Concrete
Bridge Deck/Girdwer Treatment /Bridge Joints.
Advertise
Date 08/21/00
Bids
Open 09/28/00
The responses to
bidder' inquiries, unless incorporated into a formal addenda to the contract,
are not a part of the contract and are provided for the bidder's convenience
only. In some instances, the question and answer may represent a summary
of the matters discussed rather than a word-for-word recitation. The responses
may be considered along with all other information furnished to prospective
bidders for the purpose of bidding on the project. The availability or
use of information provided in the responses to bidder' inquiries is not
to be construed in any way as a waiver of the provisions of Section 2-1.03
of the Standard Specifications or any other provision of the contract,
the plans, Standard Specifications or Special Provisions, nor to excuse
the contractor from full compliance with those contract requirements. Bidders
are cautioned that subsequent responses or contract addenda may affect
or vary a response previously given.
Caltrans District 11 Construction Department
has developed this method of answering Bidder's Inquiries to better serve
the needs of the Contractors who bid on our Projects. Only when stated
in the Special Provisions will contracts have posted INQUIRIES AND RESPONSES.
The BIDDER'S INQUIRIES
& RESPONSES will be updated continuously with the last posting no later
than 15:00 on Wednesday prior to the bid opening.
Caltrans District 11 Construction Department
will post all of the questions submitted by any of the contractors that
are registered Planholders for that Contract, but reserves the right to
not answer any questions deemed unsatisfactory for public viewing.
|
09/15/00 |
|
|
|
Inquiry |
|
|
Plan Sheet / Specification Reference=Section
5-1.04 Public safety of the Special Provision
Section 5-1.04 Public Safety of the Special Provision states that a lane of traffic shall be taken when working within 1.8M of the traffic. Please clarify this specification when working in one lane of a 2 lane freeway. |
|
|
Plan Sheet / Specification Reference=Plan
Sheets 11 of 24, 15 of 24, and 16 of 24
Dimensions on pages 11/24, 15/24 and 16/24 show shoulder width, lane width, roadway width of lanes less than one Meter. These cannot be correct. We request the correct dimension in order to verify quantities.
14/24 10' outside, 48' lanes, 15' inside, not including transition area. 15/24 10' outside, 48' lanes, 8' inside. 16/24 8' outside, 24' lanes, 5' inside, not including transition area" |
|
|
Plan Sheet / Specification Reference=Plan
Sheet 13 of 24
Eighth St. UC: At Abutment 1 plans call for replace bridge deck. Pay Quantities show Structure Concrete Bridge. Is this where the item is paid? If so, where is the removal paid?
|
|
|
Plan Sheet / Specification Reference=Page
21 of 24
Route 163/52 Abutment 3 joint seal assembly shows concrete to to be placed. The quantities do not show an item of Structure Concrete Bridge. Where is this item paid?
|
|
|
Plan Sheet / Specification Reference=Plan
sheet 22 of 24
Route 163/805 Hinge calls for concrete at hinge. No quantity for structure Concrete Bridge in Quantities. Where is this paid?
|
|
|
Plan Sheet / Specification Reference=Plan
sheet 15 of 24
Need lane closure chart for CB-2 line shown on sheet 15 of 24.
|
|
|
Plan Sheet / Specification Reference=Plan
sheets 21 of 24 and 22 of 24.
Where is the rebar paid for the new rebar shown in the "Structure Concrete Bridge" work?
|