Inquiry #1: Please advise if there will be a scheduled pre-bid conference and/or site visit for project 07-325704.
Inquiry submitted 11/08/2018

Response #1:There is no scheduled pre-bid conference and/or site visit for this contract.
Response posted 11/09/2018




Inquiry #2: In light of the recent fires and continuing drought will Caltrans allow plastic pipe for Alternative Pipe Culvert.
Inquiry submitted 11/16/2018

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 11/16/2018




Inquiry #3: Is there any "Self Performance" requirement on this project ?.
Inquiry submitted 12/05/2018

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 12/05/2018




Inquiry #4: Please advise if an insulated fiberglass translucent sandwich panel system (as manufactured by Kalwall Corp.) is an acceptable product for the translucent roof panels/skylights shown on the equipment repair shop roof plan, per A1-07. There is no specification provided. Thank you in advance.
Inquiry submitted 12/06/2018

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 12/06/2018




Inquiry #5: Please confirm bids are to be submitted electronically through Bid Express. Notice to Bidders states both sealed envelopes to Santa Fe Springs location and electronic bids will be acceptable.
Inquiry submitted 12/06/2018

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 12/06/2018




Inquiry #6: Please confirm electronic submittals will be acceptable in lieu of hard copies.
Inquiry submitted 12/06/2018

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 12/06/2018




Inquiry #7: Good morning,

1.Is there any "pre-qualification" on this project?.
2.Is there any "Self Performance" required?.
Thank you.

Inquiry submitted 12/07/2018

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 12/07/2018




Inquiry #8: What are the minority goals and/or requirements specific to this project?
Inquiry submitted 12/10/2018

Response #1:As noted on the Notice to Bidders: The Department establishes no DVBE Contract goal for this contract but encourages bidders to obtain DVBE
participation.
Response posted 12/10/2018




Inquiry #9: Are there any commissioning requirements required on this project?
Inquiry submitted 12/11/2018

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 12/14/2018




Inquiry #10: Per Section 80 - Security Metal Fences and Gates, we are required to submit a manufacturer's standard 10-year warranty for factory finish. Can you please give us a list of your approved manufacturer for the said Security Metal Fences and Gates. Thanks
Inquiry submitted 12/12/2018

Response #1:Your inquiry has been received and is being reviewed. Thank You for your patience.
Response posted 12/14/2018




Inquiry #11: Please confirm the liquidated damages on this specific project. The standard specs don't appear to be for projects in this capacity.
Inquiry submitted 12/14/2018

Response #1:The Liquidated Damages for all projects can be found in Section 8-1.10, "Liquidated Damages," of the 2015 Standard Specifications.
Response posted 12/14/2018


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.