining Traffic. Page 223 - Traffic Chart No. 6 Question= What is the intent of traffic chart no. 6? The Stage Construction Plans for stages 2A, 2C and 3A all have Lomas Santa Fe Dr striped with one lane in each direction and K-rail protecting the work area. The work activities for these stages includes CIDH bridge construction, tie back walls, cast-in-place retaining walls, roadway excavation and pavement construction. This work cannot be completed in 21 consective days. Does chart no. 6 apply to stages 2A, 2C and 3A? When and for what items of work is chart 6 used?
|
10
Q:06/13/07
R:06/21/07 |
Plan
Sheet / Specification
Reference= Bid Item 96(s), 400 MM Cast-in-drilled-hole concrete piling,
Plan sheets 551, 553,556,561, Question= Bid item 96 and the quantities on plan sheet 551 show the the diameter of the cast-in-drilled holes for abutments 1 and 4 as 400 mm. The details of these abutments and the pile data table show 600 mm as the diameter of these holes. Please advise what the correct diameter should be.
|
11 Q:06/13/07 R:06/26/07 |
Plan
Sheet / Specification
Reference= Existing k-rail located in median of 5 fwy. Question= Does the existing k-rail become property of the contractor upon contract award? Existing k-rail on site, ..Can it be used for bid item 24 temporary k-rail?
|
12 Q:06/18/07 R:06/21/07 |
Plan
Sheet / Specification
Reference=Plan Sheet 276-277 and 308-309. Question= Where is the layout sheets for work stated in Stage 1E and 1F, specifically reconstruct sidewalk and replace ac pavement?
Is this an error or does this work belong in stage 1D?
|
13 Q:06/18/07 R:06/21/07 |
Plan
Sheet / Specification
Reference= C-20 Question=IS IT THE INTENT OF THE ENGINEER TO SAVE ALL...THE OLEANDERS AT THE CENTER OF I-5? IF SO CAN THE OLEANDERS BE REMOVED IN SELECTIVE AREAS INORDER TO BRIDGE THE WORK IN BOTH DIRECTIONS OF TRAVEL?
|
14 Q:06/21/07 R:06/21/07 |
Plan
Sheet / Specification
Reference= Addendum #1, page 3, Special Provisions Section 10-1.59
"Concrete Structures", subsection: "Colored Concrete" Question=The addendum specifies that all median barriers along the SD-5 line, from Station: 585+37 to Station 658+96 shall be integrally pigmented colored concrete.... Plans denoted the limits of the 'new' median barrier on the SD-5 line from Station 585+37 to Station 628+96...There is no new barrier shown from station 628+96 to station 658+96. Please clarify the limits of the new colored concrete barriers along the SD-5 line.
|
15 Q:06/22/07 R:06/26/07 |
Plan
Sheet / Specification
Reference= Sheet 660, detail for 750mm CIDH concrete soldier pile rebar
cages. Section 'B-B' . Question= Current design of rebar cages for this structure do not meeting Caltrans propoer clearances for rebar windows. Caltrans Design memo states Minimum of 5" X 5" window clear. The current design only has 4 3/8" clear between the verticals. This will cause a problem in the concrete placement and restricted flowability of the concrete to the outside of the rebar cage.
|
16 Q:06/23/07 R:06/26/07 |
Plan
Sheet / Specification
Reference= 582 of 671 Question= In which bid item do the four deck drains for Lomas Santa Fe Drive (Widen) get paid? There is no misc. metal quantity given on sheet 551 of 671 for these drains.
|
17 Q:06/25/07 R:06/26/07 |
Plan
Sheet / Specification
Reference= Plan Sheet No. 578 Question= Referenced drawing calls for "Ultimate butt splice" at #43 Splice detail. We cannot find a Caltrans approved ultimate butt splice on your web site. Do you want a Service splice at this location in lieu of an ultimate butt splice? Alternatively, can you provide an approved detail of an ultimate butt splice?
|
18 Q:06/25/07 R:06/27/07 |
Plan
Sheet / Specification
Reference= 125 Weathering Steel Plate, 601 of 671 Question= In the "Wall Cap Texture Detail", a 152 x 152 x 6.4 weathering steel plate with 25 x 25 x 100 bar stud is called out. But in Section C-C a 6.4 x 134 x 134 A588 PL with 6.4 x 100 headed stud is called out instead. Which steel plate is required for this project?
|
19 Q:06/25/07 R:06/26/07 |
Plan
Sheet / Specification
Reference= 109 Architectural Treatment (Wall Cap Texture), 648 of
671 Question= There is no wall cap texture quantity given for Retaining Wall No. 611. The missing quantity would basically double the bid quantity.
|
20 Q:06/27/07 R:06/27/07 |
Plan
Sheet / Specification
Reference= Bid items 198, 199, 201, and 202; Plan sheets 487,
581, E-11 and E-12. Question= 1. BI# 201 "Communication Conduit Bridge" does not specify the use of expansion joints or the installation of innerduct. Are they required and if so how many? Per Sheet 581 there are no conduit supports. Is that correct? Is the measurement for single pipe?
|