| CONTRACT NO: | 11-010614 |
| ROUTE / KP | 11-SD-52,67,125-Var |
| LOCATION | In San Diego County At Various Locations. |
| DESCRIPTION | Construct A Four-lane Freeway. |
| ESTIMATE | $ 74,000,000 |
| WORKING
DAYS |
965 (Including 250 Working Days of Plant Establishment) |
| ADVERTISE DATE | 09/24/2007 |
| BID OPENING | 11/15/2007 |
| FINAL POSTING |
11/14/07
@ 16:00 |
The Caltrans District
11
Office is located at 4050 Taylor Street, San Diego, CA 92110. The
District 11
Duty
Senior telephone number is (619) 688-6635. Please submit all inquiries
in the proper format by fax to (619) 688-6988 or e-mail to:
Duty_Senior_Const_District11@dot.ca.gov.
The responses to
bidder' inquiries, unless incorporated into a formal addenda to the
contract,
are not a part of the contract and are provided for the bidder's
convenience
only. In some instances, the question and answer may represent a
summary
of the matters discussed rather than a word-for-word recitation. The
responses
may be considered along with all other information furnished to
prospective
bidders for the purpose of bidding on the project. The availability or
use of information provided in the responses to bidder' inquiries is
not
to be construed in any way as a waiver of the provisions of Section
2-1.03
of the Standard Specifications or any other provision of the contract,
the plans, Standard Specifications or Special Provisions, nor to excuse
the contractor from full compliance with those contract requirements.
Bidders
are cautioned that subsequent responses or contract addenda may affect
or vary a response previously given.
Caltrans District 11 Construction
Department
has developed this method of answering Bidder's Inquiries to better
serve
the needs of the Contractors who bid on our Projects. Caltrans District
11 Construction Department will post all of the questions submitted by
any of the contractors that are registered Planholders for that
Contract,
but reserves the right to not answer any questions deemed
unsatisfactory
for public viewing.
The BIDDER'S
INQUIRIES
& RESPONSES will be updated continuously and all attempts will be
made
to do the final posting by 15:00 on Wednesday prior to the bid opening.
INFORMATION
AVAILABLE
|
|
|
|
|
|
| INFORMATION
HANDOUTS PART 1 Last Updated 10/01/07 |
INFORMATION
HANDOUTS PART 2 Last Updated 10/01/07 |
INFORMATION
HANDOUTS PART 4 Last Updated 11/09/07 |
||
| CROSS SECTIONS | CROSS
SECTIONS Last Updated 10/29/07 |
BIDDER'S INQUIRY SUBMITTAL FORM
|
|
Inquiry |
|
1 |
Plan Sheet / Specification
Reference=
Question= will cross section
be available for this project?
MESA BLUEPRINT 5560 Ruffin Road Suite 5 San Diego, CA 92123 (858) 541-1500 FAX (858) 278-0558 e-mail to plot@mesablueprint.com San Diego, CA 92123
|
|
2 Q:09/26/07 R:10/01/07 |
Plan
Sheet / Specification
Reference= Fanita creek br. no. 57-1132
Question= where are the drawing for the fanita creek bridge?
|
|
3 Q:10/02/07 R:10/11/07 |
Plan
Sheet / Specification
Reference= Plan Sheet #559, 577 - 579, and Specification Section
10-1.39 Earth Retaining Structures; snetence beginning "The
architectural features ..............on the plans."
Question= Plan sheet 569 calls out a cobblestone finish for the panels. Plan sheets 577- 579 detail a raised surface detail. 1. What finish does the owner erquire?
2. Is the cobblestone finish from a particular form liner supplier or is a general statement of appearance such as similar to river rock?
|
|
4 Q:10/03/07 |
Plan Sheet / Specification
Reference= Earth work, Imported Borrow, Cross sections.
|
5 Q:10/03/07 R:10/03/07 |
Plan
Sheet / Specification
Reference= Fanita Drive UC Question= Please clarify your your answer to Question # 2. The drawing sheets indicated do not provide any details for the Fanita Drive UC. Where can the details for this bridge be found in order for it to be quantified. Is the Fanita Drive UC a part of this contract?
|
6 Q:10/03/07 R:10/03/07 |
Plan
Sheet / Specification
Reference= Fanita Dr UC Question= I withdraw the previously submitted question in regards to this bridge structure.
|
7
Q:10/08/07 R:XX/XX/07 |
Plan
Sheet / Specification
Reference= Bid Item 97 - Structural Concrete, Bridge Question= The "Structure List" on sheet 1 of 591, has listed the following structure: No. 6, Fanita Creek (NOT Fanita Drive UC), Bridge No. 57-1132. In reviewing all of the contract drawings, I find no details for this structure to be able to quantify it. Are these details forthcoming, or is this bridge NOT a part of the contract. The subject of this bridge was brought up in question # 2, but no conctreye answer was given
|
8 Q:10/08/07 |
Plan Sheet / Specification
Reference=ITEMS 55-58, EARTH RETAINING STRUCTURES
|
9 Q:10/19/07 R:11/08/07 |
Plan Sheet / Specification
Reference=84 DRIVE STEEL PILE (HP 360
X 132)
|
10 Q:10/19/07 R:11/08/07 |
Plan Sheet / Specification
Reference=Special Provision 10-1.01 (Page 181)and Special Provision
10-1.16 (Page 215)
|
|
11 |
Plan Sheet / Specification
Reference=Bid Item 59 - Imported Borrow - 246,000 M3 Special Provision
10-1.17 Cooperation (Page 216) Special Provision 10-1.01 Order of Work
(Page 180)
To what extent will another
contractor be working within the limits of
Were the bridges described in
Special Provision 10-1.01
Does Caltrans desire excess
material from a future Route 52 project hauled
|
|
12 |
Plan
Sheet / Specification
Reference= Addendum 1, plan sheets 23,24,28 and 29 Question= When will the revised cross sections be issued to support the changes as shown on plan sheets 23,24,28 and 29 in addendum No. 1. Without revised cross sections or new grading plans, we are unable to determine what changes were made.
MESA
BLUEPRINT |
|
13 |
Plan
Sheet / Specification
Reference= 87-92, CIDH Piling, 10-1.53 Piling Question= Can you provide contact information for the Transportation Laboratory for the purpose of viewing cores?
David Thomas at (916) 227-5450 or (916) 240-3821 Secondary Contact Mohan Bonala at (916) 227-1053 |
|
R:11/08/07
|
Plan
Sheet / Specification
Reference= Bid 68 Water Meter 4 ea Question= Page 363 Water meter supplied by Padre Dam water District and paid for by the contractor @ $27,000.00. Does that include all four water meters or is that only for one meter.
|
15
Q:11/02/07 R:11/08/07 |
Plan Sheet / Specification
Reference= 155 (S) TELEVISING SEWER MAIN, SP SECTION 10-4.01 TELEVISING
SEWER MAINS
|
|
16 |
Plan
Sheet / Specification
Reference= 86(S) DRIVE STEEL PILE (HP 360 X 174), 453, 10-1.53 PILING Question= According to page 298 of the Special Provisions the elevation of bottom of hole for the N125-E52 Connector is 103 m. However, the bottom of footing elevation for Abutment 2 shown on plan sheet 453 is 102.97 m. Please confirm the bottom of predrilled hole elevation for the N125-E52 Connector.
|
17 Q:11/07/07 R:11/14/07 |
Plan Sheet / Specification
Reference= 90 - 3.0M CIDH, Plan Sheets 383,
|
|
18 |
Plan Sheet / Specification
Reference= 89 - 2.3M CIDH, Plan Sheet 481/591
|
|
19 |
Plan Sheet / Specification
Reference= 90 - 3.0M CIDH, Plan Sheets 383,
|
|
20 |
Plan Sheet / Specification
Reference= Item # 76 - Asphalt Paving. Page C-1
|
|
21 |
Plan Sheet / Specification
Reference= BI #89 & 90, CIDH pile connections to Column. Plan
sheets 383, 404, 423, & 481, Bent 2 details and column details.
|
22 Q:11/07/07 R:11/09/07 |
Plan Sheet / Specification
Reference= B.I.'s #83 thru #94
|
|
23 |
Plan Sheet / Specification Reference=ITEM #215 (S) Catenary Work - Phase 1 & 216 (S) Catenary Work Phase 2. Railroad plans RR-4 thru RR-12 (Sheet 317 thru 325) Special Provisions Section 10-5 Railroad Construction. Section 10-5.11 OCS Material & Equipment. Question= On plan sheet RR-4 catenary phase 1 and RR-4 catenary phase 2 it calls out for certain catenary assemblies to be furnished however if you go to the sheet RR-10 thru RR-12 there are no details for the assemblies. The assemblies in question are 32-1, 32-4, 35-1, 43-2 and 43-4. Can you please provide detail for these assemblies. Also, On Sheet RR-12, in the bill of materials (Schedule) it shows assembly types 3, 6 and 7 however if you look at the details on the same sheet it only displays assembly type 34-1 & 34-2. Please provide detail for other assembly type.
|
|
24 |
Plan Sheet / Specification Reference=Final Foundation Reommendations MEMORANDUMS...regarding CIDH Rock Sockets Question= Serveral Memorandum refer to the geotechnical
capacity of the CIDH piles based on Friction ONLY! However, the
bottom of the drilled holes is to be cleaned out, INPSECTED AND
APPROVED by the engineer, prior to the placment of the drilled
reinforcement cage and concrete.
|
|
25 |
Plan Sheet / Specification Reference=Plan Sheet / Specification Reference=Traffic Handling Plan sheets 188 thru 203 and Special Provisions sheets #233 thru 243. Question=Current traffic plans and lanes closures make it very difficult for public saftey and the construction of the 3.0M CIDH piles @ Mission Gorge Rd. UC & Rte. 52/125 Separation. The current amount of working lanes (room) makes it very restirctive for the Large drilling equipment that wil be needed to drill these rock sockets. At a minimum, Can Traffic Chart #6 (Special Provisions Sheet 238) be applied during the drilling operations on Mission Gorge. Likewise, at SR125 can Traffic Charts 236 & 237 be apply during the CIDH drilling there.
|
26 Q:11/09/07 R:11/14/07 |
Plan Sheet / Specification Reference= B.I.91 (S) & 92 (S) CIDH Piling (Rock Socket) Question= Will blasting (or similar industry methods) be allowed for excavation of the 'rock' in the CIDH Pile rock sockets?
|
| 27 Q:11/12/07 R:11/13/07 |
Plan Sheet / Specification Reference= Question= Regarding Item # 171 “Chain Link Gate” 13 each. Gates widths are not given on either the engineers estimate nor on the construction plans could you please elaborate.
|
28 Q:11/12/07 R:11/14/07 |
Plan Sheet / Specification Reference= Reply by Caltrans to Question #22 of the Bidder's Inquires & Responses. Question= Since rock core
breaks are not available, we must assume the rock strengths on this
project are derived from the descriptive relative strength words used
in the LOTB. If so, can we expect where granite is described as
'extrememly hard,' the range of possible strengths would be at a
minimum 32,000PSI?
"Specimen cannot be
scratched with pocket knife or sharp pick; can only be chipped with
repeated heavy hammer blows."
Manual can be accessed through the following Caltrans website: http://www.dot.ca.gov/hq/esc/geotech/requests/logging_manual/logging_manual.html |
29 Q:11/12/07 R:11/14/07 |
Plan Sheet / Specification Reference= Items 89 & 91, Pier 2, Pile 2, Bridge 57-1100, Pile data table on sheet 469 Question= The pile data table
identifies a 4M rock socket with top of estimated hard rock at
elevation 80.5. The boring nearest this shaft (Boring B-2 on
sheet 502) identifies top of granite at approximate elevation
93M. This is a 12.5M elevation difference. Please confirm
that the rock socket bid item unit price will be paid from the top of
hard rock actually encountered.
|
|
30 |
Plan Sheet / Specification Reference= Item170- Chain Link Fence (Type CL-1.8, Vinyl-Clad)
Or is the intent to have all the material vinyl clad?
|
|
31 |
Plan Sheet / Specification Reference=Plan Sheet No. 318 of 591 RR-5 Question=1- WILL CONSTRUCTION OF THE FALSE WORK OVER THE CATENARY SYSTEM BETWEEN STA 30+33.980 AND 30+83.420 HAVE TO BE CONSTRUCTED DURING NON REVENUE HOURS. NOTE 3 REQUIRES ALL CATENARY WORK TO BE DONE UNDER THIS WINDOW. NOTE 5 DISCUSSES THE FALSE WORK. THIS WORK APPEARS TO BE WITH IN THE CAL OSHA REQUIREMENTS OF WORKING CLEARANCES OF ENERGIZED LINES. 2- IF THIS WORK IS TO BE PERFORMED UNDER THIS WINDOW, WHAT ARE THE WORKING HOURS. TYPICAL CATENARY WORK HOURS IN THIS AREA ARE 12:30AM TO 4:AM EXCLUDING SPECIAL EVENTS (PADRE AND CHARGER GAMES ETC)
|
|
32 |
Plan Sheet / Specification
Reference= Question= The plan sheets you
provided do provide the assembly details I requested in my Bidders
Inquiry, however some of the other plan sheets provided are confusing
me. sheets TP-478 and TP-479 are referring to Station
Locations from 986+50 thru 1006+20 and the original project plans are
referring to Station Locations 28+57.890 thru 32+65.170 on Plan Sheets
RR-4 & RR-6. Please advise.
· Pole at sta. 978+31 (sta. 28+95.92'cs' ) · Pole at sta. 980+37 (sta. 29+59.09 'cs') · Pole at sta. 982+40 (sta. 30+20.98 'cs') · Pole at sta. 984+45 (sta. 30+83.42 'cs') · Pole at sta. 986+50 (sta. 31+45.99 'cs') Pole at approx station 32+08.478 'cs' |