Inquiry #1: What are the subgrade compaction requirements for the gore areas?
Inquiry submitted 12/04/2018

Response #1:Submitted for consideration.
Response posted 12/04/2018


Response #2:Please refer to section 73-1.03B Subgrade Preparation of the Standard Specifications and RSS for the subgrade requirements for the Minor Concrete (Textured Paving) in the gore areas.
Response posted 12/10/2018




Inquiry #2: Does Sign S8-5 on sheet 82 of 157 required a walkway?
Inquiry submitted 12/06/2018

Response #1:Submitted for consideration.
Response posted 12/07/2018


Response #2:No, a walkway is not required for sign S8-5.
Response posted 12/10/2018




Inquiry #3: What are the subgrade compaction requirements under the slope paving?
Inquiry submitted 12/12/2018

Response #1:Submitted for consideration.
Response posted 12/13/2018


Response #2:Requirements for slope paving, including the requirements for earthwork and foundation preparation, can be found in Section 72 of the specifications. Specifically, please refer to paragraph 1 of section 72-1.03 and paragraph 4 of section 72-11.01C(1) of the Standard Specifications.
Response posted 12/13/2018




Inquiry #4: Would an integral color be accepted in lieu of the color hardener for the slope paving areas?
Inquiry submitted 12/12/2018

Response #1:Submitted for consideration.
Response posted 12/13/2018


Response #2:The requirements for coloring the slope paving are included in section 72-11.01B of the Special Provisions. Please bid per the current contract documents.
Response posted 12/13/2018




Inquiry #5: 130 working days for the reconstruction of 33 gores with curb and HMA and 16 slope paving locations with concrete barrier and vegetation control is not adequate. This equates to less than three days per gore/slope paving location. Please consider adding additional working days to the contract time.
Inquiry submitted 12/13/2018

Response #1:Submitted for consideration.
Response posted 12/13/2018


Response #2:Bid per current contract documents.
Response posted 12/14/2018




Inquiry #6: Will directional boring be allowed in place of the jacked welded steel pipe?
Inquiry submitted 12/14/2018

Response #1:Submitted for consideration.
Response posted 12/14/2018


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.