California Department of Transportation District 1
 

Confusion Hill in Mendocino County. 
This $67 million project was awarded to MCM Construction spring 2006. The project consists of two bridges crossing the South Fork Eel 
River twice.  The south bridge will be 255 feet tall and 1,355 feet long. The foundation work for the two bridges is underway. The 
project is on schedule, with completion scheduled for fall 2009.