Construction Check List

Stage 1

This phase consisted of work on I- 205 between Eleventh Street and Grant Line Road and between the eastbound Tracy Boulevard on-ramp and the Mac Arthur Drive off-ramp.

        Construct Soundwalls (2 eastbound locations)  Completed.

        Extend Auxiliary Lane on Eleventh Street on-ramp  Completed.

 

Stage 2

This phase will consist of work on I-205 between Eleventh Street and I-5.

      Replace Existing Concrete Pavement   In Progress - 90 Percent Completed.

      Place Asphalt Concrete Overlay   Completed.

 

Stage 3

Some of this work may be completed in conjunction with State 1.  This phase will consist of work on I-205 between Eleventh Street and I-5.

      Begin Bridge Widening (Piles and Columns)  In Progress - 45 Percent Completed.

        Widen Eastbound I-205 Bridge over I-5  In Progress - 20 Percent Completed.

 

Stage 4

This phase will consist of work on I-205 between Eleventh Street and I-5.

       Complete Bridge Widening  In Progress - 25 Percent Completed.

       Construct New Lanes (In Median)  In Progress - 20 Percent Completed.

 

Stage 5

This phase will consist of work on I-205 between Eleventh Street and I-5.

         Complete Asphalt Construction Overlay  Work to begin Fall 2009.

         Complete Final Roadway Work Work to begin Fall 2009.

Projected Construction Schedule