Welcome to the State of California Caltrans, District 7 Header
Governor Brown Brian P. Kelly Malcolm Dougherty Michael Miles
 
Caltrans District 7 0n Twitter
Caltrans District 7 On Friendfeed
Caltrans District 7 on FeedBurner
Caltrans District 7 RSS Feed (Atom)
 

ea: 2487U4

Route: 210     County: LA     Work:
Mile Post Beg./End: 29.2/31.5
Location: IN LA COUNTY AT VARIOUS LOCATIONS FROM SIERRA MADRE STN TO SANTA ANITA
Detailed Project Scope: PGL FOOTHILL EXTENSION SEG I
Estimate Cost Range (x $million) 1 - 10
Working Days Range: 210
Proposed Advertisement Date: 2013-09-01
Comments: LACMTA project
Types Of Work  
Arrow Bridge
Quantity Of Major Highway Items  
Asphalt Condrete (Tons) 0
PCC (cy) 0
Aggregate Base (cy) 0
Imported Borrow (cy) 0
Roadway Excavation (cy) 0
Major Structure Items  
Steel (lbs): 0
PCC (cy): 0

Page Last Modified 03/5/13 08:58
Back Button | Back To Page Top Link