Viewing inquiries for 05-1H6704

Submit new inquiry for this project


Inquiry #1: There appears to be a contrast treatment on the bridge decks, how will the removal of this be payed for?
Inquiry submitted 01/19/2018

Response #1:Section 60-3.02C(7) of the project special provisions indicate removal of existing slurry or chip seal to be handled by change order.
Response posted 01/22/2018


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.