| CONTRACT NO: | 11-224314 |
| ROUTE / KP | 11-SD-5-R58.7/R60.6 |
| LOCATION | In San Diego County In Solana Beach From 1.5 Km South To 0.4 Km North Of Lomas Santa Fe Undercrossing. |
| DESCRIPTION | To
Construct Northbound And Southbound Lanes. |
| A + B Bidding | |
| ESTIMATE | $ 9,500,000 |
| ADVERTISE DATE | 12/18/2006 |
| BID OPENING | 01/25/2007 |
| FINAL POSTING | 01/24/07 @ 17:30 |
| 1 |
Sim J.
Harris Inc. |
A) $9,975,000.00 B) 150 DAYS |
| 2 |
F C I
CONSTRUCTORS |
A) $10,035,797.80 B) 150 DAYS |
| 3 |
Ortiz
Enterprises |
A) $9,949,824.00 B) 200 DAYS |
The Caltrans District
11
Office is located at 2829 Juan Street, San Diego, CA 92110. The mailing
address is P.O. Box 85406, San Diego, CA 92186-5406. The District 11
Duty
Senior telephone number is (619) 688-6635. Please submit all inquiries
in the proper format by fax to (619) 688-6988 or e-mail to:
Duty_Senior_Const_District11@dot.ca.gov.
The responses to
bidder' inquiries, unless incorporated into a formal addenda to the
contract,
are not a part of the contract and are provided for the bidder's
convenience
only. In some instances, the question and answer may represent a
summary
of the matters discussed rather than a word-for-word recitation. The
responses
may be considered along with all other information furnished to
prospective
bidders for the purpose of bidding on the project. The availability or
use of information provided in the responses to bidder' inquiries is
not
to be construed in any way as a waiver of the provisions of Section
2-1.03
of the Standard Specifications or any other provision of the contract,
the plans, Standard Specifications or Special Provisions, nor to excuse
the contractor from full compliance with those contract requirements.
Bidders
are cautioned that subsequent responses or contract addenda may affect
or vary a response previously given.
Caltrans District 11 Construction
Department
has developed this method of answering Bidder's Inquiries to better
serve
the needs of the Contractors who bid on our Projects. Caltrans District
11 Construction Department will post all of the questions submitted by
any of the contractors that are registered Planholders for that
Contract,
but reserves the right to not answer any questions deemed
unsatisfactory
for public viewing.
The BIDDER'S
INQUIRIES
& RESPONSES will be updated continuously and all attempts will be
made
to do the final posting by 15:00 on Wednesday prior to the bid opening.
INFORMATION
AVAILABLE
| CROSS SECTIONS |
|
|
|
|
ADDENDUM
BIDDER'S
INQUIRY SUBMITTAL FORM
|
|
Inquiry |
|
1
Q:12/18/06 R:12/28/06 R:01/08/07
|
Plan Sheet / Specification
Reference= Question= I need to know if
there are any cd's available with cross sections or any other material
with information on this job other than the Plans and Specs we have
ordred. Please let me know how or where I can obtain any of the
information.
5560 Ruffin Road Suite 5 San Diego, CA 92123 (858) 541-1500 FAX (858) 278-0558 e-mail to plot@mesablueprint.com San Diego, CA 92123 |
2 Q:12/19/06 R:12/28/06 |
Plan
Sheet / Specification
Reference=5-1.17 Project Information Question= Please provide directions to bidders for obtaining project information outline in the Special Provisions Page 124, Item A,B,C,D and E.
|
3 Q:01/03/06 R:01/03/06 |
Plan
Sheet / Specification
Reference=Section 3-1.025 of the Special Provisions Question=Section 3-1.025 of the Special Provisions requires significant documentation of insurance coverage, including copies of policies, notice of election to self-insure (no form included), and a declaration by a CPA that the bidder has sufficient funds to cover the self-insurance amounts. Please delete this section in its entirety as it is extremely burdensome to provide such additional documentation of insurance coverages.
|
4 Q:01/05/07 R:01/15/07 |
Plan
Sheet / Specification
Reference=Special Provisions, Section 4, Beginning of work... Paragraph 6, states "The Contractor shall pay to the State of California the sum of $10,500 per day, for each and every calendar day's delay in finishing the phase one work after the number of working days specified for the opening of the southbound widening on State Highway Route 5. Paragraph 7, states "The Contractor shal pay to the State of California the sum of $4,600 per day, as liquidated damages,for each and every calendar day's delay in finishing the work after the expiration of teh number of working days bid. The PROPOSAL form has a space to enter ONE space in which to enter the number of working days bid. Question=The question is: it appears that there are two different time constraints specified in the referenced Special Provisions section, and only provision for one time constraint commitment to be made on the PROPOSAL form. PLEASE CLARIFY! Additinally, the Special Provisions section, paragraph 6, uses the term "phase one"; and the plans use the terminology of STAGE 1A, STAGE 1B, STAGE 1C. Please define what is meant by "phase one".
|
5 Q:01/08/07 R:01/15/07 |
Plan
Sheet / Specification
Reference=Bid Item 4 - Health & Safety Plan Question=I am unable to find the descrition and method of payment for the Health & Safety Plan in the Special Provisions. Please provide this information.
|
6 Q:01/11/07 R:01/19/07 |
Plan
Sheet / Specification
Reference=Item
No. 41 Rdway
Exc, Aerially Lead Plan
Sheet No. C-3 Question= 1 show undercut of pavement section to facilitate burial of AEL +_ .5m. How is this paid?
|
7 Q:01/12/07 R:01/19/07 |
Plan
Sheet / Specification
Reference=Item 49, Geosynthetic Embankment Reinforcement, Section
10-1.34, Page 200 under "Material Configuration Specifications" both
Subpart A & B refer to the LTDS as shown on the plans. Question=Please provide the LTDS as referenced in the above mentioned specification section.
|
8 Q:01/11/07 R:01/15/07 |
Plan
Sheet / Specification
Reference=Plan sheet X-1, Page 2 of 176, in the Existing Structural
Sections, Diamond (C) shows 686 MM of AC. Question=Is that depth correct? 2.25 Feet of AC pavement?
|
9 Q:01/12/07 R:01/19/07 |
Plan
Sheet / Specification
Reference=Item 72 (S-F), Sound Wall (Transparent Panel), Page 173 of
176 Under the design notes. Question=The plans call for a minimum thickness of 16 MM on the Sound Wall Transparent Panel. The glass cost for this thickness of tempered glass will be significantly higher than using 12.7 MM (1/2" thick tempered glass) which is the standard on many other jobs with transparent panels.
|
10 Q:01/15/07 R:01/19/07 |
Plan
Sheet / Specification
Reference=Item #50, Soil Nail Assembly, Sheet 153 of 176, Special Provision Section 10-1.36 (page 208). Question=M, the Maximum Test Load for Test Soil Nails equals 656 kN (147 kips), which exceeds the Yield Load of a #11 Grade 520 bar. Please specify a reduced test load or an anchor tendon that can take the specified load.
|
11 Q:01/17/07 R:01/22/07 |
Plan
Sheet / Specification
Reference=Item 49, Geosynthetic Embankment Reinforcement. Plan sheet 17, Special Provision Section 10-1.34, subsection "Backfill" contains a table of properties that the backfill is required to meet. One of those properties is a gradation that, in effect, requires the backfill to contain a minimum of 30%, by weight, particles larger than 4.75mm (No. 4). Question=It is a virtual certainty that there is no material available on the project within the roadway excavation that meets this gradation. This means that all of this material must be imported and shall be equivalent to class 2 aggregate base. Further,this imported material would add to the already substantial amount of export of roadway excavation that is surplus to the job. At current market prices and a volume based on the contract quantity of geogrid fabric, (approximately 5,000 cubic meters), the added cost of importing aggregate base and exporting the displaced roadway excavation could impact the project in the range of $250,000 to $300,000. This seems to be poor value engineering. There are a great number of geosynthetic embankments that have been constructed with material that was locally available and of far lower quality (and cost) than is specified for this job, and there are other less costly solutions to the problem that this geosynthetic embankment is intended to solve. Isn't there a better idea than this?
|
12 Q:01/18/07 R:01/19/07 |
Plan
Sheet / Specification
Reference=Item 65(F)Grind Existing Concrete Pavement, Special Provision
Section 10-1.48 Question=We do not know how to bid this item. There is a bid quantity provided in the Bid Schedule of 1,880 M2 and nothing shown for this work on the plan sheets. The special provisions section 10-1.48 in the final paragraph says the work will be paid as extra work. What shall we bid for item 65(F) and how do we verify the 1,880 M2?
|