Viewing inquiries for 04-3G2104

Submit new inquiry for this project


Inquiry #1: Accessible Pedestrian Signals (APS) are included in the Specs (see page 26), but the Plans call our relocating the existing Pedestrian Push Buttons (PPB) per Note 1 on Plan Sheet E-1. Are new APS required for this job?
Inquiry submitted 10/01/2017

Response #1:Submitted for consideration.
Response posted 10/02/2017


Response #2:No. No new APSs are required for this job.
Response posted 10/02/2017




Inquiry #2: How will the pre & post survey paid for?
Inquiry submitted 10/09/2017

Response #1:Submitted for consideration.
Response posted 10/09/2017


Response #2:There are no "Pre & Post Construction Surveys" on this project.

The added SSP is not applicable.

Response posted 10/10/2017




Inquiry #3: Does bid item #30 - Remove Concrete Curb cover all the concrete demolition on the project or just the curb demolition?
Inquiry submitted 10/09/2017

Response #1:Submitted for consideration.
Response posted 10/09/2017


Response #2:Yes, it covers all concrete demolition on the project.
Response posted 10/10/2017


The information provided in the responses to bidder inquiries is not a waiver of Section 2-1.07, "JOB SITE AND DOCUMENT EXAMINATION" of the Standard Specifications or any other provision of the contract, nor to excuse the contractor from full compliance with the contract. Bidders are cautioned that subsequent responses or contract addenda may change a previous response.