BIDDER'S INQUIRIES & RESPONSES
DISTRICT 11 CONSTRUCTION
CONTRACT NO:  11-077304
ROUTE / KP 11-SD-15-M21.0/R82.0
LOCATION In San Diego County At Various Locations From 0.5 Km South Of Miramar Way Overcrossing To 0.6 Km North Of Mission Road Overcrossing. 
DESCRIPTION Existing Ramps To Be Surfaced With Rubberized Asphalt Concrete.
ESTIMATE $ 5,310,000.00
ADVERTISE DATE 07/19/04
BID OPENING 08/26/04
FINAL POSTING 08/25/04    @   15:20

BID RESULTS
1
HANSON SJH CONSTRUCTION $ 4,229,021.20
2
HAZARD CONSTRUCTION CO $ 4,364,041.00
3
DAILY CCAC JV $ 5,158,138.00

The Caltrans District 11 Office is located at 2829 Juan Street, San Diego, CA 92110. The mailing address is P.O. Box 85406, San Diego, CA 92186-5406. The District 11 Duty Senior telephone number is (619) 688-6635. Please submit all inquiries in the proper format by fax to (619) 688-6988 or e-mail to:
Duty_Senior_Const_District11@dot.ca.gov.
The responses to bidder' inquiries, unless incorporated into a formal addenda to the contract, are not a part of the contract and are provided for the bidder's convenience only. In some instances, the question and answer may represent a summary of the matters discussed rather than a word-for-word recitation. The responses may be considered along with all other information furnished to prospective bidders for the purpose of bidding on the project. The availability or use of information provided in the responses to bidder' inquiries is not to be construed in any way as a waiver of the provisions of Section 2-1.03 of the Standard Specifications or any other provision of the contract, the plans, Standard Specifications or Special Provisions, nor to excuse the contractor from full compliance with those contract requirements. Bidders are cautioned that subsequent responses or contract addenda may affect or vary a response previously given.
Caltrans District 11 Construction Department has developed this method of answering Bidder's Inquiries to better serve the needs of the Contractors who bid on our Projects. Caltrans District 11 Construction Department will post all of the questions submitted by any of the contractors that are registered Planholders for that Contract, but reserves the right to not answer any questions deemed unsatisfactory for public viewing.
The BIDDER'S INQUIRIES & RESPONSES will be updated continuously and all attempts will be made to do the final posting by 15:00 on Wednesday prior to the bid opening.
INFORMATION AVAILABLE
 
BID ITEMS
 SPECIALS
 PLANS
 PLANHOLDERS
 
ADDENDUM

 ADDENDUM NO.1 07/28/04
 
 
 

BIDDER'S INQUIRY SUBMITTAL FORM
 

Inquiry No.
Inquiry
1
Q:08/18/04
    R:08/19/04
Plan Sheet / Specification Reference=1, 2, 7, 11, 12, 18, 30, 34, 39, & 46. METAL BEAM GUARD RAIL.  SHEET Q-6 LOCATION MBGR # 1 THROUGH 10.  SECTION 10-1.41 METAL BEAN GUARD RAILING, page 77 of the special provisions.

How will this item be paid for?  In the Bid Schedule New MBGR or Reconstruct  MBGR is not listed.

  •   Per plan sheet 112 (SHEET Q-6), there is no planned work of this type (New MBGR or Reconstruct MBGR) to be performed in this project. 
 2
Q:08/20/04
    R:08/23/04
Plan Sheet / Specification Reference=Item #8 Traffic control --- Special Provisions-- Traffic charts .

We can find no chart in the special provisions which allows us to close the Hwy #78 eastbount to I-15 southbound connector ramp. Since there is work to be accomplished on that ramp, what should we do?

  • Post award and approval of the contract, closure chart for the connector from eastbound route 78 to southbound route 15 will be added in accordance with section 4-1.03 CHANGES, of the Standard Specifications. This change will be at no cost to the State or the contractor. 
 
3
Q:08/20/04
    R:08/23/04
Plan Sheet / Specification Reference=1, 2, 7, 11, 12, 18, 30, 34, 39, & 46. SHEET  Q-6 LOCATION MBGR #1 THROUGH 10/ 10-1.41 METAL BEAN GUARD RAILING, page 77 of the special provisions.

Is Catrans guaranteeing that we will be able to purchase the SRT's for $895.00 (plus tax) if order is placed on or before July 29, 2005, and delivery is accepted within 90 days?
 

  • Yes.
 
4
Q:08/25/04
    R:08/25/04
Plan Sheet / Specification Reference=

On the summary quantities sheet Q-6, Metal Beam Guard Rail there is a (N) non pay item for Guard Rail Connect to Bridge Rail, Retaining Walls and Abutments Standard Plan A77J for Guard Rail Runs 1, 2, 3, 5, 7&8. The scope of work for this project is removal of existing Guard Rail and Anchors to be replaced by the Terminal System (Type SRT). There is no work to be done at the Bridge Rail Connections. So the question is; what is the intent of including this (N) Non Pay item? 
 

  • Please bid per the contract documents. 
OTHER LINKS OF INTEREST
DISTRICT 11 CONSTRUCTION BIDDER'S INQUIRIES & RESPONSES
DISTRICT 11 HOMEPAGE
CALTRANS OFFICE ENGINEER: Contract Advertisement, Special Provisions, Plan Holders, Contract Awards, etc.
DEPARTMENT OF TRANSPORTATION