Viewing inquiries for 08-1C38U4

Submit new inquiry for this project


Inquiry #1: Reference Section 9 Payment 9-1.16C: Please consider adding: Pavement Reinforcement, Tie Bars, Tie Bar Baskets, Dowel Bar, Dowel Bar Baskets; to the listing of items eligible for progress payment even if they are not incorporated into the work. This will reduce the risk on the contractor and allow more competitive bidding.
Inquiry submitted 11/14/2018

Response #1:submitted for consideration
Response posted 11/15/2018


Response #2:This matter will be addressed via an addendum.
Response posted 12/06/2018




Inquiry #2: Some of the layout drawings do not address how lane 4 is to be constructed at the on and off ramp locations. This applies to sheet L-2, L-4, L-5, L-6, L-11, L-13, L-26, L-27. The layout drawings show that lane 4 is to be constructed using structure section 1, which is standard JPCP, but the stage construction nor the traffic handling plans show how this work is to be constructed. Please clarify.
Inquiry submitted 11/26/2018

Response #1:submitted for consideration
Response posted 11/26/2018




Inquiry #3: Sheet L-15, L-18 has conflict between structure sections being called out as standard JPCP and the hatching showing it as JPCP Rapid Set. Please clarify.
Inquiry submitted 11/26/2018

Response #1:submitted for consideration
Response posted 11/26/2018


Response #2:An addendum will be issued to address this discrepancy.
Response posted 12/11/2018




Inquiry #4: Sheet L-24 appears to be missing the callout for section 8 along the shoulder both WB / EB from STA 329+00 to 338+00. Please clarify.
Inquiry submitted 11/26/2018

Response #1:submitted for consideration
Response posted 11/26/2018


Response #2:An addendum will be forthcoming to address this issue.
Response posted 12/11/2018




Inquiry #5: Sheet L-27 from STA 50+00 to 58+00 call for the Aux Lane to be structure section 1 but the stage construction and traffic handling sheets do not address how this work is to be completed. Please clarify.
Inquiry submitted 11/26/2018

Response #1:submitted for consideration
Response posted 11/26/2018


Response #2:An addendum will be forthcoming to address this issue.
Response posted 12/11/2018




Inquiry #6: In general, please review the layout, stage construction, and traffic handling drawings. There are major discrepancies between all plan sheets. Updated drawings are requested to accurately estimate this project.
Inquiry submitted 11/26/2018

Response #1:submitted for consideration
Response posted 11/26/2018


Response #2:An addendum will be forthcoming to address this issue.
Response posted 12/11/2018




Inquiry #7: Please provide lane closure charts for the mainline freeway that will allow the construction of the full depth rapid set replacement. Lane closure charts G1 and G2 do not provide sufficient time to complete this work.
Inquiry submitted 11/26/2018

Response #1:submitted for consideration
Response posted 11/26/2018


Response #2:Unless an addendum is issued, bid per current contract documents.
Response posted 12/11/2018




Inquiry #8: Please provide lane closure charts for the mainline freeway that will allow the construction of the full depth rapid set replacement. Lane closure charts G1 and G2 do not provide sufficient time to complete this work.
Inquiry submitted 11/26/2018

Response #1:submitted for consideration
Response posted 11/26/2018


Response #2:Unless an addendum is issued, bid per current contract documents.
Response posted 12/11/2018




Inquiry #9: Is there a SWPPP required for the project? If so, please provide a bid item for payment. Also, please provide the risk level for the project.
Inquiry submitted 11/26/2018

Response #1:submitted for consideration
Response posted 11/26/2018


Response #2:There is no SWPPP associated with this project. The appropriate WPCP bid item has been provided. This project carries no risk level pertinent to Storm Water.
Response posted 12/12/2018




Inquiry #10: PLAN SHEET L-1. Note 7 does not provide the structural section number for Stage 4. PLAN SHEETS L-28 TO L-30 from station RIV10-FN 69+10 TO 104+67.81 indicate the shoulder is to be removed and replaced with the Section 8 concrete pavement. Is this correct.
Inquiry submitted 11/28/2018

Response #1:submitted for consideration
Response posted 11/28/2018




Inquiry #11: PLAN SHEET L-12. Approximately 161+50 to 165+00 the call out on the drawings indicates the replacement highway pavement both east and west bound is structure section 1 but the hatch indicates structure section 8. Please clarify.
Inquiry submitted 11/28/2018

Response #1:submitted for consideration
Response posted 11/28/2018


Response #2:This is a typo and it should show structural section 8. An upcoming addendum will provide corrections.
Response posted 12/12/2018




Inquiry #12: PLAN SHEET L-17. Approximately 234+50 to 236+00 west bound and 232+00 to 236+00 east bound the call out on the drawings indicates the replacement highway pavement both east and west bound is structure section 1. This hatch indicates the shoulder is section 1 but the hatch in lanes 1 and 2 indicate structure section 8. Please clarify.
Inquiry submitted 11/28/2018

Response #1:submitted for consideration
Response posted 11/28/2018




Inquiry #13: PLAN SHEET L-18. Approximately 245+50, the call out on the drawings indicates the replacement highway pavement west bound is structure section 1 but the hatch indicates structure section 8. Please clarify.
Inquiry submitted 11/28/2018

Response #1:submitted for consideration
Response posted 11/28/2018




Inquiry #14: PLAN SHEET L-21 AND L-23. Approximately STA RIV10-C 284+33 TO 290+00 east bound and STA 288+00 to 290 west bound there is no call out for replacement shoulder pavement. Does this shoulder pavement get replaced in these locations? Starting at STA RIV10-C 299+00 and extending to the ramps near 304+00 the shoulder call out is section 8 but the hatching does not indicate rapid set pavement.
Inquiry submitted 11/28/2018

Response #1:submitted for consideration
Response posted 11/28/2018




Inquiry #15: PLAN SHEET L-50. Approximately STA RIV10-H 365+00 the call out on the drawings indicates the replacement highway pavement both east bound is structure section 1 but the hatch indicates structure section 8. Please clarify.
Inquiry submitted 11/28/2018

Response #1:submitted for consideration
Response posted 11/28/2018




Inquiry #16: Can Caltrans please provide the End Area Volume Calculations from all the roadway cross sections?
Inquiry submitted 11/29/2018

Response #1:submitted for consideration
Response posted 11/29/2018




Inquiry #17: Will Caltrans be providing waste areas along the Right of Way or in other areas for embankment of excess excavated material from the project?
Inquiry submitted 11/29/2018

Response #1:submitted for consideration
Response posted 12/05/2018




Inquiry #18: Will Caltrans be providing waste areas along the Right of Way or in other areas for embankment of excess excavated material from the project?
Inquiry submitted 11/29/2018

Response #1:submitted for consideration
Response posted 12/03/2018




Inquiry #19: PLAN SHEET NO. 360-524. The traffic handling plans, details and quantities do not address stage 4 construction. Please provide these drawings.
Inquiry submitted 11/29/2018

Response #1:submitted for consideration
Response posted 12/03/2018




Inquiry #20: PLAN SHEET TH-4. The traffic handling typical cross sections only show using temp barrier as identified within the middle cross section (RIV10-H 311+07 TO 518+00). Is it CALTRANS intent not to use any temporary barrier within all of stage 1 but for the stationing identified on page TH-4 even though there is also full depth removals in other areas of Stage 1 inside shoulder?
Inquiry submitted 11/29/2018

Response #1:submitted for consideration
Response posted 12/03/2018




Inquiry #21: PLAN SHEET TH-1 THROUGH TH-4. The traffic handling typical cross sections identify these sheets as stage 1 construction however the staging construction drawings identify stage 1 to be full depth replacement within the inside EB and WB shoulder. Plan sheets TH-1 through TH-4 appear to show stage 5 cold plane and overlay not stage 1 full depth replacement. Please clarify or provide the correct traffic handling drawings for stage 1 construction.
Inquiry submitted 11/29/2018

Response #1:submitted for consideration
Response posted 12/03/2018




Inquiry #22: PLAN SHEET CS-1. Note 5 identifies surface mounted channelizers and plastic drums shall be installed at any location shown on the plans or ordered by the engineer at any location. If additional channelizers and plastic drums are required and are not shown on the drawings. Will the contractor be compensated for this work in Bid Item 9-Channelizer and Bid Item 10-Plastic Traffic Drums?
Inquiry submitted 11/30/2018

Response #1:submitted for consideration
Response posted 12/03/2018




Inquiry #23: Based on the questions to date there are large issues with the contract documents that have been identified and need to be addressed by the Department in order for bidders to provide competitive pricing. Based on receiving timely information from the Department that address the issues we request that you extend the bid date a minimum of 2 weeks to allow enough time for the bidder’s to analyze the information. Due to the holiday season and numerous other large Caltrans projects bidding in the same time frame we request that the Department provides quick direction on this bid extension request so as Bidder’s can allocate resources accordingly.
Inquiry submitted 12/05/2018

Response #1:submitted for consideration
Response posted 12/05/2018




Inquiry #24: Typical cross sections sheets X-1 to X-16 show an existing pavement structure sections E and F along the inside shoulders for WB and EB. These existing pavement structure section are to be removed and some to be replaced with pavement structure section 7. Please provide a bid item and quantity for the removal of the AC section within existing structure sections E and F.
Inquiry submitted 12/06/2018

Response #1:submitted for consideration
Response posted 12/06/2018




Inquiry #25: PLAN SHEET PD-1 THROUGH PD-65. Traffic Stripe Detail 12M is called throughout the Pavement Delineation Plans. No quantity is allocated for the removal of the existing Traffic Stripe Detail 12M in Bid Item 87: Remove Thermoplastic Traffic Stripe. Please confirm that additional quantity needs to be added to Bid Item 87 for removal of Traffic Stripe Detail 12M.
Inquiry submitted 12/06/2018

Response #1:submitted for consideration
Response posted 12/06/2018




Inquiry #26: PLAN SHEET PDQ-1. In Table Column "DETAIL No. OR PAVEMENT MARKING" detail EXIST 13 is referenced. After reviewing Plan Sheet PD-1 through PD-65 no call outs are provided for detail EXIST 13. Please clarify or provide drawings for detail EXIST 13.
Inquiry submitted 12/06/2018

Response #1:submitted for consideration
Response posted 12/06/2018




Inquiry #27: Based on approval of the Contractor's submitted Traffic Control Plans will all temporary stripe, channelizers, plastic drums, temporary pavement markings, temporary Railing (Type K), and Temporary Crash Cushion Module all be paid by the provided unit price bid items?
Inquiry submitted 12/06/2018

Response #1:submitted for consideration
Response posted 12/06/2018




Inquiry #28: The landscaping layout plans show several locations for hardscape areas. Please provide bid item and quantities of these hardscape areas.
Inquiry submitted 12/10/2018

Response #1:submitted for consideration
Response posted 12/10/2018




Inquiry #29: The THQ Plan Sheets are the summary tables for the Traffic Handling Quantities including Temporary K-Rail. For Stage 1 work for the center median it only shows approximately 19,000 Lf for WB and same for EB in the general station range of 311-518. Why is the Department only showing Temporary K-Rail in this location and not planning on placing Temporary k-Rail in the Pavement Section 7 Full Dig out and replace of the median shoulder during Stage 1 in the following areas? Riv 10-A 428+00-50+00, Riv 10-A 58+80-157+00, Riv 10-A 165+00-191+00, Riv10 EN/ES 27+90-Riv10- FN/FS 91+00, Riv10 FN/FS 91+00-105+00, Riv10 FN/FS 122+00-171+00, Riv 10 FN/FS 182+20-282+60. Also why is there a gap in the Temporary K-Rail at the following locations from Plan Sheet THQ-1- Riv 10-H 370-372, Riv 10-H 395-400+69 and Riv 10-H 428-432 for the Stage 1 work?
Inquiry submitted 12/10/2018

Response #1:submitted for consideration
Response posted 12/10/2018


Response #2:An addendum will be forthcoming to address this issue.
Response posted 12/12/2018




Inquiry #30: The THQ Plan Sheets are the summary tables for the Traffic Handling Quantities including Temporary K-Rail. For Stage 2 & 3 work for Lane 3 & 4 and outside shoulder replacement why is the Department showing Temporary K-Rail to be placed in areas that are shown to be Rapid Set Concrete Replacement areas? The following are the station ranges of locations that is Rapid Set Concrete and the THQ summary sheet shows Temporary K-Rail being placed: Riv 10- A 50-58, Riv 10-A 157-165, Riv 10-A 191- Riv 10-EN/FS 27+90, Riv 10- FN/FS 88-122, Riv 10 FN/FS 170+70-183+80, Riv 10-H 311-314, Riv 10-H 385-387+13. Riv 10-H 518-571? Also why is there no Temporary K-Rail shown for Stage 2 & 3 for Station Riv 10-H 387+13-400+69 which is a Pavement Section 1 JPCP area?
Inquiry submitted 12/10/2018

Response #1:submitted for consideration
Response posted 12/10/2018




Inquiry #31: PLAN SHEET CS-1 provide a quantity of 500 ea plastic drum's. In Plan Sheets TH-1 through TH-158 there are no callouts provided for Plastic Drums. Please provide drawings showing the locations for the Plastic Drums.
Inquiry submitted 12/11/2018

Response #1:submitted for consideration
Response posted 12/11/2018




Inquiry #32: PLAN SHEET TH-1 THROUGH TH-158 do not provide any temporary traffic striping within the traffic handling plans for stage 1. Please confirm it is the departments intent to not use temporary traffic striping during stage 1 construction. This work would then be performed under nightly lane closures utilizing traffic control devices.
Inquiry submitted 12/11/2018

Response #1:submitted for consideration
Response posted 12/11/2018




Inquiry #33: When will an addendum be coming to address the numerous anticipated plan changes per the previous bidder inquiries? The bid opening date needs to be pushed at least three weeks so we can properly address the numerous anticipated changes to the plans.
Inquiry submitted 12/12/2018

Response #1:submitted for consideration
Response posted 12/12/2018


Response #2:Addenda addressing bidders' inquiries are currently being prepared. Depending on the rate of responses generated, and on the time needed to incorporate the changes, a notification of bid opening delay may be issued in the coming weeks.
Response posted 12/12/2018




Inquiry #34: As part of your answer to inquiry number 33, a notification of bid delay may be issued in coming weeks. This is absolutely unacceptable! It will take hundreds of hours to put together accurate costing for a project of this magnitude. These plans are a absolute mess and I would believe there will be hundreds of changes to the layout and staging sheets. It is extremely difficult to work on the current plans. We will need at a minimum of five weeks to review the new plans and price out the project, basically the bid process will start over! To be fair we need a new bid date ASAP due to the upcoming holidays and extremely full bid schedule.
Inquiry submitted 12/12/2018

Response #1:submitted for consideration
Response posted 12/13/2018


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.