Interstate-205 Stage II and Stage III Proposed Construction Schedule Stage 1
This work will be completed on Interstate 205 between Construct Soundwalls (2 eastbound Locations) Extend Auxiliary Lane at Eleventh Street On-ramp Stage 2 This work will be completed on Interstate 205 between Replace Existing Concrete Pavement Place Asphalt Concrete Overlay Stage 3 Some of this work may be completed in conjunction with Stage 1. This will work be completed on Interstate 205 Begin Bridge Widening (Piles and Columns) Widen Eastbound Interstate-205 Bridge over Interstate-5 Stage 4 This work will be completed on Interstate 205 between Complete Bridge Widening Construct New Lanes (In Median) Stage 5 This work will be completed on Interstate 205 between Complete Asphalt Construction Overlay Complete Final Roadway Work |