Inquiry #1: Q1. The Traffic Handling Plan allows the contractor to close the 5 NB Colorado st Fwy off ramp fully and the spec doesn't specify how many days the ramp can be closed for. Please advise.
Inquiry submitted 03/13/2018

Response #1:Per the contract special provisions, page 14,You may close the Colorado St off-ramp from northbound Rte 5 for widening of the off-ramp for an extended period of time by implementing the Motorist Information Plans. Per the contract special provisions, page 1,Complete the work, excluding plant establishment work, within 120 working days.
Response posted 03/14/2018

The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.

Contracting Information

Statewide Alerts and Other Information