Contractors
ea: 290104
Route:
91
County:
LA
Work:
| Mile Post Beg./End: | 4.0/11.0 |
| Location: | ON LA-91 BTWEEN 0.2 M E OF LA-110 & 0.6 M W OF LA-105 |
| Detailed Project Scope: | Concrete Barrier & Reconstruct MBGR |
| Estimate Cost Range (x $million) | 1 - 10 |
| Working Days Range: | 250 |
| Proposed Advertisement Date: | 2016-11-01 |
| Comments: | Pavement Quantities not defined in PID. 15,520 LF Concrete Barrier and 9600 LF MBGR |
| Types Of Work |
| Concrete Barrier |
| Guard Railing |
| Quantity Of Major Highway Items |
| Asphalt Condrete (Tons) | 0 |
| PCC (cy) | 0 |
| Aggregate Base (cy) | 0 |
| Imported Borrow (cy) | 25000 |
| Roadway Excavation (cy) | 0 |
| Major Structure Items |
| Steel (lbs): | 0 |
| PCC (cy): | 0 |