| CONTRACT NO: | 11-080914 |
| ROUTE / KP | 11-SD-15-M35.4/M38.7 |
| LOCATION | In San Diego County In San Diego From Camino Del Norte Undercrossing To 0.5 Km North Of Rancho Bernardo Road Undercrossing. |
| DESCRIPTION | Construct Managed Lanes Middle Unit 2. |
| ESTIMATE | $ 54,000,000.00 |
| DESIGN SEQUENCING PROJECT | |
| ADVERTISE DATE | 11/24/03 |
| BID OPENING | |
| FINAL POSTING | 06/09/04 @ 17:20 |
|
|
FCI CONSTRUCTOR/BALFOUR BEATTY, A JOINT VENTURE | $ 67,837,529.00 |
|
|
YEAGER SKANSKA INC. | $ 68,145,747.00 |
|
|
COFFMAN SPECIALTIES, INC. | $ 68,775,009.00 |
|
|
C.C. MYERS, INC. | $ 70,724,221.50 |
|
|
STEVE P. RADOS, INC. | $ 72,976,248.00 |
The Caltrans District 11
Office is located at 2829 Juan Street, San Diego, CA 92110. The mailing
address is P.O. Box 85406, San Diego, CA 92186-5406. The District 11 Duty
Senior telephone number is (619) 688-6635. Please submit all inquiries
in the proper format by fax to (619) 688-6988 or e-mail to:
Duty_Senior_Const_District11@dot.ca.gov.
The responses to
bidder' inquiries, unless incorporated into a formal addenda to the contract,
are not a part of the contract and are provided for the bidder's convenience
only. In some instances, the question and answer may represent a summary
of the matters discussed rather than a word-for-word recitation. The responses
may be considered along with all other information furnished to prospective
bidders for the purpose of bidding on the project. The availability or
use of information provided in the responses to bidder' inquiries is not
to be construed in any way as a waiver of the provisions of Section 2-1.03
of the Standard Specifications or any other provision of the contract,
the plans, Standard Specifications or Special Provisions, nor to excuse
the contractor from full compliance with those contract requirements. Bidders
are cautioned that subsequent responses or contract addenda may affect
or vary a response previously given.
Caltrans District 11 Construction Department
has developed this method of answering Bidder's Inquiries to better serve
the needs of the Contractors who bid on our Projects. Caltrans District
11 Construction Department will post all of the questions submitted by
any of the contractors that are registered Planholders for that Contract,
but reserves the right to not answer any questions deemed unsatisfactory
for public viewing.
The BIDDER'S INQUIRIES
& RESPONSES will be updated continuously and all attempts will be made
to do the final posting by 15:00 on Wednesday prior to the bid opening.
INFORMATION
AVAILABLE
|
|
|
|
|
|
|
|
|
|||
|
|
BIDDER'S
INQUIRY SUBMITTAL FORM
|
|
Inquiry |
|
Q:12/22/03 |
Plan Sheet /
Specification Reference=NOTICE TO CONTRACTORS
When will the cross sections be available and where?
5560 Ruffin Road Suite 5 San Diego, CA 92123 (858) 541-1500 FAX (858) 278-0558 e-mail to plot@mesablueprint.com San Diego, CA 92123 |
|
Q:12/22/03 |
Plan Sheet /
Specification Reference=NOTICE TO CONTRACTORS =Bid Items # 29, 30, 31,
32.
Please explain
the differences between bid items # 29, 30, 32. ( Item # 31 is
|
|
Q:12/29/03 |
Plan Sheet /
Specification Reference=sec. 5-1.13 Force Account Payment
Will there be an amendment to adjust the force account rates for subcontractors works?
When extra work to be paid for on a force account basis is performed by a subcontractor, approved in conformance with the provisions in Section 8-1.01, "Subcontracting," of the Standard Specifications, an additional markup of 7 percent will be added to the total cost of that extra work including all markups specified in this section, "Force Account Payment". The additional 7 percent markup shall reimburse the Contractor for additional administrative costs associated with the work being performed by a subcontractor, and no other additional payment will be made. |
|
Q:12/29/03 R:01/20/04 |
Plan Sheet /
Specification Reference= Cross sections CN-1A
The cross sections
CN-1A (001 to 007) posted on Caltrans internet site are different from
the bid drawings (sheets 16, 32, 503, 504) (position of the retaining wall
and slopes).
|
|
Q:12/29/03 |
Plan Sheet /
Specification Reference= Cross sections CV-2A
On cross sections
CV-2A (001 to 013), the retaining wall data (RW 379L) is omitted and is
qualified as "done by others".
|
|
Q:01/05/04 |
Plan Sheet /
Specification Reference =
1. Contract requires
hub "Conforming with details shown onplans and as specified in these special
provisions."
|
|
Q:01/05/04 |
Plan Sheet /
Specification Reference = Item 126 Structure Concrete
Retaining Wall Item 133 Swirled Plaster Texture
Contract Plan Sheet 494 of 911 (sheet Q-6) Contract Plan Sheets 500 thru 540 of 911 (sheets R-1 thru R-41) Engineer's Estimate of Quantities Special Provisions Section 10-1.55 Concrete Structures 1) The quantities shown on sheet 494
do not equal the quantities
|
|
Q:01/06/04 |
Plan Sheet /
Specification Reference = SPECIAL PROVISION SECTION:PRE-BID QUALIFICATION
QUESTIONAIRE,PG 63
1)WHO DO WE CALL
TO MAKE SURE THE QUESTIONAIRE WAS RECIEVED ON TIME?
RENEE SMITH AT (916)227- 6296 COULD BE CONTACTED FOR CONFIRMING THAT THE QUESTIONNAIRE WAS RECEIVED ON TIME. |
|
Q:01/20/04 |
Plan Sheet /
Specification Reference = Contract Page #312 Section 10-3.16 HUB CABINET
First sentence
reads "The hub cabinet consists of prefabricated aboveground
|
|
Q:01/21/04 |
Plan Sheet /
Specification Reference = Section 5-1.13 force account payment
How does the subcontractor get reinbursed for the time related overhead (TRO) portion of force account work? is it the State's intent to have the subcontractor's bid a portion of the TRO?
extra work to be paid for on a force account basis is performed by a subcontractor, approved in conformance with the provisions in Section 8-1.01, "Subcontracting," of the Standard Specifications, an additional markup of 7 percent will be added to the total cost of that extra work including all markups specified in this section, "Force Account Payment". The additional 7 percent markup shall reimburse the Contractor for additional administrative costs associated with the work being performed by a subcontractor, and no other additional payment will be made". |
|
Q:01/21/04 R:04/07/04 |
Plan Sheet /
Specification Reference = Special Provision Section 5-1.13, page
88, paragraph 3 Standard Specifications
Section 9-1.03A, para 2, allows markup of
|
|
Q:01/26/04 R:06/09/04 |
Plan Sheet /
Specification Reference =
1)WHEN WILL THE DISTRICT PUBLISH THE LIST OF THE PREQUALIFIED CONTRACTORS
PER SECTION 2-1.012?
|
|
Q:01/26/04 |
Plan Sheet /
Specification Reference =
Retaining Walls 364L, 370L, 374L, 377R, and 394R are listed on sheet 494 of 911 in the “Retaining Wall Quantities” summary table. These walls are also shown on the layout plans, but there are no details to be found. Please provide details for these walls.
|
|
Q:01/26/04 |
Plan Sheet /
Specification Reference =PC/PS I-Girders, plan #894 & 895
Note on plans,
reference girder bearing face reads "Bevel bearing
|
|
Q:01/28/04 |
Plan Sheet /
Specification Reference =Special Provisions, Section 10-4, "Televise Sewer"
Special Provisions, 10-4.02, Page 342 refers to "The Contract lump sum price", yet there is no bid item in the "engineer Estimate" for "Televise Sewer". Please clarify.
|
|
Q:01/29/04 |
Plan Sheet /
Specification Reference =SPECIAL PROVISION SECTION 2-1.013
PLEASE PROVIDE THE LIST OF CONTRACTORS WHO HAVE BEEN PRE-QUALIFIED FOR THIS DESIGN SEQUENCE PROJECT.
|
|
Q:01/29/04 |
Plan Sheet / Specification Reference=SPECIAL
PROVISION SECTION 2-1.013
PLEASE PROVIDE THE LIST OF CONTRACTORS WHO HAVE BEEN PRE-QUALIFIED FOR THIS DESIGN SEQUENCE PROJECT.
|
|
Q:01/30/04 |
Plan Sheet / Specification Reference=GENERAL
QUESTION:
IN TALKING W/ THE DUTY SENIOR ON 1-26-04, IT IS OUR UNDERSTANDING THAT AN ADDENDA WILL BE ISSUED POSTPONING THE BID DATE UNTIL MID APRIL. WE WOULD APPRECIATE AN IMMEDIATE ADDENDA FOR THE POSTPONMENT. THIS WILL BETTER ENABLE US TO SCHEDULE OUR WORK FORCES EFFECTIVELY.
|
|
Q:02/04/04 |
Plan Sheet / Specification Reference=
Section 2-1.02 prebid Qualification Questionnaire.
1. If the bid opening is postponed,
will the qualification period be reopened?
|
|
Q:04/02/04 |
Plan Sheet / Specification Reference=
Items 64, 66, 67, 126, 133, 149, & 224
Retaining wall items 64, 66, 67, 126,
133, 149, & 224 are designated as Final Pay items. However, details
for walls 364L, 370L, 374L, 377R, & 394R will not be provided until
30 or 60 days after approval of the contract. Since there are no
details for these walls for the Contractor to verify the Department’s quantities,
how will variations in quantities, if they are encountered, be handled
once the Contractor receives the missing plans? Will the matter be
dealt with by change order since the issuance of Phases II to IV will be
by change order anyway as stated in the Special Provisions? Or will
the Final Pay quantity (and dollar amount) be adjusted to reflect the actual
quantity per Standard Specification 9-1.015? In any case, the Contractor
should not be held accountable for quantities he cannot confirm.
|
|
Q:04/02/04 |
Plan Sheet / Specification Reference=
166, Prepare and Paint Concrete, Summary of Quantities sheet 494
Exactly what is to be painted under the Prepare and Paint Concrete item? Are the barriers painted? Are these included in the quantities given in the Summary of Quantities on sheet 494? Is wall 377R not to be painted since no quantity was given? If it is, will the Engineer’s Estimate and Summary of Quantities be revised?
|
|
Q:04/02/04 |
Plan Sheet / Specification Reference=
133(F), Swirled Plaster Texture, Summary of Quantities sheet 494
The Swirled Plaster Texture quantities
for walls 379L, 390L and 394R total 2,075 M2 but the Prepare and Paint
Concrete quantities for the same walls total 1,321 M2. Does this
mean that the Swirled Plaster Texture does not get painted? Which
quantities are correct? Are walls 376R, 380R and 392R not to receive
Swirled Plaster Texture since no quantities were given? If they are,
will the Engineer’s Estimate and Summary of Quantities be revised?
|
|
Q:04/07/04 |
Plan Sheet / Specification Reference=
Special Provisions Section 5-1.13 Force
Account Payment Answer to Question 11 contradicts wording
in section 5-1.13 of
|
|
Q:04/14/04 |
Plan Sheet / Specification Reference=
1. The quantity for Item 224 (F),
Concrete Barrier (Type 732 Modified), given in the Engineer’s Estimate
is 3,514 m but quantities shown on sheets 493, 494 and on the bridge plans
total 5,859 m. Neither of these quantities can be confirmed until
the following inconsistencies are clarified:
• The barrier lengths for the Access Ramp Walls on sheet 811 do not match the lengths shown on the wall plan sheets, 812 to 830. Which quantities are correct? 2. Concrete barriers are shown on top of walls 363R, 379L, & 388L on sheets 503, 509, & 526 respectively. Concrete barrier quantities are given for missing walls 370L, 374L, & 394R on sheet 494. All of these walls support cuts for the highway. Is this correct? Shouldn’t these barriers be changed to cable railing? 3. Will the Engineer’s Estimate and the Summary of Quantities be revised to reflect the actual quantities shown on the plans?
|
|
Q:04/14/04 |
Plan Sheet / Specification Reference=Contract
Drawings SC12&SC13, SC84&SC85
Stage 1B & 4B call for structure
construction at the Bernardo
|
|
Q:05/03/04 |
Plan Sheet / Specification Reference=Plan
sheets L6-L9 & X4-X5
There are 8 retaining walls (MSE &
Type 1) that separate the 15M
|
|
Q:05/12/04 |
Plan Sheet / Specification Reference=
Please give us info. on how many % DBE?
The Department has established the following goal for Disadvantaged Business Enterprise (DBE) participation for this project: Disadvantaged Business Enterprise (DBE): 19 percent |
|
Q:05/12/04 |
Plan Sheet / Specification Reference=1.
Item 126: Structure Concrete
Retaining Wall - Reference Plan Sht 514. 2. Item 202: Bridge Deck Drainage System - Reference Spec Page 272 10-1.84 1. The typical detail on plan page 514
calls out a Type 7 Modified
measured by the Kilogram as determine by scale weights. Will the item be measured, or is it final pay? We have reviewed Addendum 6 for the
past few days and due to the vast amount
|
|
Q:05/13/04 |
Plan Sheet / Specification Reference=Item
273: Concrete Barrier (Type KA26A
Mod) - Plan Sht. 494, 505, 540B Plan sheet 494 summarized Type KA26A
Mod barrier on wall 377R, but
On plan sheet 540B the detail for the
Type KA26A barrier call out Tile
134 "BARRIER TILE TEXTURE" of the Special Provisions. |
|
Q:05/13/04 |
Plan Sheet / Specification Reference=Geotechnical
Information
Will Geotechnical Design Reports for
the bridge foundations and
|
|
Q:05/13/04 |
Plan Sheet / Specification Reference=VARIOUS
PLEASE PROVIDE A LISTING OF THOSE PROSPECTIVE
BIDDERS WHO HAVE PREQUALIFIED AND WILL BE DETERMINED TO BE A RESPONSIBLE
BIDDER, AS REQUIRED IN SPECIAL PROVISION SECTION 2-1.012, FOR THE USE OF
ALL INTERESTED SUBCONTRACTORS AND SUPPLIERS, BEFORE BID TIME.
3286 Fitzgerald Rd; Rancho Cordova, CA 95742 Phone: (916) 635-9370 | Fax: (916) 635-1527
(2) FCI Constructors
(3) Yeager Skanska Inc
(4) Balfour Beatty Construction Inc
(5) MCM Construction Inc
(6) Coffman Specialities Inc
(7) Steve P Rados Inc
|
|
Q:05/14/04 |
Plan Sheet / Specification Reference=119
(S), 120 (S), 400 and 600 CIDH Piling.
Are there any rock cores available for
viewing? If they are available, can contact information or a location for
viewing be provided?
|
|
Q:05/14/04 |
Plan Sheet / Specification Reference=addendum
# 6, sheet 504a thru 504f
Question=MSE Wall location 10 calss
for Coping on top of the wall. We
|
|
Q:05/14/04 |
Plan Sheet / Specification Reference=494,
Addendum 6 plan revisions
Please confirm that Retaining Wall 388L has been deleted from the scope of work since no quantities were given on the revised Summary of Quantities. If it has, what is the final configuration of the corresponding section? Will a new cross section and layout plan be released like the ones for 379L?
|
|
Q:05/17/04 |
Plan Sheet / Specification Reference=Stage
Drawings
Stage 5 covers the same areas as Stage
3. What happens in what Stage. Which one takes precedence?
What quantities go with which Stage (Stage 3 or 5)?
|
|
Q:05/18/04 |
Plan Sheet / Specification Reference=Special
provisions pg 153, Plan sheet
SC-19 Question=We are
in aggreement with the Traffic Opening's shown on the
|
|
Q:05/19/04 |
Plan Sheet / Specification Reference=Eart
Retaining Sructures #9 & #10
Typical section (walls 364L & 376R) Question=The typical sections for both
walls indicate a zone of permeable
|
|
Q:05/20/04 |
Plan Sheet / Specification Reference=item
#279 shared field data management system.
Question=Pursuant to section 10-1.16A;
which companies meet the critera of the specification?
DRMcNatty & Associates
ShareChive LLC
Integral Vision
|
|
Q:05/21/04 |
Plan Sheet / Specification Reference=Item
#279, Item code 033041, Shared
Field Data Management System, Reference Addendum No. 7 Question=1. How many working days does
the Shared Field Data Management
calendar days prior to the first chargeable working day, then shall be maintained until 30 calendar days after receiving the final estimate or as authorized by the Engineer. 2. Does the system need to be synchronized
to the electronic certified
|
|
Q:05/24/04 |
Plan Sheet / Specification Reference=Item
#279, Item code 033041, Shared
Field Data Management System, Reference Addendum No. 7 Question=Question 1- Does the unit(hardware)
used for the Shared Field Data
office/desk docking station and if so is it intended for the state truck or car?
unit(hardware) used for the SFDMS need to be?
and does the contractor, subcontractor, supplier such as trucking need to submit electronic certified payroll?
standard, labor and equipment charge book published in the units(hardware)?
for field tracking? and if so? would it need to track all items and change orders in the field using the units(hardware)?
|
|
Q:05/24/04 |
Plan Sheet / Specification Reference=Special
Provisions section 10-1.38
Earth Retaining Structures (Earthwork) Question=It is our interpretation of
the backfill spec that the backfill
|
|
Q:06/03/04 |
Plan Sheet / Specification Reference=Special
Provision Section 10-1.03 Water
Pollution Control - Page 129 Question=Under the Payment subsection it states that the contract lump sum price paid for water pollution control shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in installing, constructing, removing, and disposing of water pollution control practices, including non-storm water management, and waste management and materials pollution water pollution control practices, except those for which there is a contract item of work as specified in the Standard Specifications and these special provisions, and as directed by the Engineer. There is no bid item "Water Pollution
Control." How does this work get paid
|
|
Q:06/03/04 |
Plan Sheet / Specification Reference=279
Shared Field Data Management System, 1-1.16A
Question=In the section for Portable
Computer Hardware Requirements, Item C requires 2 GB of RAM. There
are no currently available notebook computer systems that will accept 2
GB of RAM. Is this correct?
|
|
Q:06/08/04 |
Plan Sheet / Specification Reference=279
SHARED FIELD DATA MANAGEMENT
SYSTEM Question=1: Does the hardware(computer)
need to be used in the field under
for the diary use using the tablet?
tablet and with the desk top in the office (such as sacramento, san diego headquater, project field office)? in real time?
forms in the field units? and if so does it require edit and redline capability (for the plan) and be shared with all the users?
and approval and participation?
and does the data being collected require the search capability?
|
|
Q:06/08/04 |
Plan Sheet / Specification Reference=
Question=1. Does the 250 plant establishment days in the contract require the SFDMS?
|
|
Q:06/08/04 |
Plan Sheet / Specification Reference=279
Shared Field Data Management
System, 1-1.16A Question=1: Does the hardware(computer)
need to be used in the field under
search and access all the data being collected with the tablets (hardware)?
|
|
Q:06/08/04 |
Plan Sheet / Specification Reference=Item
#131, Minor Concrete (Minor Structure)
Question=Drainage Quantity sheet 361, D-96 is the last Q sheet provided. Missing drainage systems 59 through 62 and quantity summary sheet? Using drainage profile sheets, total quantity does not match bid item quantity. Please advise as soon as possible.
|
|
Q:06/09/04 |
Plan Sheet / Specification Reference=
The steel isolation design for the project in San Diego calls out for a minimum wall area of 2100 mm^2/m and minimum moment of inertia of 90,000 mm^4/m. What's the reason for this requirement? Is it for ease of installation because it comes in pieces? The sectional properties required limits the material choice to 6"x2" multi-plate structure (one fabricator and supplier in California). We have utilized 3"x1" CSP split caisson
to accomplish the same function. We have been successful in converting
the multiplate structures to the split caisson. The 3"x1" caisson can be
manufactured to the length required for easy of installation compared to
a multi-plate while meeting the structural requirements (see attached detail).
Please give me a call to discuss or I'll try you tomorrow.
|