Questions and Answers

Q:  What are the hours of construction?

A: The hours of construction on this project will vary depending on what work is

being done and the location of the work.  Monday-Friday (eastbound 11 pm-6 am;

westbound 9 pm-3 am)

  

Q:  Is there a penalty if a contractor does not pick up on time?

A:   Yes.  There is a penalty and it is outlined in their contract.

 

Q:  Will I-205 ever be completely closed?

A:   No.  I-205 will never be completely closed.

 

Q:  Will there be advanced notification for lane shifts and ramp closures?

A: Yes.  Information for lane shifts and ramp closures will be posted on the Caltrans

website  (www.dot.ca.gov/dist10), under the I-205 link and at the job site.

 

Q:  Will Caltrans give a public notice via Tracy TV?

A:  Caltrans would be happy to give a public notice on Tracy TV.

 

Q: Will Caltrans inform affected bordering neighborhoods when any loud work is going to take

 place?

A: Yes.  Notice will be given to those neighborhoods that may be affected by any loud

construction work.

 

Q:  Could bridge or widening work be done during the day?  Pile driving might be better during the day.

A: Yes.  There could be bridge work done during the day.  Notice will be given to those neighborhoods that may be affected.

 

Q:  Are soundwalls and bridge work being done to allow for 8 lanes in the future?

A:  No.  There is no work in the contract to accommodate for 8 lanes.

 

Q:  Will Caltrans make presentations to the public?

A: Yes.  If requested, Caltrans will be available for additional public presentations/

meetings.

 

Q:  Will information be displayed on the overhead Changeable Message Signs?

A:  No.  Changeable Message Signs will be used if there are accidents or horrific traffic congestion.  They will not be used for general information.

 

 

 

 

 

 

 

 

 