Bidder Inquiries

Sign In | Create Account

Viewing inquiries for 06-0S3404

Submit new inquiry for this project


Inquiry #1: Where is the removal of the existing Concrete median located on Highway 198 and Road 180 to be paid, as the quantity sheets do not appear to address it in either of the concrete removal items or the Roadway Ex quantities shown in the summary of quantities sheets.

Inquiry submitted 09/19/2017

Response #1:
Submitted for consideration.
Response posted 09/19/2017


Response #2:
The removal of the existing concrete median located on Highway 198 at Road 180 is included in the quantity of roadway excavation and is paid for as such. This quantity is shown in the ‘Roadway Quantities’ table on sheet Q-4 under the row for ‘Sta 322+11.00 to Sta 335+70.00, Median Left Turn Pockets’.
Response posted 09/29/2017




Inquiry #2: In stage 1 Phase 1 the contractor is to widen the outside shoulder of the existing East bound lanes near station 220+00 to near 419+00. The stage construction and traffic handling plans do not show any K-Rail being placed on the outside shoulder in order to complete this work. The typical cross sections for this area show Road Ex, AB and HMA to be placed. This will require more than a 12 hour closure window in order to complete. Will the state please add in the required quantity of K-rail to do this work.
Inquiry submitted 09/22/2017

Response #1:
Submitted for consideration.
Response posted 09/22/2017


Response #2:
Bid per current contract documents.
Response posted 09/22/2017




Inquiry #3: Will the state please provide a typical cross section for the area between STA 420+55.09- STA 435+47.35, as it is currently not provided, and upon a site visit it appears that it includes a paved median.
Inquiry submitted 09/27/2017

Response #1:
Submitted for consideration.
Response posted 09/27/2017




Inquiry #4: Based on the detail shown on sheet C-7 it looks as though the contractor is to remove material outside of the existing pavement structural section in order to place shoulder backing. On sheet Q4, Summary of quantities, no grading work is shown to be done from Sta 58+14-STA 475+58, which is contradictory to the amount of shoulder backing required in this area. Which would require excavation according to sheet C-7. Will the state please provide additional Road Ex quantity for this work or revise the detail on sheet C-7?
Inquiry submitted 09/28/2017

Response #1:
Submitted for consideration.
Response posted 09/29/2017




Inquiry #5: On the reconstruct of DBL Thrie Beam and Single Thrie Beam, will contractor be able to re-use the posts if good shape, or is it just reconstructing the rail with new post?
Inquiry submitted 10/05/2017

Response #1:
Submitted for consideration.
Response posted 10/05/2017


Response #2:
Per section 15-1.03A of the Standard Specifications, replacing existing posts with new posts is only required if the Engineer determines the existing post is unsuitable for reuse.
Response posted 10/16/2017




Inquiry #6: How does the State plan to pay for the corrective grinding needed to bring the existing asphalt's localized roughness below the required 180 in/mi? The State needs to specify where the Prepaving Grinding Days, stated in 39-2.01C(3)(e), will be paid.
Inquiry submitted 10/10/2017

Response #1:
Submitted for consideration.
Response posted 10/10/2017


Response #2:
Per Section 39-2.01C(3)(e), the section only applies to existing asphalt concrete surfaces that will not be cold planed or milled. The project does not have any such areas. Bid per current contract documents.
Response posted 10/16/2017


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.