Construction Check List |
|
Stage 1 This phase consisted of work on I- 205 between Eleventh Street and Grant Line Road and between the eastbound Tracy Boulevard on-ramp and the Mac Arthur Drive off-ramp. Construct Soundwalls (2 eastbound locations) Completed. Extend Auxiliary Lane on Eleventh Street on-ramp Completed.
Stage 2 This phase will consist of work on I-205 between Eleventh Street and I-5. Replace Existing Concrete Pavement In Progress - 90 Percent Completed. Place Asphalt Concrete Overlay Completed.
Stage 3 Some of this work may be completed in conjunction with State 1. This phase will consist of work on I-205 between Eleventh Street and I-5. Begin Bridge Widening (Piles and Columns) In Progress - 45 Percent Completed. Widen Eastbound I-205 Bridge over I-5 In Progress - 20 Percent Completed.
Stage 4 This phase will consist of work on I-205 between Eleventh Street and I-5. Complete Bridge Widening In Progress - 25 Percent Completed. Construct New Lanes (In Median) In Progress - 20 Percent Completed.
Stage 5 This phase will consist of work on I-205 between Eleventh Street and I-5. Complete Asphalt Construction Overlay Work to begin Fall 2009. Complete Final Roadway Work Work to begin Fall 2009. |
Projected Construction Schedule |