ea: 290104

Route: 91     County: LA     Work:
Mile Post Beg./End: 4.0/11.0
Location: ON LA-91 BTWEEN 0.2 M E OF LA-110 & 0.6 M W OF LA-105
Detailed Project Scope: Concrete Barrier & Reconstruct MBGR
Estimate Cost Range (x $million) 1 - 10
Working Days Range: 250
Proposed Advertisement Date: 2016-11-01
Comments: Pavement Quantities not defined in PID. 15,520 LF Concrete Barrier and 9600 LF MBGR
Types Of Work  
Arrow Concrete Barrier
Arrow Guard Railing
Quantity Of Major Highway Items  
Asphalt Condrete (Tons) 0
PCC (cy) 0
Aggregate Base (cy) 0
Imported Borrow (cy) 25000
Roadway Excavation (cy) 0
Major Structure Items  
Steel (lbs): 0
PCC (cy): 0