| CONTRACT NO: | 11-068004 |
| ROUTE / KP | 11-Imp-7,8, 98-Var |
| LOCATION | In Imperial County Near Calexico At Various Locations. |
| DESCRIPTION | Existing Bridge Is To Be Widened And New Bridges And Retaining Walls Are To Be Constructed And New Highway Is To Be Constructed With Asphalt Concrete Over Aggregate Base. |
| ESTIMATE | $ 31,000,000.00 |
| A + B Bidding | |
| ADVERTISE DATE | 09/29/03 |
| BID OPENING | 11/20/03 |
| FINAL POSTING | 11/19/03 @ 16:00 |
|
|
COFFMAN SPECIALTIES INC. | $ 32,435,000.00
260 DAYS |
|
|
FCI CONSTRUCTORS INC.
W R CONNELLY INC A JV |
$ 32,372,078.00
280 DAYS |
|
|
GRANITE CONSTRUCTION COMPANY | $ 34,272,170.00
350 DAYS |
The Caltrans District 11
Office is located at 2829 Juan Street, San Diego, CA 92110. The mailing
address is P.O. Box 85406, San Diego, CA 92186-5406. The District 11 Duty
Senior telephone number is (619) 688-6635. Please submit all inquiries
in the proper format by fax to (619) 688-6988 or e-mail to:
Duty_Senior_Const_District11@dot.ca.gov.
The responses to
bidder' inquiries, unless incorporated into a formal addenda to the contract,
are not a part of the contract and are provided for the bidder's convenience
only. In some instances, the question and answer may represent a summary
of the matters discussed rather than a word-for-word recitation. The responses
may be considered along with all other information furnished to prospective
bidders for the purpose of bidding on the project. The availability or
use of information provided in the responses to bidder' inquiries is not
to be construed in any way as a waiver of the provisions of Section 2-1.03
of the Standard Specifications or any other provision of the contract,
the plans, Standard Specifications or Special Provisions, nor to excuse
the contractor from full compliance with those contract requirements. Bidders
are cautioned that subsequent responses or contract addenda may affect
or vary a response previously given.
Caltrans District 11 Construction Department
has developed this method of answering Bidder's Inquiries to better serve
the needs of the Contractors who bid on our Projects. Caltrans District
11 Construction Department will post all of the questions submitted by
any of the contractors that are registered Planholders for that Contract,
but reserves the right to not answer any questions deemed unsatisfactory
for public viewing.
The BIDDER'S INQUIRIES
& RESPONSES will be updated continuously and all attempts will be made
to do the final posting by 15:00 on Wednesday prior to the bid opening.
INFORMATION
AVAILABLE
|
|
|
|
|
|
|
|
|
|
10/09/03 |
|
|
BIDDER'S
INQUIRY SUBMITTAL FORM
|
|
Inquiry |
|
Q:10/02/03 |
Plan Sheet /
Specification Reference=NOTICE TO CONTRACTORS
When will the cross sections be available and where?
5560 Ruffin Road Suite 5 San Diego, CA 92123 (858) 541-1500 FAX (858) 278-0558 e-mail to plot@mesablueprint.com San Diego, CA 92123 |
|
Q:10/15/03 |
Plan Sheet /
Specification Reference=
1. If a Contractor who owns/controls his own commercial material facility, including aggregates, asphalt-concrete, and aggregate bases, supplies itself on this project in the capacity as a Prime Contractor, is trucking from the commercial facility owned/controlled by the Prime Contractor considered covered work?
|
|
Q:10/30/03 |
Plan Sheet /
Specification Reference= BID ITEM # 134 TRAFFIC MONITORING STATION (LOCATION
1) PLAN SHEET E-3 & E-10
SHEETS E-4 E-6 E-7 E-10 E-11 1. SHEET E-4 SAYS SEE SIGN DETAIL ON SHEET S-1 SHEET S-1 SAYS ES-6U-TYPE 5 THERE IS NO ES-6U PLEASE CLARIFY, SHEET E-6 STATES III B R SERVICE. WHICH IS CORRECT? E-7 SHOWS TWO POLES WITH FLASHING BEACON CAN YOU CLARIFY WHAT TYPE POLES AND ARE R/B CTRS NEEDED? E-10 AND E-11 ARE THE LOOPS GOING IN THE NEW CONCRETE ROAD? AND SHOULD THEY BE PERFORMED?
|
|
Q:11/06/03 R:11/14/03 |
Plan Sheet /
Specification Reference= #34- Roadway Ex.
Special provisions section 10-1.32
states that compaction for foundation treatment will be paid for as roadway
ex, but quantity is shown in the quantity summary. What quantities
are correct?
|
|
Q:11/07/03 |
Plan Sheet /
Specification Reference=Special Provisions Section 3 Award and
Execution of contract. Special Provisions Section 10-1.02 Water Pollution Control. In Section 3 of the Special Provisions,
the number of working days
1. Request is reasonable.
|
|
Q:11/07/03 R:11/14/03 |
Plan Sheet /
Specification Reference=
On the cross sections line "AW" at station 117+00 to the right the finish grade line never daylights with the existing grade. If you check the grading plans it shows you only grading the slope. This leads me to believe that at the toe of the slope your finish grade should match existing grade. This is not what is shown on the cross sections. This also occurs at sta 118+40 on the "AW" line. Could you please clarify what is supposed to happen.
|
|
Q:11/07/03 R:11/17/03 |
Plan Sheet /
Specification Reference=
I am wondering where you have taken
into account in your earthwork summary for shrink or swell? There
is no information in the plans that I can find. I was also wondering
if there were earthwork calculation sheets available? Usually they
are included with the cross sections, but I didn't happen to see any with
this particular job. Thanks.
|
|
Q:11/07/03 |
Plan Sheet /
Specification Reference=Special Provisions Section 3 Award and Execution
of contract. Special Provisions Section 10-1.02 Water Pollution Control.
In Section 3 of the Special Provisions,
the number of working days must not exceed 450 which is approximately 20
months. In Section 10-1.02, the rainy season is defined as between
Aug 1 and Oct 1, and between Nov 1 and
|
|
Q:11/10/03 |
Plan Sheet /
Specification Reference=
What is happening on the cross sections on the HUN line between Sta 14+60 and 15+60? Which line on the sections is the actual existing contour? Are we responsible for filling in the channel in that area? It looks like from 15+60 to 16+60 we do fill it in. Please clarify.
|
|
Q:11/14/03 |
Plan Sheet /
Specification Reference= Plan sheets L-7 to L13 and G-51 to G-62
In the Contract Plans, Layout sheets
L-7 to L-13 direct the
|
|
Q:11/17/03 |
Plan Sheet /
Specification Reference= Plan sheets L-7 to L13 and G-51 to G-62
The weights for items #79, 80, 81 &
82 are not correct. Please review and advise us of action to be taken.
|
|
Q:11/17/03 |
Plan Sheet /
Specification Reference= 510129, Class 2 Concrete (Box Culvert), Sheet
C-13 & D-83
For the box culverts, there is no specified height or span for any of the box culverts. What are the spans and heights of the box culverts?
|