Questions and Answers |
|
Q: What are the hours of construction? A: The hours of construction on this project will vary depending on what work is being done and the location of the work. Monday-Friday (eastbound 11 pm-6 am; westbound 9 pm-3 am)
Q: Is there a penalty if a contractor does not pick up on time? A: Yes. There is a penalty and it is outlined in their contract.
Q: Will I-205 ever be completely closed? A: No. I-205 will never be completely closed.
Q: Will there be advanced notification for lane shifts and ramp closures? A: Yes. Information for lane shifts and ramp closures will be posted on the Caltrans website (www.dot.ca.gov/dist10), under the I-205 link and at the job site.
Q: Will Caltrans give a public notice via Tracy TV? A: Caltrans would be happy to give a public notice on Tracy TV.
Q: Will Caltrans inform affected bordering neighborhoods when any loud work is going to take place? A: Yes. Notice will be given to those neighborhoods that may be affected by any loud construction work.
Q: Could bridge or widening work be done during the day? Pile driving might be better during the day. A: Yes. There could be bridge work done during the day. Notice will be given to those neighborhoods that may be affected.
Q: Are soundwalls and bridge work being done to allow for 8 lanes in the future? A: No. There is no work in the contract to accommodate for 8 lanes.
Q: Will Caltrans make presentations to the public? A: Yes. If requested, Caltrans will be available for additional public presentations/ meetings.
Q: Will information be displayed on the overhead Changeable Message Signs? A: No. Changeable Message Signs will be used if there are accidents or horrific traffic congestion. They will not be used for general information.
|