| EB | 05/27/2008 06:00PM | 05/28/2008 06:00AM | Paramount Blvd | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | EB Artesia Frwy |
| WB | 05/27/2008 06:00PM | 05/28/2008 06:00AM | Long Beach Frwy, Rte 710 | HOV | All | 1 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Harbor Frwy, Rte 110 |
| WB | 05/27/2008 06:00PM | 05/28/2008 06:00AM | Long Beach Frwy, Rte 710 | Mainline | #1 | 5 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Harbor Frwy, Rte 110 |
| WB | 05/27/2008 06:00PM | 05/28/2008 06:00AM | Long Beach Frwy, Rte 710 | Mainline | #5 | 5 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Harbor Frwy, Rte 110 |
| WB | 05/27/2008 07:00PM | 05/28/2008 05:00AM | Long Beach Frwy, Rte 710 | Mainline | #1,#2 | 5 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Harbor Frwy, Rte 110 |
| WB | 05/27/2008 07:00PM | 05/28/2008 05:00AM | Long Beach Frwy, Rte 710 | Mainline | #4,#5 | 5 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Harbor Frwy, Rte 110 |
| WB | 05/27/2008 07:00PM | 05/28/2008 05:00AM | WB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Alameda St / Santa Fe Ave |
| WB | 05/27/2008 07:00PM | 05/28/2008 05:00AM | Downey Ave | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | WB Artesia Frwy |
| EB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | EB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Acacia Ave |
| EB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | EB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Alameda St / Santa Fe Ave |
| EB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | EB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Avalon Blvd |
| EB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | EB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Cherry Ave |
| EB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | EB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Downey Ave |
| EB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | EB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Main St |
| EB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | EB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Wilmington Ave |
| EB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | EB Riverside Frwy | Off-Ramp | All | 1 | Drainage Work, | N&S Long Beach Blvd |
| EB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | Alameda St / Santa Fe Ave | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | EB Artesia Frwy |
| EB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | Atlantic Ave | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | EB Artesia Frwy |
| EB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | Avalon Blvd | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | EB Artesia Frwy |
| EB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | Cherry Ave | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | EB Artesia Frwy |
| EB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | Long Beach Blvd | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | EB Artesia Frwy |
| EB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | Main St | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | EB Artesia Frwy |
| WB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | WB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Atlantic Ave |
| WB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | WB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Avalon Blvd |
| WB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | WB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Central Ave |
| WB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | WB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Main St |
| WB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | WB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Paramount Blvd |
| WB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | Acacia Ave | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | WB Artesia Frwy |
| WB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | Atlantic Ave | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | WB Artesia Frwy |
| WB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | Avalon Blvd | On-Ramp | All | 1 | Pavement Rehabilitation,Slab Replacement,Including on & off ramps (no consecutive ramps will be closed), | WB Artesia Frwy |
| WB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | Central Ave | On-Ramp | All | 1 | Pavement Rehabilitation,Slab Replacement,Including on & off ramps (no consecutive ramps will be closed), | WB Artesia Frwy |
| WB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | Cherry Ave | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | WB Artesia Frwy |
| WB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | Lakewood Blvd, Rte 19 | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | WB Artesia Frwy |
| WB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | Long Beach Blvd | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | WB Artesia Frwy |
| WB | 05/27/2008 07:00PM | 05/28/2008 06:00AM | Wilmington Ave | On-Ramp | All | 1 | Pavement Rehabilitation,Slab Replacement,Including on & off ramps (no consecutive ramps will be closed), | WB Artesia Frwy |
| EB | 05/27/2008 07:00PM | 05/28/2008 07:00AM | Harbor Frwy, Rte 110 | HOV | All | 1 | Bridge Work,Pavement Rehabilitation, | Long Beach Frwy, Rte 710 |
| EB | 05/27/2008 07:00PM | 05/28/2008 07:00AM | Harbor Frwy, Rte 110 | Mainline | #1 | 5 | Bridge Work,Pavement Rehabilitation, | Long Beach Frwy, Rte 710 |
| EB | 05/27/2008 07:00PM | 05/28/2008 07:00AM | Harbor Frwy, Rte 110 | Mainline | #5 | 5 | Bridge Work,Pavement Rehabilitation, | Long Beach Frwy, Rte 710 |
| WB | 05/27/2008 08:00PM | 05/28/2008 05:00AM | Downey Ave | HOV | All | 1 | Bridge Work,Pavement Rehabilitation,Median Barrier Installation, | Long Beach Frwy, Rte 710 |
| WB | 05/27/2008 08:00PM | 05/28/2008 05:00AM | Downey Ave | Mainline | #1 | 5 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Long Beach Frwy, Rte 710 |
| WB | 05/27/2008 08:00PM | 05/28/2008 05:00AM | Downey Ave | Mainline | #5 | 5 | Bridge Work,Pavement Rehabilitation,Median Barrier Installation, | Long Beach Frwy, Rte 710 |
| EB | 05/27/2008 08:00PM | 05/28/2008 06:00AM | EB Artesia Frwy | Connector | All | 2 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | SB Long Beach Frwy, Rte 710 |
| EB | 05/27/2008 08:00PM | 05/28/2008 06:00AM | Long Beach Frwy, Rte 710 | HOV | All | 1 | Bridge Work,Pavement Rehabilitation, | Long Beach Frwy, Rte 710 |
| EB | 05/27/2008 08:00PM | 05/28/2008 06:00AM | Long Beach Frwy, Rte 710 | HOV | #1 | 1 | Bridge Work,Pavement Rehabilitation, | Downey Ave |
| EB | 05/27/2008 08:00PM | 05/28/2008 06:00AM | EB Long Beach Frwy, Rte 710 | Mainline | #1 | 3 | Bridge Work,Pavement Rehabilitation, | EB Long Beach Frwy, Rte 710 |
| EB | 05/27/2008 08:00PM | 05/28/2008 06:00AM | Long Beach Frwy, Rte 710 | Mainline | #1 | 5 | Bridge Work,Pavement Rehabilitation, | Downey Ave |
| EB | 05/27/2008 08:00PM | 05/28/2008 06:00AM | Harbor Frwy, Rte 110 | Mainline | #1,#2 | 5 | Bridge Work,Pavement Rehabilitation, | Long Beach Frwy, Rte 710 |
| EB | 05/27/2008 08:00PM | 05/28/2008 06:00AM | EB Long Beach Frwy, Rte 710 | Mainline | #3 | 3 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | EB Long Beach Frwy, Rte 710 |
| EB | 05/27/2008 08:00PM | 05/28/2008 06:00AM | Harbor Frwy, Rte 110 | Mainline | #4,#5 | 5 | Bridge Work,Pavement Rehabilitation, | Long Beach Frwy, Rte 710 |
| EB | 05/27/2008 08:00PM | 05/28/2008 06:00AM | EB Long Beach Frwy, Rte 710 | Mainline | #5 | 5 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | EB Downey Ave |
| EB | 05/27/2008 08:00PM | 05/28/2008 06:00AM | EB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Central Ave |
| EB | 05/27/2008 08:00PM | 05/28/2008 06:00AM | EB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Long Beach Blvd |
| WB | 05/27/2008 08:00PM | 05/28/2008 06:00AM | WB Artesia Frwy | Connector | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | NB Long Beach Frwy, Rte 710 |
| WB | 05/27/2008 08:00PM | 05/28/2008 06:00AM | WB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Long Beach Blvd |
| WB | 05/27/2008 08:00PM | 05/28/2008 06:00AM | WB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Wilmington Ave |
| WB | 05/27/2008 08:00PM | 05/28/2008 06:00AM | Paramount Blvd | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | WB Artesia Frwy |
| EB | 05/27/2008 09:00AM | 05/27/2008 03:00PM | EB Riverside Frwy | Off-Ramp | All | 1 | Drainage Work, | N&S Long Beach Blvd |
| WB | 05/27/2008 09:00PM | 05/28/2008 05:00AM | Long Beach Frwy, Rte 710 | HOV | All | 1 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Long Beach Frwy, Rte 710 |
| WB | 05/27/2008 09:00PM | 05/28/2008 05:00AM | Long Beach Frwy, Rte 710 | Mainline | #1 | 3 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Long Beach Frwy, Rte 710 |
| WB | 05/27/2008 09:00PM | 05/28/2008 05:00AM | Long Beach Frwy, Rte 710 | Mainline | #3 | 3 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Long Beach Frwy, Rte 710 |
| EB | 05/27/2008 09:00PM | 05/28/2008 06:00AM | Wilmington Ave | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | EB Artesia Frwy |
| WB | 05/27/2008 10:00PM | 05/28/2008 05:00AM | WB Artesia Frwy | Connector | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Harbor Frwy, Rte 110 |
| WB | 05/27/2008 10:00PM | 05/28/2008 05:00AM | Downey Ave | Mainline | #1,#2 | 5 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Long Beach Frwy, Rte 710 |
| WB | 05/27/2008 10:00PM | 05/28/2008 05:00AM | Long Beach Frwy, Rte 710 | Mainline | #1,#2,#3 | 5 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Harbor Frwy, Rte 110 |
| WB | 05/27/2008 10:00PM | 05/28/2008 05:00AM | Long Beach Frwy, Rte 710 | Mainline | #3,#4,#5 | 5 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Harbor Frwy, Rte 110 |
| WB | 05/27/2008 10:00PM | 05/28/2008 05:00AM | Downey Ave | Mainline | #4,#5 | 5 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Long Beach Frwy, Rte 710 |
| WB | 05/27/2008 10:00PM | 05/28/2008 05:00AM | Main St | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | WB Artesia Frwy |
| EB | 05/27/2008 10:00PM | 05/28/2008 06:00AM | EB Artesia Frwy | Connector | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | NB Long Beach Frwy, Rte 710 |
| EB | 05/27/2008 10:00PM | 05/28/2008 06:00AM | EB Long Beach Frwy, Rte 710 | Mainline | #1,#2 | 5 | Bridge Work,Pavement Rehabilitation, | EB Downey Ave |
| EB | 05/27/2008 10:00PM | 05/28/2008 06:00AM | Harbor Frwy, Rte 110 | Mainline | #1,#2,#3 | 5 | Bridge Work,Pavement Rehabilitation, | Long Beach Frwy, Rte 710 |
| EB | 05/27/2008 10:00PM | 05/28/2008 06:00AM | Harbor Frwy, Rte 110 | Mainline | #3,#4,#5 | 5 | Bridge Work,Pavement Rehabilitation, | Long Beach Frwy, Rte 710 |
| EB | 05/27/2008 10:00PM | 05/28/2008 06:00AM | EB Long Beach Frwy, Rte 710 | Mainline | #4,#5 | 5 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | EB Downey Ave |
| EB | 05/27/2008 10:00PM | 05/28/2008 06:00AM | EB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Atlantic Ave |
| EB | 05/27/2008 10:00PM | 05/28/2008 06:00AM | EB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Paramount Blvd |
| EB | 05/27/2008 10:00PM | 05/28/2008 06:00AM | Central Ave | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | EB Artesia Frwy |
| WB | 05/27/2008 10:00PM | 05/28/2008 06:00AM | WB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Downey Ave |
| WB | 05/27/2008 11:00PM | 05/28/2008 04:00AM | Long Beach Frwy, Rte 710 | Mainline | #1,#2 | 3 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Long Beach Frwy, Rte 710 |
| WB | 05/27/2008 11:00PM | 05/28/2008 04:00AM | Long Beach Frwy, Rte 710 | Mainline | #2,#3 | 3 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Long Beach Frwy, Rte 710 |
| EB | 05/27/2008 11:00PM | 05/28/2008 05:00AM | EB Long Beach Frwy, Rte 710 | Mainline | #1,#2 | 3 | Bridge Work,Pavement Rehabilitation, | EB Long Beach Frwy, Rte 710 |
| EB | 05/27/2008 11:00PM | 05/28/2008 05:00AM | EB Long Beach Frwy, Rte 710 | Mainline | #1,#2,#3 | 5 | Bridge Work,Pavement Rehabilitation, | EB Downey Ave |
| EB | 05/27/2008 11:00PM | 05/28/2008 05:00AM | EB Long Beach Frwy, Rte 710 | Mainline | #2,#3 | 3 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | EB Long Beach Frwy, Rte 710 |
| EB | 05/27/2008 11:00PM | 05/28/2008 05:00AM | EB Long Beach Frwy, Rte 710 | Mainline | #3,#4,#5 | 5 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | EB Downey Ave |
| WB | 05/27/2008 11:00PM | 05/28/2008 05:00AM | WB Artesia Frwy | Connector | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | SB Long Beach Frwy, Rte 710 |
| WB | 05/27/2008 11:00PM | 05/28/2008 05:00AM | Downey Ave | Mainline | #1,#2,#3 | 5 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Long Beach Frwy, Rte 710 |
| WB | 05/27/2008 11:00PM | 05/28/2008 05:00AM | Downey Ave | Mainline | #3,#4,#5 | 5 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Long Beach Frwy, Rte 710 |
| EB | 05/27/2008 11:59PM | 05/28/2008 04:00AM | EB Long Beach Frwy, Rte 710 | Mainline | #1,#2,#3,#4 | 5 | Bridge Work,Pavement Rehabilitation, | EB Downey Ave |
| EB | 05/27/2008 11:59PM | 05/28/2008 04:00AM | EB Long Beach Frwy, Rte 710 | Mainline | #2,#3,#4,#5 | 5 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | EB Downey Ave |
| WB | 05/27/2008 11:59PM | 05/28/2008 04:00AM | Long Beach Frwy, Rte 710 | Mainline | #1,#2,#3,#4 | 5 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Harbor Frwy, Rte 110 |
| WB | 05/27/2008 11:59PM | 05/28/2008 04:00AM | Long Beach Frwy, Rte 710 | Mainline | #2,#3,#4,#5 | 5 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Harbor Frwy, Rte 110 |
| EB | 05/27/2008 11:59PM | 05/28/2008 05:00AM | EB Artesia Frwy | Connector | All | 2 | Bridge Work,Pavement Rehabilitation, | NB Harbor Frwy, Rte 110 |
| EB | 05/27/2008 11:59PM | 05/28/2008 05:00AM | Harbor Frwy, Rte 110 | Mainline | #1,#2,#3,#4 | 5 | Bridge Work,Pavement Rehabilitation, | Long Beach Frwy, Rte 710 |
| EB | 05/27/2008 11:59PM | 05/28/2008 05:00AM | Harbor Frwy, Rte 110 | Mainline | #2,#3,#4,#5 | 5 | Bridge Work,Pavement Rehabilitation, | Long Beach Frwy, Rte 710 |
| WB | 05/27/2008 11:59PM | 05/28/2008 06:00AM | WB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Cherry Ave |
| WB | 05/28/2008 01:00AM | 05/28/2008 04:00AM | Downey Ave | Mainline | #1,#2,#3,#4 | 5 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Long Beach Frwy, Rte 710 |
| WB | 05/28/2008 01:00AM | 05/28/2008 04:00AM | Downey Ave | Mainline | #2,#3,#4,#5 | 5 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Long Beach Frwy, Rte 710 |
| EB | 05/28/2008 06:00PM | 05/29/2008 06:00AM | Paramount Blvd | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | EB Artesia Frwy |
| WB | 05/28/2008 06:00PM | 05/29/2008 06:00AM | Long Beach Frwy, Rte 710 | HOV | All | 1 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Harbor Frwy, Rte 110 |
| WB | 05/28/2008 06:00PM | 05/29/2008 06:00AM | Long Beach Frwy, Rte 710 | Mainline | #1 | 5 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Harbor Frwy, Rte 110 |
| WB | 05/28/2008 06:00PM | 05/29/2008 06:00AM | Long Beach Frwy, Rte 710 | Mainline | #5 | 5 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Harbor Frwy, Rte 110 |
| WB | 05/28/2008 07:00PM | 05/29/2008 05:00AM | Long Beach Frwy, Rte 710 | Mainline | #1,#2 | 5 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Harbor Frwy, Rte 110 |
| WB | 05/28/2008 07:00PM | 05/29/2008 05:00AM | Long Beach Frwy, Rte 710 | Mainline | #4,#5 | 5 | Bridge Work,Median Barrier Installation,Pavement Rehabilitation, | Harbor Frwy, Rte 110 |
| WB | 05/28/2008 07:00PM | 05/29/2008 05:00AM | WB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Alameda St / Santa Fe Ave |
| WB | 05/28/2008 07:00PM | 05/29/2008 05:00AM | Downey Ave | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | WB Artesia Frwy |
| EB | 05/28/2008 07:00PM | 05/29/2008 06:00AM | EB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Acacia Ave |
| EB | 05/28/2008 07:00PM | 05/29/2008 06:00AM | EB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Alameda St / Santa Fe Ave |
| EB | 05/28/2008 07:00PM | 05/29/2008 06:00AM | EB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Avalon Blvd |
| EB | 05/28/2008 07:00PM | 05/29/2008 06:00AM | EB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Cherry Ave |
| EB | 05/28/2008 07:00PM | 05/29/2008 06:00AM | EB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Downey Ave |
| EB | 05/28/2008 07:00PM | 05/29/2008 06:00AM | EB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Main St |
| EB | 05/28/2008 07:00PM | 05/29/2008 06:00AM | EB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Wilmington Ave |
| EB | 05/28/2008 07:00PM | 05/29/2008 06:00AM | EB Riverside Frwy | Off-Ramp | All | 1 | Drainage Work, | N&S Long Beach Blvd |
| EB | 05/28/2008 07:00PM | 05/29/2008 06:00AM | Alameda St / Santa Fe Ave | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | EB Artesia Frwy |
| EB | 05/28/2008 07:00PM | 05/29/2008 06:00AM | Atlantic Ave | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | EB Artesia Frwy |
| EB | 05/28/2008 07:00PM | 05/29/2008 06:00AM | Avalon Blvd | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | EB Artesia Frwy |
| EB | 05/28/2008 07:00PM | 05/29/2008 06:00AM | Cherry Ave | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | EB Artesia Frwy |
| EB | 05/28/2008 07:00PM | 05/29/2008 06:00AM | Long Beach Blvd | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | EB Artesia Frwy |
| EB | 05/28/2008 07:00PM | 05/29/2008 06:00AM | Main St | On-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | EB Artesia Frwy |
| WB | 05/28/2008 07:00PM | 05/29/2008 06:00AM | WB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Atlantic Ave |
| WB | 05/28/2008 07:00PM | 05/29/2008 06:00AM | WB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Avalon Blvd |
| WB | 05/28/2008 07:00PM | 05/29/2008 06:00AM | WB Artesia Frwy | Off-Ramp | All | 1 | Bridge Work,Pavement Rehabilitation,Including on & off ramps (no consecutive ramps will be closed), | Central Ave |