| CONTRACT NO: | 11-080934 |
| ROUTE / KP | 11-SD-15,56-M30.4/M31.4,14.3/15.3 |
| LOCATION | In San Diego County In San Diego On Route 15 From 0.9 Km South To 0.1 Km North Of Route 56/15 Separation And On Route 56 From 0.5 Km West To 0.5 Km East Of Route 56/15 Separation. |
| DESCRIPTION | Construct Additional Lanes, Movable Barriers, And Replace Bridges. |
| ESTIMATE | $ 37,000,000.00 |
| DESIGN SEQUENCING PROJECT | |
| ADVERTISE DATE | 01/10/05 |
| BID OPENING | 03/03/05 |
| FINAL POSTING | 03/02/05 @ 18:55 |
|
|
F C I CONSTRUCTOR, INC. | $32,228,497.00 |
|
|
COFFMAN SPECIALTIES, INC. | $32,685,000.00 |
|
|
MCM CONSTRUCTION, INC. | $32,937,879.00 |
|
|
HERZOG CONTRACTING CORP. | $36,510,497.00 |
The Caltrans District 11
Office is located at 2829 Juan Street, San Diego, CA 92110. The mailing
address is P.O. Box 85406, San Diego, CA 92186-5406. The District 11 Duty
Senior telephone number is (619) 688-6635. Please submit all inquiries
in the proper format by fax to (619) 688-6988 or e-mail to:
Duty_Senior_Const_District11@dot.ca.gov.
The responses to
bidder' inquiries, unless incorporated into a formal addenda to the contract,
are not a part of the contract and are provided for the bidder's convenience
only. In some instances, the question and answer may represent a summary
of the matters discussed rather than a word-for-word recitation. The responses
may be considered along with all other information furnished to prospective
bidders for the purpose of bidding on the project. The availability or
use of information provided in the responses to bidder' inquiries is not
to be construed in any way as a waiver of the provisions of Section 2-1.03
of the Standard Specifications or any other provision of the contract,
the plans, Standard Specifications or Special Provisions, nor to excuse
the contractor from full compliance with those contract requirements. Bidders
are cautioned that subsequent responses or contract addenda may affect
or vary a response previously given.
Caltrans District 11 Construction Department
has developed this method of answering Bidder's Inquiries to better serve
the needs of the Contractors who bid on our Projects. Caltrans District
11 Construction Department will post all of the questions submitted by
any of the contractors that are registered Planholders for that Contract,
but reserves the right to not answer any questions deemed unsatisfactory
for public viewing.
The BIDDER'S INQUIRIES
& RESPONSES will be updated continuously and all attempts will be made
to do the final posting by 15:00 on Wednesday prior to the bid opening.
INFORMATION
AVAILABLE
|
|
|
|
|
|
|
|
|
|
||
|
|
|
|
|
|
BIDDER'S
INQUIRY SUBMITTAL FORM
|
Q:01/18/05 |
Plan Sheet / Specification Reference=project
Cross sections
We would like a electronic copy of the project cross sections.
5560 Ruffin Road Suite 5 San Diego, CA 92123 (858) 541-1500 FAX (858) 278-0558 e-mail to plot@mesablueprint.com San Diego, CA 92123 |
|
Q:01/19/05 |
Plan Sheet / Specification Reference=Project
Plans - Retaining Walls -
Miscellaneous Details No. 5 Plan sheet no. 558 of 579. Question=What are the limits of excavation
below the footing and leveling
315+23 to 315+38 Varies (@ 1:10 slope) from 0 m to 1.5 m 315+38 to 318+30 1.5 m 318+30 to 318+45 Varies (@ 1:10 slope) from 1.5 m to 0 m |
|
Q:02/10/05 R03/02/05 |
Plan Sheet / Specification Reference=
Contract Plan Sheet #s 415,441,468 and 493 of 579
Question = What are the specified strengths for the CIDH piles for the NB/SB ON/OFF ramps. For NB/SB ON/OFF ramps see Section 49-4.01, "Description," of the Standard Specifications which states: "Concrete filling for cast-in-place concrete piles is designated by compressive strength and shall have a minimum 28-day compressive strength of 25MPa. For the Main Access ramp see Plan Sheet 337 with CIDH (28 MPa at 28 days). |
|
Q:02/10/05 |
Plan Sheet / Specification Reference=Section
2 Proposal Requirements and Conditions Subsectuion 2-1.01 General
Question=Is there an addenda pending for this project and will it change/delay the bid date?
|
|
Q:02/22/05 |
Plan Sheet / Specification Reference=
Rebar cage designs for Column and CIDH piles. Sheets 382,365,447
& 448
Question=Upon the review of the rebar cages for the CIDH piles and Column Cages (which embed approx. 12' to 17' feet down in the piles) we have noted some potential problems related to the clear rebar spacing windows. Can and will the Column rebar cage "window"
spacing be modified to meet Caltrans required design standard of 5"x5"
minimum? The column cage at Bent 1 & Bents 5 thru 7 only have
4 1/4" clearance between the vertical bars. Since this cage is embeded
down in the CIDH pile and will have to be poured with the pile, it may
effect the concrete flowability through this cage before it even reaches
the outter CIDH cage.
Bents 2 & 3 column cages meet minimum clearance and spacing.
|
|
Q:02/22/05 |
Plan Sheet / Specification Reference=CIDH
pile and Column connection...Sheets 362,363,364,365,366, 447, 448 &450
Question=The current contract plan design of the connection of the column rebar cages to the CIDH piles is cumbersome, difficult, and unsafe to the traveling public. With no splices allowed in the column
cages, the cages will all have to be set full height, after the CIDH pile
cage is first set and supported at grade. This task will be difficult,
if not impossible to complete and pour, all in 1-day, especially if these
shafts are constructed utilizing slurry.
Also, we request the possibility (in
conjuction with the above alternate C.J.) of allowing the isolation casing
being extended to a depth of 3'-0" (min.) past the tip elevation of the
column cage to allow the proposed alternate C.J. as well as a clean C.J.
to produce a quality shaft.
|
|
Q:02/22/05 |
Plan Sheet / Specification Reference=
Section 10-1.45 “Piling,” of the Special Provisions indicates that “Acceptance tests of the concrete will be made by the Engineer…” and “Tests will included gamma-gamma logging.” Pursuant to section 6-3.01 of the Standard Specifications, “…all tests shall be performed in accordance with the methods used by the Department of Transportation…”, however we are unable to locate Caltrans’ defined test method for gamma-gamma logging. Accordingly, please provide the following information: · Defined procedures for gamma-gamma
logging (Cal Test number);
Additional information
regarding gamma-gamma logging is available at the following websites:
|
|
Q:02/23/05 |
Plan Sheet / Specification Reference=ITEM
#151 REMOVABLE BOLLARD.
SHEET # 47. SPECIAL PROVISION SECTI0N 10-1.76 Question=SHOULD THE REMOVABLE BOLLARDS BE FABRICATED (GALVANIZED STEEL)PER THE DETAILS SHOWN ON THE PLANS.OR ARE THE TO BE CAST IRON AND POWDER COATED PER THE SPECIAL PROVISIONS.
|
|
Q:02/24/05 |
Plan Sheet / Specification Reference=The
Special Provisions...Sheet 223
Question=Under CIDH piles...aprroixmately paragraph 7 states; "If the drilling for any cast-in-drilled-concrete pile cannot be completed in the same shift, the Contractor will be required to keep the drilled hole 'dry' by pumping methods until drilling starts again on next shift" Please clarify...does this apply to
the shaft only when it is completely drilled to specified tip elevation
or during the intial start (at grade) throughout the entire drilling and
until poured?
|
|
Q:02/25/05 |
Plan Sheet / Specification Reference=bid#171
tru. 177 all electrical
work to be done. ,E-1truE-6, 10-3-signals,lighting and electrical systems. Question=Q: What size are the sizes of the luminair arms.
method".
|
|
Q:02/28/05 |
Plan Sheet / Specification Reference=Sheet
366 & 450 Isolation Casings
Question=Can the Cut-off elev. be lowered
to match the bottom of the Isolation casing?
|
|
|
|
|
Q:03/01/05 |
Plan Sheet / Specification Reference=Item
159 (F) CONCRETE BARRIER TYPE 732 (MOD) EE 2513 METERS On Bridges and Barrier
Slab
Item 182 (F) CONCRETE BARRIER TYPE 182 (MOD) EE 1063 METERS On Retaining Walls Question=Item 159 Final Pay Quantity is 2513 Meters. This is over what is shown on the contract drawings. Is the 575 meters of Type 732 Mod rail
shown on sheet 228 actually supposed to be Type 732A as first shown on
sheet 231?
|
|
Q:03/01/05 |
Plan Sheet / Specification Reference=CIDH
Piling
Question=Will Foundation Recommendations
be made available for the Bridges
See Section 5-1.17, "Project Information," (page 104) of the Special Provisions and Addendum No. 1 dated February 18, 2005 for information included in the Information Handout. |
|
Q:03/01/05 |
Plan Sheet / Specification Reference=Items
161 and 181, and Item 182. Sheet 228, 229 and 245
1. The summary of Quantity Sheets
on pages 228 and 229 show 189m of Type KA26A rail with tubularhandrail
on wall No. 14L, but sheet 245 shows a type 732A modifiedrail on top of
wall 14L. Plaese clarify.
|
|
Q:03/02/05 |
Plan Sheet / Specification Reference=Concrete
barrier at Retaining Walls
Question=1- Plan sheets 249 through
251 appear to have concrete barrier details similar to the "Structural"
final design plans , sheets 518 through 561. The barrier shown on structural
plans appear to agree with "Final Pay" quantities of Items 155 and 156.
Request confirmation that "Final Pay" Items will be adjusted if and when
the other Retaining wall designs are finalized and the required barrier
types are identified.
|